Hydro-Turbine Generator Mechanism for UM

Download Report

Transcript Hydro-Turbine Generator Mechanism for UM

Design and Development of a Hydro-Turbine

Senior Engineering Design Project - 2008 John Connor Elisia Garcia Som Tantipitham Faculty Advisor: Dr. Quamrul Mazumder

Abstract

The usage of fossil fuels is slowly being replaced by cleaner and more renewable sources of energy. Since Michigan has varying amounts of sunlight, the use of solar energy would not be practical. With the Flint River located on the campus of the University of Michigan-Flint, hydroelectric energy may be a feasible alternative. Connecting a micro-turbine to a generator and using the natural current of the river can prospectively generate 200 to 300 watts of energy. Funneling the water into the turbine will increase the velocity of the current. With more velocity, more revolutions the turbine will experience. Then, with the goal of 200 to 300 watts desired, the turbine will be equipped with the appropriate number of blades, along with appropriate blade angle. This will ensure that not only the desired energy is produced, but that also that the system is as efficient as possible.

Project Schedule

Task Name

Project Propsals Background Research Technical Paper (Abstract/Intro) Technical Paper (Background) Technical Paper (Current Work) Technical Paper (Design Analysis) Technical Paper (Final Correlations) Design Proposal Design (Detail Spec Drawings Pro-E) Design Data Computations Design Software Analysis Machining (Casing) Machining (Turbine) Machining (Supports) Machining (Generator Assemby) Machining (Final Assembly) Testing (Initial) Testing (Modifications) Testing (Final) Project Status Report/Demonstration Final Presentation

January February March April

8-Jan 14-Jan 21-Jan 28-Jan 4-Feb 11-Feb 18-Feb 25-Feb 3-Mar 10-Mar 17-Mar 24-Mar 31-Mar 7-Apr 14-Apr 21-Apr Estimated Task Completion Actual Task Completion Schedule Performance Index: 102.68%

Progress

Schedule Performa nce In dex

Project Proposals Background Research Technical Paper (Abstract/Intro) Technical Paper (Background) Technical Paper (Current Work) Technical Paper (Design Analysis) Technical Paper (Final Corre lations) Design Proposals Design (Detail Spec Drawings Pro-E) Design (Data Comp utations) Design Software Analysis Machining (Casing) Machining (Turbine) Machining (Final Assembly) Testing (Initial) Testing (Modifications) Final Presentation Testing (Final) Project Status Report/Demonstration

Over all Average = 102.68 %

(21 days/21 days) * 100 = 100% (21 days/28 days) * 100 = 75% (14 days/14 days) * 100 = 100% (14 days/28 days) * 100 = 75% (14 days/21 days) * 100 = 67% (14 days/7 days) * 100 = 200% (42 days/42 days) * 100 = 100% (28 days/28 days) * 100 = 100% (28 days/28 days) * 100 = 100% (28 days/28 days) * 100 = 100% (14 days/21 days) * 100 = 67% (7 days/7 days) * 100 = 100% (14 days/14 days) * 100 = 100% (14 days/7 days) * 100 = 200% (7 days/7 days) * 100 = 100% (14 days/14 days)* 100 = 100% (14 days/21 days)* 100 = 67% (14 days/14 days)* 100 = 100% (7 days/7 days) * 100 = 100%

Cost Analysis

20 0 60 40 120 100 80

Efficiency

RPM Outputs vs . Tur bine Efficie ncy

268 532

RPM Output

800 1064 The generator efficiency is directly proportional to the rpm

Force

Assume:

ρ

water

= 62.4 lb

m

/ft

3

V V

  

Av

( 0 .

625

ft

2 )( 8

blades

)( 11

ft

/

s

)  55

ft

3 /

s

V

water init

= 7.5 mph = 11ft/s

V

water final

= 7.0 mph = 10.26 ft/s

Propeller Diameter = 292 mm = 0 .958 ft

m

 

water

 

v

m

 ( 62 .

4

lb m

/

ft

3 )( 55

ft

3 /

s

)  3432

lb

/

s

Area of Blade = 90 in

2

= 0.625

F

ft

2 F

One dimensional Flow

F

   ( ( 

m

(

v

2 3432 

lb v

1 / )

s

2539 .

68

lb

)(

f

10 .

26

ft

/

s

/ 8

blades

)   11

ft

/

s

)  317 .

46

lb f

2539 .

68

lb f

 1412 .

13

N

Detail Drawings

FEA

 Stress analysis for the turbine support frame  Max stress occurs at the fixed ends  Max stress of about 16000 Pa

FEA

 Total deformation of support frame  Max deformation occurs where turbine rest  Max deformation of about 1.7e-8m

FEA

 Stress analysis on the turbine  1400N forced placed on shaft  Max stress 14357Pa

FEA

 Total deformation of turbine  1400N force placed on the shaft  Max deformations is about 0.17m

 Cause of large deformations is because sheet metal was used for the blades

Assembly

Early Stage of Development: Housing for the Turbine

Assembly

First Generator Delivered 300W at 3400rpms

Assembly

 Ametek 38 Volt Motor  Can deliver 300W with 600rpms  More compacted and lighter

Ametek 38 Volt Motor

Assembly

Early Stage of Development: Turbine

Changes from Original

 Redesigned 10 blades turbine to 8  Reversed placement of generator on the support to better fit the location  Changed generators

Difficulties

 First generator didn’t perform as expected  Water flow of the river was inconsistent  River dried up before final testing could be done

Difficulties

River dried up in the location that was going to be used

Plan B Testing

 Using a power washer to simulate water flow  Voltage output of 35.5V

 Using the performance curve, this is equivalent to 398W of power

Completed Generator