Todays Topics
AB 3023-George Elsmore Sec 130 Grade Crossing Maintenance Funding-Bree Arnett Near-miss data collection-Ariana Merlino Grade Crossing Warning Device Recycling Program-Gerald Muffley
Infrastructure Security
Article 7.3 Local Community Security Act of 2006 PU Code § 7665 Effective January 1, 2007 Risk Assessments due July 1, 2007 Commission Director OHS OES § 7665.4(d) Information is confidential
Infrastructure Security
PU Code § 7665 Effective January 1, 2007 Infrastructure Protection Program implemented by January 1, 2008 Updated annually Reviewed by Commission
Signage & Flags
PU Code § 7662 (a)-Approaching Grade Crossings-Whistle boards (b)-Temporary Stop Orders (Form B, Red/Yellow flags) and Speed Restrictions (Form C, Yellow flags) (c)-Mileboards (e)-Speed Signs
Miscellaneous
PU Code § 7662 (f)-notification of new RCO’s (g)-Immediate accident notification
CPUC-BNSF/UPRR AB 3023 Settlement Agreement Infrastructure Security & Protection Invalid Provisions PU Code §7665.6(c)-prohibition on unattended idling locomotives PU Code §7665.6(d)-Locomotive cab security PU Code §7665.6(e)-No RCO’s w/Haz-mat over camera-equipped public xings
CPUC-BNSF/UPRR AB 3023 Settlement Agreement (Cont’d) Flags & Signage Invalid Provisions PU Code §7662(e)-Wayside speed increase signage