Transcript SA SRAS
SOUTH AUSTRALIA REGION RESTART July 2013 PRESENTED BY PETER BIDDLE SLIDE 1 AGENDA 1. The System Restart standard 2. What are the proposed changes a) b) c) d) Main assumptions Electrical sub-networks Quantity of SRAS SRAS Definition 3. Restart process 4. Questions 5. Summary SLIDE 2 SYSTEM RESTART STANDARD • Procure sufficient SRAS to achieve the following targets in each electrical sub-network; o Provide auxiliary supply to sufficient generation within 90 minutes to provide generation & transmission capacity to meet 40% of peak demand within 4 hours • For South Australia peak demand = 3400 MW • Need to supply 1360 MW capacity within 4 hours • The restoration timeframe represents the target timeframe to be used by AEMO in the procurement process. It is not a specification of any operational requirement that should be achieved in the event of a black system condition SLIDE 3 WHAT ARE THE PROPOSED CHANGES • Current assumption is that SRAS is procured to manage a NEM wide shutdown o This is an overly conservative assumption o Changing to a Region only shutdown • NEM wide shutdown requires each region to be selfsupporting for SRAS o Region only shutdown allows use of adjoining regions as a restart supply • Currently one electrical sub-network in SA o No change recommended SLIDE 4 RECOMMENDED CHANGES (CONT.) • Quantity of SRAS o Recommending a minimum of 1 SRAS in each subnetwork Single SRAS for SA region o Using supply from Victoria plus one SRAS still provides two sources of restart supply The restart process from Victoria is documented in the AEMO system restart plan for SA SLIDE 5 RECOMMENDED CHANGES (CONT.) • Current definitions of primary & secondary SRAS has led to a number of perverse outcomes o small gas turbines starting large thermal units at the same power station that do not assist in AEMO meeting the System Restart Standard because: No output to transmission network for several hours Do not assist in restarting other generating units o Contracting with diesel units used to restart hydro and gas turbine generating units Makes testing difficult and inefficient SLIDE 6 RECOMMENDED CHANGES (CONT.) • Recommending a single SRAS definition • Objective is to ensure contracted services assist AEMO in meeting the System Restart Standard o ≥ 100MW delivered to the local transmission bus within 60 minutes. Availability/reliability ≥ 90% Could be delivered by • • • • TTHL Hydro Gas Turbines Other o Testing would involve black starting the unit, connecting to the power system and increasing output to contracted output within the contracted timeframe. • AEMO is currently consulting with a number of generators to see if changes to this proposal are warranted. SLIDE 7 RESTART PROCESS • Under AEMO’s proposal SA will have two restart sources o o From Victoria SRAS • A restart will normally start from both sources concurrently. o A restart from Victoria is currently documented in AEMOs published system restart plan for SA, so for this exercise we will assume that connection to Victoria is not available and a restart will use an SRAS only. • The aim is to provide auxiliary supply to the majority of power stations within 90 minutes. o If this is done then the time to restore supply capacity is minimised but is then outside AEMO’s control. Load restoration determined by rate at which power stations can restore capacity SLIDE 8 SOME ASSUMPTIONS • No change from current process o All generation & transmission equipment is available for service o Generation capability is in accordance with Local Black System Procedures as provided by Generators o Reasonable time frames allowed for restoration of transmission elements o Load can be restored for voltage control o Major generation • • • • • • • • Torrens Island Pelican Point Quarantine Osborne Northern Hallett Mintaro Dry Creek o There are potentially a number of ways to do this SLIDE 9 RESTORATION • For the purpose of this exercise assume SRAS is supplied by Dry Creek • Part 1 – supply to Torrens Island area • Start one Dry Creek unit and energise the 66KV bus at Torrens Island via Kilburn • Restore sufficient load ex Kilburn and TIPS 66KV bus to stabilise the Dry Creek unit. o Provides auxiliary supply to the Torrens Island and Quarantine power stations • Start the 4 small Quarantine and remaining Dry Creek units • Restore load ex Kilburn and TIPS 66KV bus to stabilise units • Restore Torrens Island to New Osborne and then to OCPL o Provides connection/auxiliary supply to Osborne generation SLIDE 10 RESTORE QPS – TIPS 66KV SLIDE 11 RESTORATION • Restore the Torrens Island 275KV bus from the TIPS 66KV bus (east bus is preferable) • Restore the Torrens Island to Para line and start at least one of the SVCs at Para (set point <= 280KV) • Restore Torrens Island – LeFevre – Pelican Point – PGWest – Para lines o Provides connection/auxiliary supply to Pelican Point • Supply to all Torrens Island area generation now available and can be started as required/available. SLIDE 12 RESTORE TORRENS ISLAND 275KV NETWORK SLIDE 13 RESTORATI0N • Part 2a – Northern area generation • Recommend both SVCs at Para in service prior to proceeding (trip of an SVC during next steps may result in an overvoltage situation) • Restore Para to Robertstown • Restore Robertstown to Davenport via Canowie • Restore Playford 132KV bus o Provides auxiliary supply for Northern power station • Restore connection to Hallett power station (not the wind farm) from Canowie. SLIDE 14 RESTORATION • Part 2b – restore connection to Angaston & Mintaro • Can be done at the same time as part 2a • Restore Para to Roseworthy, Temple, Dorrie and Angaston o Connection for Angaston power station • Restore Temple to Waterloo and Mintaro o Connection to Mintaro power station SLIDE 15 PARA TO DAVENPORT & MINTARO SLIDE 16 TIMING ESTIMATES TO MAKE AUXILIARY SUPPLY AVAILABLE • Elapsed time = 30 minutes o o Quarantine Dry Creek • Elapsed time = 60 minutes o o o Osborne Torrens Island Pelican Point • Elapsed time = 90 minutes o o Mintaro Angaston • Elapsed time = 120 minutes o o Northern Hallett SLIDE 17 AFTER 4 HOURS – LIKELY SUPPLY CAPACITY • • • • • • • • • • Dry Creek 135 MW Quarantine 225 MW Osborne 190 MW Pelican Point 430 MW Torrens Island 320 MW Mintaro 100 MW Angaston 50 MW Hallett 180 MW Northern 250 MW Total = 1880MW (require 1360 MW to meet the SRS) SLIDE 18 WIND FARMS • In South Australia wind generation comprises a significant portion of the total installed generation capacity. • Due to the unreliable nature of the output reconnecting wind farms during the early stages of the restart is not practical. • Wind farms will not be reconnected until either o An AC connection is restored to Victoria, or o 40% of load has been restored Limited to 10% of on line generation SLIDE 19 QUESTIONS QUESTIONS SLIDE 20 SUMMARY • • • • • Region only shutdown Minimum of one SRAS to be procured Revised SRAS definition Still two sources of restart supply Expect to be able to provide auxiliary supply/connection to the majority of power stations within 90 minutes. • Rate of load restoration will depend on rate of generation restoration and is outside AEMO’s control. SLIDE 21