Transcript Slide 1

Southeastern Region
Transmission Planning
2009 SERTP
Economic Studies
2009 SERTP
Economic Planning Studies
2009 SERTP
Five Economic Planning Studies
 North Georgia to FRCC
• 650 MW
 SCE&G to Georgia
• 1000 MW
 Gulfport, MS to Georgia
• 1000 MW
 Washington County, GA to Georgia
• 5000 MW
 Savannah, GA to Southern Balancing Authority
• 400 MW Summer Peak
• 1000 MW Off Peak
2009 SERTP
Power Flow Cases Utilized
 Study year: 2014
 Load Flow Cases:
• 2009 Series Version 2A
• Summer Peak with 2250 MW Interchange
to FRCC, 3600 MW to FRCC, and
Shoulder
2009 SERTP
Five Economic Planning Studies
 Final Report Components:
• Thermal Analysis
• DC contingency analysis to attain
monitored/contingency pairs with Siemens
PSS MUST
• AC verified with Siemens PTI PSS/E
• Interface Transfer Capability Impacts
• Stability Impacts
• Potential Solutions
• Transmission Projects and Cost Estimates
2009 SERTP
• The following information does not represent a
commitment to proceed with the recommended
enhancements nor implies that the
recommended enhancements could be
implemented by the study date of 2014.
• These potential solutions only address
constraints identified within the Southern
Balancing Area that are associated with the
proposed transfers. Other Balancing Areas were
not monitored which could result in additional
limitations and required system enhancements.
North Georgia
to
FRCC
650 MW
North Georgia to FRCC: 650 MW
• Transfer Type: Generation to Load
• Source: 500 kV, Murray County, GA
• Sink: 650 MW of FRCC load scaled up
• 488 MW Florida Power & Light
• 162 MW Progress Energy Florida
Source
Sink
North Georgia to FRCC: 650 MW
• Transfer Type: Generation to Load
• Source: 500 kV, Murray County, GA
• Sink: 650 MW of FRCC load scaled up
• 488 MW Florida Power & Light
• 162 MW Progress Energy Florida
650 MW
North Georgia to FRCC: 650 MW
Transmission System Impacts
 Thermal Constraints Identified:
• One (1) 500kV Line
• One (1) 230 kV Line
• Six (6) 115 kV Lines
 Interface Constraints Identified:
• One (1) 500 / 230 kV Transformer
• One (1) 230 kV Line
 Stability Constraints Identified:
• None Identified
Thermal Constraints
Interface Constraints
Interface Constraints
North Georgia to FRCC: 650 MW
Transmission Project Estimates
Item
Potential Project
Cost
P1
North Americus – North Tifton 115 kV TL
$1,350,000
P2
Douglas – Kettle Creek 115 kV TL
$900,000
P3
Thalmann – Duval 500 kV TL
N/A1
P4
Lloyd Shoals – South Griffin 115 kV TL
$500,000
P5
Barneyville – Pine Grove 115 kV TL
$250,000
P6
Mitchell – Moultrie 115 kV TL
$3,000,000
P7
Jasper – Pine Grove 115 kV TL
$11,000,000
I1
North Tifton 500 / 230 kV Substation
$36,000,000
I2
Woodstock 230 kV Substation
$100,000
Total Cost: $53,100,000
1
Limiting element is within FRCC
Potential Enhancements
P2
P1
P6
P5
P7
Potential Enhancements
I1
Potential Enhancements
I2
SCE&G
to
Georgia
1000 MW
SCE&G to Georgia:
1000 MW
• Transfer Type: Load to Generation
• Source: SCE&G Load
• Sink: Georgia Generation
Source
Sink
SCE&G to Georgia:
1000 MW
Transmission System Impacts
 Thermal Constraints Identified:
• One (1) 230 / 115 kV Transformer
• One (1) 115 kV Line
 Interface Constraints Identified:
•
•
•
•
One (1) 500 / 230 kV Transformer
Two (2) 230 kV Lines
One (1) 230 / 115 kV Transformer
Four (4) 115 kV Lines
 Stability Constraints Identified:
• None Identified
Thermal Constraints
CENTER
Interface Constraints
SCE&G to Georgia:
1000 MW
Transmission Project Estimates
Item
Potential Project
Cost
P1
Avalon Junction – Bio 115 kV TL
$3,800,000
P2
Gainesville #2 115 kV Substation
$200,000
I1
Athena – Hartwell 230 kV TL
$44,000,000
I2
Center Primary 230 kV Substation
Athena 230 kV Substation
Total Cost: $48,300,000
$300,000
SCE&G to Georgia:
1000 MW
Transmission Project Estimates
Item
Potential Project
Cost
P1
Avalon Junction – Bio 115 kV TL
$3,800,000
P2
Gainesville #2 115 kV Substation
$200,000
I1
Athena – Hartwell 230 kV TL1
$44,000,000
I2
Center Primary 230 kV Substation
Athena 230 kV Substation
Total Cost: $44,500,000
1Project
I1 alleviates the need for Project P1
$300,000
Potential Enhancements
P2
P1
CENTER
Potential Enhancements
P2
I2
P1
I1
Gulfport, MS
to
Georgia
1000 MW
Gulfport, MS to Georgia:
1000 MW
• Transfer Type: Generation to Generation
• Source: 500 kV, Harrison County, MS
• Sink: Georgia Generation
Source
Sink
Gulfport, MS to Georgia:
1000 MW
• Transfer Type: Generation to Generation
• Source: 500 kV, Harrison County, MS
• Sink: Georgia Generation
1000 MW
Stability Enhancements
P1
Gulfport, MS to Georgia:
1000 MW
Transmission System Impacts
 Thermal Constraints Identified1:
• Six (6) 230 kV Lines
• Nine (9) 115 kV Lines
 Interface Constraints Identified2:
• Two (2) 230 kV Lines
1
2
Constraints remaining after implementing stability
enhancement
Constraints remaining after implementing all
thermal enhancements
Gulfport, MS to Georgia:
1000 MW
Transmission System Impacts Continued
 Stability Constraints Identified:
• With the additional transfer of 1000 MW
from Gulfport, MS to the Georgia ITS, a
fault on the Daniel – McKnight 500 kV
transmission line could result in all of the
units within the local area to pull out of
synchronism with the rest of the Eastern
Interconnect.
Constraints After
Stability Enhancements
Constraints After
Stability Enhancements
Interface Constraints
Interface Constraints
Gulfport, MS to Georgia:
1000 MW
Transmission Project Estimates
Item
Potential Project
Cost
P1
Daniel – Snowdoun 500 kV TL
$340,000,000
P2
Daniel – Bennett 230 kV TL
$23,000,000
P3
Barry - Crist 230 kV TL
$2,200,000
P4
South Montgomery – Union Spring 115 kV TL
$3,500,000
P5
Pike County – Snowdoun 230 kV TL
$18,300,000
P6
Farley – South Bainbridge 230 kV TL
$2,500,000
P7
Anniston – Bynum 230 kV TL
$10,000,000
P8
Bull Creek – Victory Drive 115 kV TL
$2,500,000
P9
Crooked Creek – Martin Dam 115 kV TL
$8,500,000
P10
Madison Park – Thurlow Dam 115 kV TL
$750,000
…
…Continued…
…
Gulfport, MS to Georgia:
1000 MW
Transmission Project Estimates
Item
Potential Project
Cost
…
...Continued…
….
P11
South Bainbridge 230 kV Substation
$20,000,000
P12
Bainbridge Area 115 kV Network
Enhancements
$5,000,000
I1
Bennett – North Theodore 230 kV TL
$760,000
I2
Goat Rock – Fortson 230 kV TL
$20,000,000
Total Cost: $457,010,000
Potential Enhancements
P9
P8
P10
P4
P5
P1
P2
P3
I1
P12
P6
P11
Potential Enhancements
I2
Washington County
to
Georgia
5000 MW
Washington Co. to Georgia:
5000 MW
• Transfer Type: Generation to Generation
• Source: Washington County, GA
• Sink: Georgia Generation
Source
Sink
Washington Co. to Georgia:
5000 MW
• Transfer Type: Generation to Generation
• Source: Washington County, GA
• Sink: Georgia Generation
5000 MW
Washington Co. to Georgia:
5000 MW
Transmission System Impacts
 Thermal Constraints Identified:
•
•
•
•
•
Ten (10) 500 kV Lines
Four (4) 500 / 230 kV Transformers
Thirty (30) 230 kV Lines
Six (6) 230kV / 115 kV Transformers
Twenty-three (23) 115 kV Lines
 Interface Constraints Identified:
• Three (3) 230 kV Lines
 Stability Constraints Identified:
• None Identified
Thermal Constraints
Potential Enhancements (P1)
P1
Thermal Constraints After P1
Potential Enhancements (P1
through P3)
P2
P3
P1
Thermal Constraints After P3
Interface Constraints
Interface Constraints
Washington Co. to Georgia:
5000 MW
Transmission Project Estimates
Item
Potential Project
Cost
1 Yr. Advancement of Bethabara 230 /
115 kV Project from 2015
$3,200,000
1 Yr. Advancement of East Walton 500
/ 230 kV Project from 2015
$13,300,000
P2
East Walton – South Hall 500 kV TL
$54,500,000
P3
Rockville – ECO2 500 kV TL
$81,700,000
P4
3 Yr. Advancement of the Middlefork –
Thomson 500 kV TL
$47,300,000
P5
Wilson 230 kV Substation
$300,000
P6
Vogtle 500 / 230 kV Substation
$35,300,000
P7
Waynesboro 230 / 115 kV Substation
$50,000
P8
Jesup – Ludowici Primary 115 kV TL
$1,750,000
…
…Continued…
…
P1
Washington Co. to Georgia:
5000 MW
Transmission Project Estimates
Item
Potential Project
Cost
…
…Continued…
…
I1
Wadley Primary – Waynesboro Primary
230 kV TL
$500,000
I2
Dum Jon – Goshen 230 kV TL
$500,000
I3
Goat Rock – Fortson 230 kV TL
$20,000,000
Total Cost: $258,400,000
Potential Enhancements
(P1 through P8)
P2
P4
P6
P3
P1
P5
P7
Potential Enhancements
I2
I1
Potential Enhancements
I3
Savannah, GA
to
Southern Balancing
Authority
400 MW – Summer Peak
1000 MW – Off Peak
Savannah, GA to Southern
Balancing Authority
• Transfer Type: Generation to Generation
• Source: Savannah, GA
• Sink: Southern Balancing Authority
Source
Sink
Savannah, GA to Southern
Balancing Authority
• Transfer Type: Generation to Generation
• Source: Savannah, GA
• Sink: Southern Balancing Authority
400 MW Summer
1000 MW Off Peak
Savannah, GA to SBA
400 MW Summer Peak
Transmission System Impacts
 Constraints Identified:
• Two (2) 230kV Lines
• One (1) 115kV Line
 Interface Constraints Identified:
• None Identified
 Stability Constraints Identified:
• None Identified
Thermal Constraints
Savannah, GA to SBA
400 MW Summer Peak
Transmission Project Estimates
Item
P1
P2
Potential Project
Cost
1 Yr. Advancement of the
Bethabara 230/115kV Project
from 2015
$3,200,000
1 Yr. Advancement of the East
Walton 500/230 kV Project from
2015
$13,300,000
Athena – Union Point 115kV TL
$11,300,000
Total Cost: $27,800,000
Potential Enhancements
P2
P1
Savannah, GA to SBA
1000 MW Off Peak
Transmission System Impacts
 Thermal Constraints Identified:
• One (1) 115kV Line
 Interface Constraints Identified:
• None Identified
 Stability Constraints Identified:
• None Identified
Thermal Constraints
Savannah, GA to SBA
1000 MW Off Peak
Transmission Project Estimates
Item
Potential Project
Cost
P1
McIntosh – Yemassee 115kV TL
$675,000
Total Cost: $675,000
Potential Enhancements
P1
2009 SERTP
Project Cost Summary
 North Georgia to FRCC
• $53,100,000
 SCE&G to Georgia
• $44,500,000
 Gulfport, MS to Georgia
• $457,010,000
 Washington County to Georgia
• $258,400,000
 Savannah, GA to Southern Balancing Authority
• $28,475,000
• $27,800,000 for Summer Peak
• $675,000 for Off Peak
Questions?