Construction Project Bankruptcy Strategic Considerations
Download
Report
Transcript Construction Project Bankruptcy Strategic Considerations
Construction Project Bankruptcy
Strategic Considerations for Owners, General
Contractors and Construction Managers
December 16, 2008
Presenters
Charles A. Dale, Boston
office, focuses his practice
on matters of bankruptcy
and insolvency with
extensive experience in
the construction industry.
Joseph B.C. Kluttz, Charlotte
office, focuses on the
structuring and restructuring of
large financial transactions
within construction and other
industries to avoid and manage
insolvency risk.
Brian R. Davidson,
Pittsburgh office, focuses in
the area of complex
commercial litigation with an
emphasis on construction
industry litigation.
Andrew L. Swope, Harrisburg
office, focuses in the area of
complex commercial litigation
with an emphasis in
commercial, construction and
bankruptcy law.
1
State of the Industry
“McGraw-Hill Construction (of which ENR is part) is forecasting a 7.4% decline
in construction starts in 2009, following declines of 12.4% this year and 8.0%
in 2007.” — All Sectors Go Negative Next Year As A Real Recession Rattles
Markets, by Tim Grogan and Steve Setzer, ENR.com, 11/12/08
“Litigation is cropping up across the country over … building developments
that unraveled as U.S. financing tightened … , leaving financiers, developers
and contractors to fight over who should pay for the failed deals.” — As
Building Projects Collapse, Suits Pile Up, by Lynne Marek, The National Law
Journal, 11/3/08
“The U.K.'s 82 billion-pound building industry, accounting for about 5% of the
economy, has ground to a halt, with little work being booked because of
faltering demand and a credit freeze.” — Builders Hold $1.7 Billion Payments
in Recession Sign, by Tim Barwell, Bloomberg.com, 10/17/08
2
3
Basic Facts
200 Million Dollar Ethanol Plant
Project Specific Owner
EPC Contractor
Major Subcontractors / Suppliers
Project Partially Financed – Remaining Financing to be Obtained
During Construction
Fast Track to Meet Peak Season Demand
Performance / Payment Bonds
Owner Letters of Credit
Parental Guarantee from Owner
Various Forms of Insurance
4
Scenario 1
Owner Learns About Problems on the Project
Two Major Subcontractors Have Not Been Paid for Two Months and
are Threatening to File Liens
One Major Equipment Supplier Behind Schedule and Unwilling to
Complete Fabrication Absent Substantial Advance Payment Due to
Cash Flow Problems Unrelated to the Project
5
Scenario 1 – The Issues
What Can the Owner Do to Protect Its Interest:
Direct Payment
Joint Payment Arrangements
Set Off
Lien on Equipment
Passage of Title
What Can the EPC Contractor Do to Protect Its Interest:
Mechanic’s Lien Waivers
Performance Bonds
Liens
6
Scenario 2
Major Equipment Supplier Goes Bankrupt
Absent Delivery of the Equipment, the Project Will be Substantially
Delayed
EPC Contractor Claims that the Automatic Stay Constitutes a Force
Majeure Event
7
Scenario 2 – The Issues
What Can the Owner/EPC Contractor Do to Protect
Their Interests:
Passage of Title
Executory Contracts
Termination of Subcontract Due to Bankruptcy Filing
Right of EPC Contractor/Owner to Equipment
Force Majeure Issue
8
Scenario 3
Corn and Gas Prices Skyrocket – Increases Costs of Production
and Decreases Demand for Ethanol
Financial System Meltdown Makes Financing Very Difficult to
Obtain
Owner Unable to Obtain Financing to Complete the Project and
Falls Behind on Invoices
Owner Asks EPC Contractor to Continue Performing
EPC Contractor Has Procured $50 Million of Services, Equipment
and Materials From Subcontractors and Suppliers That Has Not
Been Paid For
EPC Contractor Falls Behind on Invoices from Subcontractors and
Begins Receiving Demands for Payment
9
Scenario 3 – The Issues
What Can the EPC Contractor Do to Protect Its
Interests:
Limited NTP with Guaranteed Funding
Bonds
Letter of Credit
Securing Payments
Escrow Accounts
Parental Guarantees
Can Market Forces Excuse Performance of a Contract
Force Majeure
Commercial Impracticability
10
Scenario 4
Owner Files For Bankruptcy Protection
Owner Threatens To Reject The EPC Contract In Bankruptcy
Subcontractors and Suppliers Assert Claims Against EPC
Contractor in Court and Arbitration
11
Scenario 4 – The Issues
How Will the Bankruptcy Filing Impact the EPC Contract
Treatment of Executory Contracts
Impact of Assumption
Can the EPC Contractor Continue to Push for Payment
Automatic Stay
What About Pre-Petition Payments from the Owner
Preference Issues
12
Scenario 5
Owner Rejects EPC Contract
EPC Contractor Asserts Claims Against Owner in Bankruptcy
Court
Multiple Subcontractors and Suppliers Commence Separate
Arbitrations and Lawsuits Against EPC Contractor in Various
Forums
13
Scenario 5 – The Issues
What Happens as a Result of Rejecting the EPC Contract
Rejection v. Termination
How Can the EPC Contractor Obtain Payment
Letter of Credit
Payment Bonds
Parental Guarantee
Bankruptcy Claim Process
Mechanic’s Liens
Preference Issues
EPC Contractor Options - Forum for Resolving Claims
Arbitration Provisions in EPC Contract
Extension of Automatic Stay to Other Actions
Removal of Actions to Bankruptcy Court
14
Scenario 6
Project is Partially Destroyed by Fire
Cause of Fire Is Traced to Equipment Provided by Bankrupt
Supplier
Owner Receives Substantial Settlement From Casualty Insurer
Owner Seeks to Assert Claim Against Supplier and Its Insurer in the
Supplier’s Bankruptcy Case
15
Scenario 6 – The Issues
Right to Casualty Insurance Proceeds
Lien Issues
Right to Assert a Claim Against Supplier
Claims Covered by Insurance Proceeds and the Automatic Stay
16
Construction Project Bankruptcy
Strategic Considerations for Owners, General
Contractors and Construction Managers
December 16, 2008
Contact Information
To contact Charles A. Dale:
[email protected]
617.261.3112
To contact Joseph B.C. Kluttz:
[email protected]
704.331.7485
To contact Brian R. Davidson:
[email protected]
412.355.6267
To contact Andrew L. Swope:
[email protected]
717.231.4512
18