Transcript Slide 1
Project Management Work Breakdown Structure and the "Yellow Sticky" Process glb - 5/2003 Project Management The Work Breakdown Structure What is a project? A temporary endeavor undertaken to create a unique product or service. What is a Work Breakdown Structure (WBS)? An activity oriented family-tree division of work tasks that define the entire project. The Work Breakdown Structure WBS Terminology: Activity: A task or work package performed over a period of time. Relationships/Precedence: Dependencies that exist between activities. Duration: Length of the period of time to complete a task. Milestone: Zero time duration activity. Early Start: The earliest an activity can start based on project logic. Late Start: The latest an activity can start without delaying a project completion. Early Finish: The earliest an activity can finish based on early start and duration. Late Finish: Latest an activity can finish without delaying a project completion. Float: The amount of time an activity can be delayed without delaying the project finish date. Total Float: The amount of time that a pathway may be delayed from it's early start without delaying the project finish date. Critical Path: The longest time period from start to completion of a project; also the shortest total length of the project. The Work Breakdown Structure Task Relationships: –Finish to Start: Activity 1 must be totally finished before activity 2 can start. Activity 2 Activity 1 –Start to Start: Activity 2 can not start before activity 1 starts. Activity 1 Activity 2 The Work Breakdown Structure Task Relationships: –Finish to Finish: Activity 2 can not finish until activity 1 finishes. Activity 1 Activity 2 The Work Breakdown Structure "Yellow Sticky" Exercise: Early Start Early Finish Task Name / Brief Description: Late Start Duration: Resource: Late Finish Uses 3 X 5 Yellow Stickum Note Pads The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Activities/Tasks To Make: Toast, Eggs, and Coffee Toast Eggs Get Bread Get Pan Toast It Butter Toast Coffee Setup Put Water In Get Dishes Melt Butter Put Coffee In Set Table Cook Egg Turn on Maker Pour Coffee The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Set Precedence Get Pan Start: Butter Toast Toast It Get Bread Cook Egg Melt Butter Finish: Alarm Clock Eat Breakfast Put Water In Put Coffee In Get Dishes Turn on Pour Coffee Set Table The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Add Durations Get Bread Toast It Butter Toast 1 3 1 Start: Get Pan Alarm Clock 1 Cook Egg Melt Butter Finish: 5 2 Eat Breakfast Put Water In Put Coffee In 1 1 Turn on Pour Coffee 4 1 Get Dishes Set Table 2 3 The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Perform Forward Pass 2 2 1 6 5 5 Get Bread Toast It Butter Toast 1 3 1 2 2 1 Get Pan Start: 9 4 4 Cook Egg Melt Butter Finish: 9 1 1 5 2 1 Alarm Clock 2 3 2 Put Water In Put Coffee In 1 1 1 3 7 3 7 8 Turn on Pour Coffee 4 1 3 6 Get Dishes Set Table 2 3 Determine Early Start and Early Finish Eat Breakfast The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Perform Backward Pass 2 2 1 5 5 1 Get Pan 9 4 4 9 1 8 8 3 2 2 1 Start: Butter Toast Toast It Get Bread 4 6 5 5 Cook Egg Melt Butter Finish: 9 1 1 Alarm Clock 1 2 1 1 2 Put Water In 2 1 3 2 3 1 1 3 2 9 7 Turn on 4 4 8 3 1 6 Set Table 6 6 Determine Late Start and Late Finish 3 Eat Breakfast 8 9 Pour Coffee 8 4 Get Dishes 4 5 7 3 Put Coffee In 3 4 4 2 2 9 9 The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Determine Critical Path 2 2 1 5 5 1 Get Pan 9 4 4 9 1 8 8 3 2 2 1 Start: Butter Toast Toast It Get Bread 4 6 5 5 Cook Egg Melt Butter Finish: 9 1 1 Alarm Clock 1 2 1 1 2 Put Water In 2 1 3 2 3 1 1 3 2 9 7 Turn on 4 4 8 3 1 6 Set Table 6 6 3 Eat Breakfast 8 9 Pour Coffee 8 4 Get Dishes 4 5 7 3 Put Coffee In 3 4 4 2 2 9 Key: Any actions to shorten the overall project plan must be done to the critical path. 9 The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Determine Total Float 2 2 1 Butter Toast Toast It Get Bread 4 6 5 5 5 5 1 9 1 8 8 3 3 2 2 1 Get Pan Start: Cook Egg Melt Butter Finish: 9 0 1 1 Alarm Clock 9 4 4 2 1 4 4 2 2 5 9 Eat Breakfast 1 1 1 2 Put Water In 2 1 3 2 3 1 7 Turn on Put Coffee In 3 7 3 4 4 8 1 3 1 3 3 4 2 6 Set Table Get Dishes 6 6 9 Pour Coffee 8 4 8 3 9 9 The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Determine Activity/Task Float 2 2 1 5 5 1 Butter Toast 0 0 2 2 1 Get Pan 9 1 8 8 3 0 Start: 6 5 5 Toast It Get Bread 4 3 3 3 9 4 4 Cook Egg Melt Butter Finish: 9 1 1 Alarm Clock 2 1 1 1 1 1 2 Put Water In 2 1 3 1 4 9 8 1 9 3 3 2 8 Pour Coffee 8 4 3 6 Set Table Get Dishes 4 7 Turn on 4 6 Eat Breakfast 1 3 1 9 7 3 Put Coffee In 3 5 1 3 2 4 4 2 2 6 3 9 Activity/Task Float (Exclusive / Or) - Any one task on a pathway can use the total float, or the total float can be shared among all of the tasks on the pathway. However, the total float can not be exceeded without affecting the project end date. The Work Breakdown Structure WBS Terminology: Activity: A task or work package performed over a period of time. Relationships/Precedence: Dependencies that exist between activities. Duration: Length of the period of time to complete a task. Milestone: Zero time duration activity. Early Start: The earliest an activity can start based on project logic. Late Start: The latest an activity can start without delaying a project completion. Early Finish: The earliest an activity can finish based on early start and duration. Late Finish: Latest an activity can finish without delaying a project completion. Float: The amount of time an activity can be delayed without delaying the project finish date. Total Float: The amount of time that a pathway may be delayed from it's early start without delaying the project finish date. Critical Path: The longest time period from start to completion of a project; also the shortest total length of the project. Project Management Work Breakdown Structure and the "Yellow Sticky" Process glb - 5/2003