1

PJM Transmission Owners

Legend ZONE

4/27/2020 ©2006 PJM www.pjm.com

2

PJM RTO After Market Integrations • • • • •

PJM - Full Service RTO

Control Area Operator Transmission Provider Market Administrator Regional Transmission Planner NERC Reliability Coordinator

4/27/2020 ©2006 PJM

PJM RTO Generating Units Generation Capacity Peak Load Annual Energy Area (Square Miles) Miles of Transmission 1,082 163,806 MW 133,763 MW 700 million MWh 164,260 56,070 Population Served States (+ D.C.) Members Transmission Customers 51 Million 13 states + D.C.

350+ 100+

www.pjm.com

3

PJM - Backbone Transmission Systems

4/27/2020 ©2006 PJM www.pjm.com

4

Options for Energy Supply

Bilateral Transactions Self-schedule own resources PJM Spot Market Load Serving Entities Obtain energy to serve customers

4/27/2020

Industrial

©2006 PJM

Commercial Residential

www.pjm.com

5

Spot Market Volume (2005)

4/27/2020 ©2006 PJM www.pjm.com

6

Security Constrained Re-Dispatch

Control Area Constrained System Low Cost Generator $$

Transmission “Bottleneck” or Constraint 4/27/2020 ©2006 PJM

High Cost Generator $$$$ Higher cost Generator more advantageously located relative to transmission system limit

www.pjm.com

7

Power Generated Power Imported Demand

Achieving Energy Balance

Power Exported Losses Daily Load Curve 26 24 MW 22 20 18 3

4/27/2020

6 9 12 Hour 15 18 21 24

©2006 PJM

Frequency in Hz

60 www.pjm.com

8

Interchange Trends 4/27/2020 ©2006 PJM www.pjm.com

9

Interchange Trends 4/27/2020 ©2006 PJM www.pjm.com

10

Proposed AEP 765 kV Line 4/27/2020 ©2006 PJM www.pjm.com

11

Proposed AEP 765 kV Line • Timeline: 8 years to complete (2014) • AEP terminus of 3 765 kV connections and 8000 mw of generation • Low impedance of 765 kV network makes geographically distant generation sources “close” Benefits: 1) midwest to east transfer capability improvement of 5,000mw 2) reduction of transmission losses by 280 mw during peak loading 3) spawn transmission investment by incumbents that will integrate 4/27/2020 ©2006 PJM www.pjm.com

12

Proposed AP 500 kV Line 4/27/2020 ©2006 PJM www.pjm.com

13

Proposed AP 500 kV Line Trans-Allegheny Interstate Line 500 kV Transmission Line across the Allegheny Power service territory • Proposed Length: 330 miles •Total Cost: $1.4 Billion • Benefits: 1) Improve reliability of transmission infrastructure 2) Allow cost-efficient generation to reach more consumers 3) Increase west-to-east transfer by 3,800 mw 4) Reduce congestion and address system stability ©2006 PJM www.pjm.com

4/27/2020 14

Status: Under Construction

Neptune HVDC

4/27/2020 ©2006 PJM www.pjm.com

15

Neptune HVDC

4/27/2020 ©2006 PJM www.pjm.com