In which phase are the specifications
produced?
Construction
Design Phase- Schematic
Design Phase- Construction Documents
Planning Phase
1.
a.
b.
c.
d.
In which phase are the specifications
produced?
Construction
Design Phase- Schematic
Design Phase- Construction Documents
Planning Phase
2.
a.
b.
c.
d.
Whose responsibility is it to produce the
shop drawings?
The Architect/Engineer
The Contractor
The Owner
The Sub-Contractor
2.
a.
b.
c.
d.
Whose responsibility is it to produce the
shop drawings?
The Architect/Engineer
The Contractor
The Owner
The Sub-Contractor
3.
Which phase fixes and describes the size
and character of the entire project?
a. Design Phase- Schematic
b. Design Phase- Construction Documents
Phase
c. Bidding/Contract Negotiation Phase
d. Design Phase – Design Development
Phase
3.
Which phase fixes and describes the size
and character of the entire project?
a. Design Phase- Schematic
b. Design Phase- Construction Documents
Phase
c. Bidding/Contract Negotiation Phase
d. Design Phase – Design Development
Phase
4.
The Construction Phase begins…
a. When the first clod of earth is moved by
a bulldozer
b. When the surveyor measures the site
c. When the bids are received
d. When the agreement is executed
4.
The Construction Phase begins…
a. When the first clod of earth is moved by
a bulldozer
b. When the surveyor measures the site
c. When the bids are received
d. When the agreement is executed
5.
What activities take place in the
planning/pre-design phase?
a. The engineers develop the mechanical
and electrical systems
b. The site is selected and the demolition is
done
c. Feasibility studies and budget is set
d. The program is evaluated and the
engineers are selected
5.
What activities take place in the
planning/pre-design phase?
a. The engineers develop the mechanical
and electrical systems
b. The site is selected and the demolition is
done
c. Feasibility studies and budget is set
d. The program is evaluated and the
engineers are selected
6.
During which project phase does the A/E review
the owner’s program and budget requirements and
suggest alternative approaches?
a.
b.
c.
d.
e.
Planning/Pre-Design
Design
Bidding/Contract Negotiation
Construction
Post Construction
6.
During which project phase does the A/E review
the owner’s program and budget requirements and
suggest alternative approaches?
a.
b.
c.
d.
e.
Planning/Pre-Design
Design
Bidding/Contract Negotiation
Construction
Post Construction
7.
During the Planning/Pre-Design Phase,
the A/E may be retained to:
a. Develop outline specifications
b. Describe the character of the mechanical
system
c. Prepare renderings
d. Assist in financial feasibility studies
7.
During the Planning/Pre-Design Phase,
the A/E may be retained to:
a. Develop outline specifications
b. Describe the character of the mechanical
system
c. Prepare renderings
d. Assist in financial feasibility studies
8.
a.
b.
c.
d.
e.
A project’s “life cycle” includes all of the
following EXCEPT:
Planning
Financing
Construction
Evaluation
Demolition
8.
a.
b.
c.
d.
e.
A project’s “life cycle” includes all of the
following EXCEPT:
Planning
Financing
Construction
Evaluation
Demolition
9.
a.
b.
c.
d.
The Design Phase includes all of the
following EXCEPT:
Surveys
Design Development
Schematic Design
Bid Security
9.
a.
b.
c.
d.
The Design Phase includes all of the
following EXCEPT:
Construction Document Phase
Design Development Phase
Schematic Design Phase
Bid Security
10.
The specification type document prepared
during the Design Development phase is called the:
a. Outline Specification
b. Rough Draft Specification
c. UniFormat Elements
10.
The specification type document prepared
during the Design Development phase is called the:
a. Outline Specification
b. Rough Draft Specification
c. UniFormat Elements
Answers
1. C
2. B
3. D
4. D
5. C
6. B
7. D
8. B
9. D
10. A