Transcript Document
ESKOM UNIVERSAL ACCESS TO ELECTRICITY BUSINESS PLAN AMEU Convention Durban 16 October 2007 Anton Theron Peter Sebola 1. CONTENTS Introduction UAP Context Methodology Results Critical Success Factors Conclusion 2. INTRODUCTION Our state president, in his state of the nation address in May 2004, set a target for all South Africans to have access to electricity by 2012. Universal Access is not a new concept, been on government’s agenda since the 90’s. However, in 2004 a committed timetable was officially extended to the nation. 3. UAP CONTEXT 2005 DME contracted Eskom for approach. 2006 statistics presented: - Current: 3 million - By 2012: 5 million Workshop identified need for plan to manage “Universal Access”. DME contracted Eskom to undertake the work. 3. UAP CONTEXT - Programme PHASE 1 PHASE 2 PHASE 3 Integrated Network Plan Composed of 2 Stages • Short Term • Medium Term • High Level • Planning Proposal UAP Planning Proposal Per Municipality Long Term STAGE 1 STAGE 2 Electrification Integrated Network Plan 3 months In line with Government Objectives 3-year MTEF cycle Universal Access Business Plan Master Plans For Accelerated Growth 3. UAP CONTEXT – Phase 3 Stage 1 Verify with the Regions Gather & Analyse Data Input to Bus. Case Handover to Electrification and Network Planning Electrification and Network Planning Analysis & Workshop with Regions Compile plans, Input to Bus. Case agree with regions on plans Handover to Electrification and Network Planning Strategic Studies Determine best guess growth figures based on econometric and demographic modeling Input to Bus. Case PMO Finalise Business Case Data Management 4. METHODOLOGY • Definition of Universal Access - Grid electrification option of choice with alternate technologies as interim solution - Alternate technologies replaced through process of continuous improvement • Determining Backlog - All existing authorised housing units with no access - Brownfields (Infills) & Greenfields - Exact locality of backlog - Census 2001official source for backlog statistics BACKLOG PROCESS: • Combination of HELP, DWAF & Census data • GIS buffer around all electrification transformers; • Count homesteads inside and outside this buffer; • Brownfields (Infills) = Inside count - Prepaid customers • Greenfields = Outside count existing land rate customers • Strategic Studies Team adjusted results for growth and Census alignment 4. METHODOLOGY Continued… • Planning Process (3 months) – Qualitative planning approach – Workshops (Demand side & Supply side plan) – Iterative process • Load & Energy Estimates – Past load research data – Function of income • GIS Platform 4. METHODOLOGY Continued… Has Capacity Limited Capacity No Capacity 5. RESULTS - Backlog per province 600,000 2 million households 500,000 in Eskom supply area 400,000 300,000 200,000 100,000 0 Backlog % of Backlog Eastern Cape Free State Northern Cape Western Cape Kwa-Zulu Natal Limpopo Mpumalanga Gauteng North West 548,192 110,679 24,764 28,632 528,060 312,364 124,847 147,094 164,589 28% 6% 1% 1% 27% 16% 6% 7% 8% 5. RESULTS - Accelerated Plan: No constraints Accelerated Plan 2.5 million connections by 2012 with growth 500,000 450,000 400,000 Connections 350,000 300,000 250,000 200,000 150,000 100,000 50,000 0 7/8 8/9 9/10 Allocated Backlog 10/11 Unallocated backlog 11/12 Growth 12/13 5. RESULTS – Pragmatic Plan with 07/08 Funding Accelerated Plan 2.5 million connections by 2012 with growth 600,000 500,000 Connections 400,000 300,000 200,000 100,000 0 7/8 8/9 9/10 Allocated Backlog 10/11 Unallocated backlog 11/12 Growth 12/13 5. RESULTS – Total Forecasted Demand ANTICIPATED DEMAND GROWTH DUE TO UAP 4500.0 4000.0 3500.0 3000.0 MVA 2500.0 2000.0 1500.0 1000.0 500.0 0.0 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Years Allocated Backlog Unallocated Backlog Growth Municipal Backlog TOTALS (incl Munics) TOTALS (excl Munics) 5. RESULTS - Summary SCOPE: HV Substations HV Lines (km) 19,071 MV Lines (km) 70,528 Trfrs (Units) 20,849 LV Lines (km) COST: 154 141,381 Wood Poles 6,181,371 Meters 2,540,712 R 24.7 bn 6. CRITICAL SUCCESS FACTORS • Inclusion of municipal backlog areas • Data update (satellite imagery) • Maintain geospatial planning platform • Stage 2 to proceed • Detailed Industry supplier capacity assessment • Understanding of REDS impact • Operational expansion 7. CONCLUSION • UAP shows that although great strides have already been made, much work still lies ahead to provide universal access to electricity • Task is not limited to electrification projects only as we remember it in the 90’s but also requires substantial upstream network expansion & strengthening Thank You Q’s ?