Transcript Slide 1

Supporting people with a learning disability
Introduction to Project
Management
Presenter: Steve Raw FInstLM,
FCMI
Welcome
Who am I?
•
•
•
•
Background
My current role
Qualifications
Example of Projects
Attendee Introductions
Please explain:
• Your current Position
• Background in Project Management
• Current Project/Projects
• Any Special Expectations from today
• Something about yourself
What is the difference?
Between
a project
and
day to day work
What is a Project?
• An effort or temporary endeavour with a
specific objective
• Most frequently it is a one-off/unique
effort
• It has a specific start and end dates
• It can be divided into project phases
• Progressively elaborated
Another Project Definition
A project is a temporary endeavour involving
a connected sequence of activities and a
range of resources, which is designed to
achieve a specific and unique outcome,
which operates within time, cost and quality
constraints and which is often used to
introduce change
Lake (1997)
Types of Projects
There are broadly two types of work-based project you can
carry out:
1.
A consultation project – here you analyse a problem,
situation, challenge or opportunity related to your work,
draw conclusions and recommend appropriate solutions,
explaining how your solutions could be implemented.
2.
A change project – where you identify improvements to
processes for which you have responsibility, and then
implement appropriate changes to bring about particular
benefits, such as cost savings or better customer service
to the people we support
Project Life Cycle – Prince 2
1.
5 Stages
Initiation – what is the vision?
2.
Planning – how will the vision be achieved, by
whom, by when and at what cost?
3.
Implementation – doing it!
4.
Monitoring and review – how well are you
doing it?
5
Project closure and evaluation – the vision
made real, accepted, signed off and
evaluated.
What are the benefits of Project
Management?












Can be used for all types of products
Manage by stages
Focus on products
A disciplined approach to introducing change
Use a common language
Recognises the roles and responsibilities in the
introduction of change
Is time specific
Focus on the business case and strategic objectives of
the organisation
Stakeholder involvement
Promotes learning
Monitors risk
Stage Boundaries
Work Breakdown Structure and
Task Definition
The Work Breakdown Structure (WBS) is the
document that translates your objectives into a list
of specific and concrete activities or tasks – the
project menu.
• Ensure that every aspect of the project has been
covered adequately and that there are no gaps
• Enable detailed resource planning
• Allocate responsibilities for tasks to specific
individuals or groups
What is a Gantt Chart?
• A Gantt chart, in its simplest form, consists of 2
elements: task and time.
• Tasks can be specified as individual pieces of work
• Time will normally be broken down into periods of weeks
or months
• They have an immediate impact. They are a powerful
way of showing the length of time that different activities
are expected to take, and which activities will be running
at the same time.
• Are there time overlaps in project activities that will put a
strain on resources?
Carrying out a Forcefield Analysis
Task
For the project you chose
• Identify the driving forces that are working
for your project
• Identify the forces that are working against
your project – these are the resisting
forces
• Score them on the basis of +1 or -1 for a
weak force to +5 or -5 for a strong force
Estimating Using Ranges
• A single figure estimate is almost certain to be
wrong. It is better to determine a “most likely”
figure and then to estimate the smallest and
largest figure for each task.
• Estimates showing a wide range, or spread,
between the smallest and largest figure indicate
estimates with a large degree of uncertainty
• These tasks can be targeted to see if the
uncertainty can be reduced in any way. For
example, the task may be too large and should
be broken down further.
Estimating Time and Resources
Common Problems in Estimating
• Attitude that projects “always overrun”
• Acceptance by Managers of poor estimating
• Not allowing enough time
• Estimating for too large a task
• Fear of committing to a time
• Estimates can become a self fulfilling prophesy!
(Parkinson’s Law…..”Work expands to fill the time
available.”)
Assigning Resources
• The Manager’s job is to make the best fit
between the available resources and the project
tasks
• When assigning staff consider:
- Availability
- Level of experience
- Productivity
- Past Track Record
Risk Definition
A risk is an uncertain event or set of events
that should it occur will have an effect on the
achievement of objectives.
It consists of a combination of the
probability of a perceived threat or
opportunity occurring, and the magnitude
of its impact on objectives
What is Risk Management
• Provides a disciplined environment for proactive
decision-making
• Identifies and describes risks
• Assess likelihood and impact
• Control through responses, monitoring and
reporting
• Applied to strategic, operational, programme
and project perspectives
Identify and manage potential risks in
relation to the project
• To reduce the risks inherent in a project, you need first to
identify their source. Possible sources of risk include
timing, technology, people, finance, managerial and
political.
• To help you to identify and respond to risk, ask:
What can go wrong here?
How likely is this?
What impact would it have?
What can be done to avoid to mitigate this?
Project Closure
•
•
•
•
Ensure all outstanding items are in place
Finish the documentation!
Formally close down the project account
Learning log
DON’T FORGET A TEAM CELEBRATION
It’s good for psychological closure after a good
team effort
Finishing the project