Horizontal Drilling

       Why Drill Horizontal Wells?

Relative Production Rates Relative Costs Types of Horizontal Wells Drilling Problems & Solutions How Popular is Horizontal Drilling?

Examples

2

3

Why Drill Horizontal Wells?

 Increase Reserves  Increase Production Rates  Control Water Production  Control Gas Production

4

Why Drill Horizontal Wells?

 Control Sand Production  Produce From Thin Reservoirs  Connect Vertical Fractures  Produce Methane from Coal Seams  Increase Injectivity (steam, water, polymers, etc.)

5

6

7

8

9

10

Vertical Well B/D

Production Rates Oryx - Austin Chalk

Horizontal Well B/D Horizontal/Vertical Production Ratio 12 507 42 15 215 14 5 107 21

11

Production Rates

Drilled 7 wells from 1986 to 1989.

Drilled ~ 85 wells in 1990 Vertical Well Drilling Cost: 235 $/ft Horizontal Well Drilling Cost: 520-282 $/ft Cost Ratio: 2.2-1.2

12

Drilling Costs Austin Chalk (1993)

Vertical well ~ $500,000 Recompletion as Horizontal Well ~ $375,000 New Horizontal Well ~ $1,000,000-2,000,000 ~ $100+/ft to $150/ft {these numbers are rough estimates only}

13

Rospo Mare - Italy 14

Prudhoe Bay

Vertical Well: Horizontal Well: Production Ratio: Vertical Well: Horizontal Well: Cost Ratio: 3000 - 4000 B/D 10,000 - 12,000 B/D 3 - 4 235 $/ft 520 - 282 $/ft 2.2-1.2

15

Long Radius (~1,000-3,000 ft) {~2-6 deg/100 ft} Medium Radius (140~700 ft) {~8-40 deg/100 ft} Short Radius (~20-40 ft) {~1.5-3 deg/ft} <1,000 ft ~5,000 ft ~8,000 ft 16

New Drilling Technology

Measurement While Drilling (MWD) Directional Surverying and Control Indentification of Markers (identify zones) Top Drive Drill with 90-ft stands instead of 30-ft joints Circulate while pulling drillpipe out of hole Rotate drillpipe while pulling out of hole

17

New Drilling Technology

Mud Motors Drill without rotating pipe Change hole direction while drilling Steerable systems

18

19

Potential Problems in Horizontal Drilling

• Running equipment in and out of hole • drillstring, casing, cables • Preventing/Remedying differential sticking • Excessive torque

20

Potential Problems in Horizontal Drilling

• Cleaning the hole and preventing cuttings from settling along the hole bottom • Controlling weight on bit to achieve and maintain directional control • Cementing casing or liner

21

Summary

• Horizontal wells may produce at 3-5 times the rate of vertical wells in the same area (… as much as 20 times higher in special cases).

• Horizontal wells typically cost 1.5-3 times as much as vertical wells in the same area.

• Horizontal wells are often very attractive in formations with extensive vertical fractures.

22

Summary

• The use of horizontal wells has been growing - worldwide.

• Horizontal wells has increased our recoverable reserves.

• In the U.S. one rig in ten is drilling horizontal wells. (1994) (1998) • Today ~ one rig in fifteen is drilling horizontal wells. (2002)

23

24

25

Long - Radius Wells

• Used for achieving large horizontal displacements from platforms or drilling pads • Used for achieving very long horizontal sections (to 6,000 ft +) Build Rate: ~ 2-6 degrees/100 ft Build Radius: ~ 1,000-3,000 ft Length of Horiz. Section: 1,000 - 8,000 ft (1995)

26

Method:

• Use conventional directional drilling technology • Use rigid bottom hole assemblies, motors & bent subs, stabilizers • or Use Navigation drilling systems with “steerable” drilling motors

27

Medium - Radius Wells

Build Rate: ~ 8 - 20 degrees/100 ft (up to 40 deg/100 ft in some cases) Build Radius: ~ 300 - 700 ft Length of Horiz. Section: 1,000-6,000 ft

28

Method:

• Use modified long-radius drilling technology • Use different motors for

Angle Build Angle Hold

sections.

and • Use a

“Tangent Section”

between the two build sections • Use compressive service drillpipe through the curve if Build Rate > 15 deg./100 ft .

(CS drillpipe has integral wear knots every ~ 10 ft )

29

Short-Radius Wells

Build Rate: ~ 1 - 3 degrees/ft Build Radius: ~ 20 - 40 ft Length of Horiz. Section: 200 - 1,000 ft

30

Method:

 Two downhole motor designs are available  Drill vertical “rathole” to identify horizon  Build angle with special curve-drilling assembly with a non-rotating shell that gives curvature to the tool  After building angle to horizontal, use a special angle-hold assembly: this consists of two undergauge stabilizers behind the bit, and flexible drillpipe.

31

32

Horizontal Well Pair

33

Horizontal Well Pair

34

Vertical Injection Wells and Horizontal Production Well

35