www.tristategt.org

Download Report

Transcript www.tristategt.org

Large Generator
Interconnection Procedures
Reform
Stakeholder Meeting
February 19, 2009
Agenda
•
•
•
•
•
Goals and Expectations
Background
Recap of Recent Changes
LGIP Reform
Next Steps
February 19, 2009
2
Goals and Expectations
• Goal: Develop a process that allows competitive
generators to deliver their energy to load on a
reliable transmission system.
• Expectations of this stakeholder process:
– An iterative process that examines Tri-State’s
interconnection procedures;
– Constructive dialog with stakeholders on specific
improvements to Tri-State’s concept paper;
– Final procedures that meet the goal.
February 19, 2009
3
Background
• In 2007 and 2008, 57 requests were added to
Tri-State’s queue
– Process became unmanageable
• Recently several ISOs implemented queue
reforms.
• Tri-State reviewed these reform efforts and
initiated its own.
February 19, 2009
4
2008 LGIP Process
• Nov. 5, 2008: Tri-State stopped accepting
applications.
• Nov. 20, 2008: Interconnection Customer meeting
on proposed LGIP modifications.
• Nov.20-Dec.15, 2008 accepted comments.
• Jan. 9, 2009: Posted modified LGIP with
revisions based on comments.
• Jan. 12, 2009: Modified LGIP effective
• Jan. 12, 2009: Began accepting applications
February 19, 2009
5
LGIP Changes Effective 1/12/09
• Application deposit:
– $125,000 for projects 75 MW or less,
– $250,000 for larger projects.
– $25,000 is non-refundable if project drops out
of queue.
• Site Control:
– No additional Deposit in lieu of Site Control
– Require 50% of necessary land at application
– 100% prior to interconnection agreement.
February 19, 2009
6
LGIP Changes Effective 1/12/09
• Projects designated as a network resource or with
a power purchase agreement receive priority for
study work—FIRST READY-FIRST SERVED.
• Prior to Facilities Study, network interconnection
requestors must have power customer.
• Suspension of construction for Force Majuere
events only.
• Only accept “immediately available funds” in
advance.
• Several changes to streamline study process.
February 19, 2009
7
LGIP Reform
• Tri-State’s LGIP Reform concept paper is the
second step in a two step process
• Changes in January were designed to improve
queue management and the interconnection
study process.
• Tri-State’s LGIP Reform concept paper
presents ideas that will simplify and expedite
the generation interconnection process.
February 19, 2009
8
LGIP Reform
• Most of the changes adopted in January 2009
will be retained.
• New Concepts:
– Interconnection process based on Load and
Resource Transmission Study.
– New options for determining Network Upgrades.
– Biannual Interconnection Request Windows.
February 19, 2009
9
LGIP Reform
• New Concepts (continued):
– Multiple Customer options for proceeding to
Facilities Study
– Queue Management:
• First Come-First Served through the System Impact
Study, subject to priority for projects with
designation as Network Resource;
• First Ready-First Served after the System Impact
Study.
February 19, 2009
10
Load and Resource Plan
• Load and Resource Plan
– Submitted by all Network Customers.
– Identify resource amounts and anticipated
geographic areas.
– Up to 4 resource distribution scenarios will be
accepted with each plan.
February 19, 2009
11
Draft Definition
• Load and Resource Plan shall have the
meaning set forth in Section 31.6 of the
Tariff and shall identify projected load
growth and projected amounts of generating
capacity from each Resource Zone to meet
the network integration transmission
customers’ network load requirements.
February 19, 2009
12
Load and Resource
Transmission Study
• Performed once annually
• Will include transmission upgrades in
Tri-State’s most recent 10 year
transmission plan.
• Will determine and estimate the cost of
additional upgrades required to
accommodate the needs presented in the
Load and Resource Plans.
February 19, 2009
13
Draft Definition
• Load and Resource Transmission
Study means a transmission planning
study that models the Transmission
System and identifies Network Upgrades
and projected amounts of generation
from each Resource Zone to
accommodate the combined Load and
Resource Plan.
February 19, 2009
14
Draft Definition
• Resource Zone means a geographic area that is
a projected location for interconnection of new
Network Resources to the Transmission System.
Transmission Provider shall evaluate each
Resource Zone on the basis of the combined
Load and Resource Plan of all Network
Integration Transmission Service customers as
required by Section 31.6 of the Tariff, and in
coordination with Transmission Provider’s
applicable Tariff and regional transmission
planning responsibilities.
February 19, 2009
15
Interconnection Service
• Pro Forma LGIP:
– Energy Resource Interconnection Service
– Network Resource Interconnection Service
• Tri-State concept:
– Single Interconnection Service
– Focuses on Interconnection Facilities
– Network Upgrades handled either in Load and
Resource Study or subsequent to Transmission
Service Request (TSR)
February 19, 2009
16
Interconnection Service—Draft
• Interconnection Service. For the purpose of
Interconnection Service, Transmission
Provider shall make no distinction among
types of transmission service or delivery
capabilities from physically similar
Interconnection Facilities, except that
Network Upgrades shall be identified either
through a Load and Resource Transmission
Study or through studies to be provided as part
of a Transmission Service Request.
February 19, 2009
17
Interconnection Service—Draft
• The Product. Transmission Provider shall conduct the
necessary Studies to construct the Interconnection Facilities and
Network Upgrades needed to integrate the Large Generating
Facility (1) in a manner comparable to that in which
Transmission Provider integrates its generating facilities to serve
native load customers based upon a Load and Resource
Transmission Study that includes Network Upgrades; or (2) with
Interconnection Facilities provided and Network Upgrades added
pursuant to a Transmission Service Request; or (3) with
Interconnection Facilities provided and Network Upgrades
deferred at the Interconnection Customer’s own risk of operating
limits for the purpose of future Transmission Service.
February 19, 2009
18
Customer
Review Published
Load & Resource
Transmission Study
A
Attend Information
Session at beginning
of IR Application
Window
Customer may perform
Optional Feasibility Studies
and have access to Base
Case Data
$250,000 Study Deposit for >75 MW Projects
OR,
$125,000 Study Deposit for ≤ 75 MW Projects
(Includes $25,000 non-refundable for both generation levels)
Proof of 50% site control at time of application
Submit IR
IR Applications reviewed on semi-annual basis.
Two-month windows to submit application
B
SIS Scoping
Meeting
Three levels of generation
allowed and specified for
study at time of meeting
SIS
After power flow portion
of SIS, customer is
asked to select one
generation level
IC Facilities Only
C
LGIA
EXIT
SIS Review (with cost
estimates) and
FS Scoping Meeting
100% of Site Control required
at this point
Customer deposits IC
Facilities money and
submits TSR or
proceeds at own risk
D
Customer shows
designation as
Network Resource
At Risk
Path
Network
Upgrade
Studies
TSR
Path
Facilities
Study
Alternatives for Advancement to
Facilities Study
• Interconnection Customer has five options:
– Show designation as Network Resource; or
– Advance funds for facility construction and
submit Transmission Service Request (TSR); or
– Advance funds for facility construction without
TSR and proceed at own risk; or
– Suspend work for up to one year; return to queue
behind any project ready for Facilities Study; or
– Withdraw project from the queue.
February 19, 2009
23
$250,000 Study Deposit for >75 MW Projects
OR,
$125,000 Study Deposit for ≤ 75 MW Projects
Customer
EXIT
LGIA
(Includes $25,000 non-refundable for both
generation levels)
SIS
Review
Proof of 50% site control at time of application
Review
Published
Load &
Resource
Transmission
Study
Attend
Information
Session at
Beginning
of IR
Application
Window
A
SIS Scoping
Meeting
Submit IR
B
Three levels of
generation allowed
and specified for
study at time of
meeting
SIS
After power
flow portion
of SIS,
customer is
asked to
select one
generation
level
(with cost
estimates)
and
FS
Scoping
Meeting
100% of
Site
Control
required at
this point
Customer
Shows
Designation
as Network
Resource
C
D
IC
Facilities
Only
Customer
may perform
Optional
Feasibility
Studies and
have access
to Base Case
Data
IR Applications
reviewed on
semi-annual
basis. Two
month windows
to submit
application
At Risk
Path
Customer deposits
IC Facilities money
and submits TSR
or proceeds at own
risk
TSR
Path
Network
Upgrade
Studies
Facilities
Study
Next Steps
• March 19th—Comments due on concept.
• April 21st—Tri-State will post comments and
responses, and formal proposal.
• May 5th—Second Stakeholder meeting.
• June 5th—Second round of comments due.
• Balance of timeline will be determined after
second stakeholder meeting.
February 19, 2009
25
Comments
• Submit your comments today or by March 19th to:
• Ron Steinbach
Transmission Policy Administrator
Tri-State Generation and Transmission
Association, Inc.
P.O. Box 33695
Denver, CO 80233
• OR to
– [email protected]
• Questions—call Ron at
– 303-254-3355
February 19, 2009
26