Transcript Slide 1

D41
D55
D40
D39
D37
D25
D22
LINK CANAL
D19
APPROACH
PUMP HOUSE ,
CHANNEL
PUMPS &
PREASUE MAINS
MAIN CANAL
Km. 23.20
1.47 KM
(1.5 TMC)
D41 TO D55
• The main canal works completed.
EPC PACKAGE NO.
80
PACKAGE 77
• All 4 Pumps installed and water was let out into canals.
• No. of pumps : 4 Nos. of 18MW each.
PACKAGE 78
PACKAGE 79
• Lift height : 100M
• Power required : 153 Millions Units
• The distributaries & field channels are under progress
• The project will be completed in all respects by 3/2008
DISTRIBUTORIES
(D19, D22, D25, D37, D39, D40 TO D55) CONSTRUCTION OF
WHOLE DISTRIBUTORY SYSTEM, CM & CD WORKS AND
MICRO NETWORK (FIELD CHANNELS)
• Reservoir: Akkampally & Udayasamudram
• Utilisation : 30.00TMC (2.50TMC for drinking water to 516 villages)
• Ayacut : 2.70 Lakh Acs.
• Length of canal : 136.150 Kms – 3000 c/s.
• .With
the completion of Distributaries and field channels in packages 77 to 81 and low level canal with lift an IP of
2.70 Lakh acres will be created by 3/2008.
Musi Reservoir
TUNNEL CISTERN
Km. 0.00
3 KM
(PUTTAMGANDI)
AKKAMPALLY
BALANCING RESERVOIR
UDAYA SAMUDRAM
BALANCING
RESERVOIR
(1.5 TMC)
Aiti Pamula
Reservoir
136.150 KM
AMRP PROJECT
FORESHORE OF
NAGARJUNA
SAGAR
RESERVOIR
AMRP PROJECT (Low Level Canal)
1
Project Profile
: Lifting of 30 TMC of water from
foreshore of Nagarjuna Sagar Reservoir
2
Administrative Sanction
: Rs.1327.00 Crs.
3
No. of EPC Packages
4
Agt. Value of 6 EPC Pkgs. + OC (tunnel)
: Rs.2160.63 Crs.
5
Budget Provision for 2006-07
: Rs. 299.95 Crs.
6
Expenditure
: 7 Nos.
upto 2004-05 : Rs. 728.46 Crs. (including Non-EPC ongoing)
2005-06 : Rs. 208.00 Crs. (including Non-EPC ongoing)
TOTAL : Rs. 936.46 Crs.
7
Utilisation
: 30 TMC
8
Ayacut
: 2,70,000 Acres
AMRP PROJECT (Low Level Canal)
9
Land Acquisition
Required :
8200 Acres
Acquired :
216 Acres
Requisitioned :
4524 Acres
10
Estimate cost of LA
: Rs. 148.00 Crores
11
Estimate cost of R & R
: Rs. 67.00 Crores
12
Mobilisation Advance
: Paid
2004-05 :
13
Target date for completion
Recovered
Rs. 8.14Crs.
-
Rs.106.87Crs.
2005-06 : Crs.
Rs.0.99
Rs.115.01 Crs.
Total : Crs.
Rs.0.99
: 3/2008
AMRP PROJECT
14. High Level Canal
 Lift Height
: 100 M
 No. of Pumps
: 4 No.s
 Pump Capacity (each) : 18 MW
 Power Required
: 72 MW
PRESENT STATUS :
 High Level canal including Head works
 Two Balancing Reservoirs (2 Nos.)
 Distributary system for 36,000 Acres
 Distributary system for 1,90,000 Acres
15. Low Level Canal
 Lift Height
: 27.50 M
 No. of Pumps
: 3 Nos.
 Pump Capacity(each) : 4 MW
 Power required
: 12MW
PRESENT STATUS :
 Low Level Canal (Km. 0.00 to Km. 13.00)
 Low Level Canal (Km. 13.00 to Km. 63.00)
 Lifts and low level canal beyond 63Kms
: Completed
: Completed
: Completed
: Under progress
: Completed
: Under Progress
: Tenders under finalisation
AMRP PROJECT
PKG
No.
Description
Awarded
Bid Amount
Rs. in Crs.
Construction of distributaries D19, D22, D25 lining of upstream
and downstream canal portions at structures and Micro Network
(Field Channels
SIDHARDHA AND
SWAPNA (JV)
33.44
78
Construction of distributaries D37 and Micro Network (Field
Channels), and lining of upstream and downstream canal
portions at structures
ECCI-MRKR (JV)
49.99
79
Construction of distributaries D39, D40 and Micro Network (Field
Channels), and lining of upstream and downstream canal
portions at structures
SIDHARDHA AND
SWAPNA (JV),
40.29
80
Construction of distributaries D41 to D55 and Micro Network
(Field Channels), and lining of upstream and downstream canal
portions at structures
ECCI-MRKR (JV)
44.79
81
Execution of Low level canal from Km. 27.00 to Km 63.00
including distributary system and Micro net work from Km. 0.00
to Km 63.00
AKR – COASTAL
(JV)
67.124
Investigation, Design and execution of Tunnels I & II including
head regulator at the entrance porter of Tunnel I of SLBC Tunnel
Scheme
M/s. Jai prakash
associates, new
Delhi
77
OC
TOTAL :
1925.00
2160.63
AMRP PROJECT
Package
No.
77/Cat-II
:
Execution
of
Name of the Contractor
: M/s Siddhartha
Constructions (P) Ltd.,& Swapna Constructions (JV)
distributaries of D-19, D-22&D-25, lining of
Agreement Amount
: Rs. 33.44 Crores
upstream and downstream canal portions at
Agreement Date
: 19-3-2005
structures and Micro Network (Field Channels )
Period of Completion
: 36 Months (10milestones)
Date of completion
: 18-03-2008

Investigation (HPs)
: Completed (Total length of 167 Kms)

Designs (Structures)
: Approval for 40 Kms length against 167Km structure.

Execution (Distributary)
: Progress in 10Km against total length of 167Km.

Qty. of earth work done
: 3,30,000Cum

Land Acquisition
: Required 1194 Acres, Requisitioned – 988 Acres; Acquired 24
Acres
AMRP PROJECT
Package No.78/Cat-II : Excavation of
Name of the Contractor
: M/s ECCI-MRKR (JV)
distributaries D-37 and Micro Network
Agreement Amount
: Rs. 49.99 Crs.
(Field Channels), and lining of upstream
Agreement Date
: 24-3-2005
Period of Completion
: 36 Months(10 milestones)
Date of Completion
: 23-03-2008
and
downstream
canal
portions
at
structures, CM & CD works.

Investigation (HPs)
: Major & Minor Completed. Sub-Minors are in progress.

Designs (Structures)
: Under approval.

Execution (distributary) : Earthwork excavation for 17Km of Major & 15Km Minors is
completed against 219Kms length.

Qty. of earth work done : 5.00 Lakh Cum against 20 Lakh Cum

Expenditure
Rs.49.99Crs.
: Rs. 5.29 Crores (including Mob.Adv. of Rs.2.50Crs) against
AMRP PROJECT
Package No.79/Cat-II : Excavation and
formation of embankments and construction
of D-39 & D-40 distributary system, CM & CD
works, lining the U/s and D/s canal portions
at structures with concrete and Micro
Network (Field channels)
Name of the Contractor
: M/s Siddhartha
Constructions Pvt. Ltd., - Swapna Constructions (JV)
Agreement Amount
: Rs. 40.29 Crs.
Agreement Date
: 19-3-2005
Period of Completion
: 36 Months(10 milestones)
Date of completion
: 18-03-2008

Investigation
: Major & Minors completed (Total length of 193.65Kms)

Designs (Structures)
: approved in 36 KM against 193.65 Kms length

Execution(Distributary)
: Progress in 13.00 Km of Majors against 193.65 Kms.

Qty. of earth work done : 3,75,000 Cum

Land Acquisition
: Required 1836 Acres, Requisitioned 1232 Acres, Acquired 97 acres

Expenditure
: Rs. 9.305 Crs. (Inc. Mob.Adv. Rs. 4.025 Crs.) against Rs. 4.029 Crs.
AMRP PROJECT
Package No. 80/Cat-II : Execution of
distributaries D41 to D55 and Micro
Network (Field Channels) and lining of
upstream and downstream canal portions at
structures.
Name of the Contractor
: M/s ECCI-MRKR (JV)
Agreement Amount
: Rs. 44.795 Crs.
Agreement Date
: 13-5-2005
Period of Completion
: 39 Months
Date of completion
: 12-08-2008
 Investigation
: Investigation completed
 Designs approval
: HPs are approved from D41 to D45, D47,D49,D50,D51
and
 Execution
D53 to D55.
: Progress in 8Kms of Major
 Qty. of earth work done: 1,30,000 cum
 Expenditure
: Rs. 3.60 Crs (including Mob. Advance Rs.2.20Crores)
against Rs.44.795Crs.
 Land Acquisition
: Required 1500 Acres, Requisitioned – 391 acres
AMRP PROJECT
Package No. 81/Cat-II: Execution of Low
Name of the Contractor
: M/s AKR – Coastal (JV)
level canal from Km.27.00 to Km.63.00
Agreement Amount
: Rs. 67.124 Crs.
including distributary system and Micro
Agreement Date
: 28-03-2005
network from Km.0.00 to Km.63.00
Period of Completion
: 36 Months(10milestones)
Date of completion
: 27-03-2008

Investigation
: Main canal completed
Structures on main canal, distributary system in progress.

Execution
: Progress in 12Km of Main canal against 36 Kms length

Qty. of earth work done : 7,50,000 Cum

Expenditure
: Rs. 15.274 Crs. (inc. Mob. Adv. Rs. 6.694 Crs.) against
Rs.16.69Crores
LA Paid
: Rs. 0.73 Crs.
Mob. Adv. Recovered : Rs. 0.99 Crs.

Land Acquisition
: Required 2100 Acres, Requisitioned – 690 Acres;
DN/DD Published : 200 Acres.
AMRP PROJECT (Tunnel Scheme)
Tunnel: Execution of Tunnels 1 & 2 of
SLBC including Construction of Head
Regulator.

Investigation
for
Name of the Contractor
: M/s. Jaiprakash
Associates Ltd.
Agreement Amount
: Rs. 1925 Crs.
Agreement Date
: 25-08-2005
Period of Completion
: 60 Months(20milestones)
Date of completion
: 24-08-2010
: Investigation, design, planning and procurement of TBM
tunnel is in progress

Expenditure
: Rs.96.25 Crores (Mob. Advance)

Execution
: Starts from 9/2006 (Investigation, design, bore hole,
exploration etc to be completed by 8/06 – 12 months
period)