Economic Regulation
Download
Report
Transcript Economic Regulation
Regulatory Risk
David Newbery
Eighth ACCC Regulatory Conference
The evolution of regulation
26-27 July 2007
Gold Coast, Queensland
http://www.electricitypolicy.org.uk
Outline
• Why (and where) worry?
• Lessons from elsewhere:
– Successes and failures
• electricity vs rail
– Evolution of British regulation
– Boundary cases
• airports, interconnectors, gas pipelines
– Withdrawing from regulation
• EU Communications Directive
• mobile cal termination
Newbery - ACCC
2
Why worry?
Perceived risk from
– future access regulation, or
– tightening existing regulation
could
– deter infrastructure investment
– deter innovation
– deter facilities-based competition
Newbery - ACCC
3
Possible responses
• Regulatory protection could entrench
incumbent lock-in
– remove downside of first-mover advantage
– shift cost to other consumers
• Regulatory protection if utility unbundles
– works well for pipes and wires, not for ICT?
Gas and electricity differ from rail and ICT
Newbery - ACCC
4
Franchise regulation
• Utility submits investment plan
• Regulator assesses, approves
– possible test of consumer WTP
• Allows WACC on efficient investment cost
– subject to dispute resolution
• Customers have to pay
Risk: deters innovative investments (AT&T
cell phones)
Newbery - ACCC
5
Liberalised networks
• No franchise: no captive market to recover
unprofitable investments
• Merchant investments:
– able to take risks for rewards
– to challenge sleepy incumbents
Risks: threat of future access regulation,
predatory competition from incumbents =>
under-investment by entrants
Newbery - ACCC
6
Part IIIA of Trade Practices Act
Access Regime amended 2006
• Provides for regulated access to essential facility
of national importance where necessary to permit
material increase in competition in at least one
other market (whether or not in Australia)
• Earlier concerns
– lacked national interest test (public interest?)
– lacked efficiency test (resolved?)
– earlier vagueness on pricing (resolved?)
Newbery - ACCC
7
Efficient infrastructure investment
• ‘Easy’: upgrade mature regulated networks
• Hard: major regulated network development
• Problematic: unregulated essential facilities
Problem: asymmetric information + abuse of
market power vs regulatory opportunism
Solution: legal predictability and sanity
Newbery - ACCC
8
Successes: liberalising access
• US, UK generation investment
– huge boom after liberalisation
• US: 200 GW 1997-2003; from 776 -980 GW ’96-’05
– over-investment, price collapse bankrupted
companies, consumers protected
• US gas network after unbundling
– investment OK, resilient to shocks
• Dot-com boom, ICT investment, 3G auctions
– innovation encouraged, consumers benefit
Newbery - ACCC
9
Generation in England and Wales
Newbery - ACCC
10
Newbery - ACCC
11
Failures?
• IPPs in developing countries?
– Enron’s Dabhol: contract terminated, plant shut,
Maharashtra short of 2,100 MW for 6 yrs
• NETA changed the GB wholesale electricity
market?
– prices collapsed, companies bankrupted
– caused by delayed competition?
– Risky to rely on sustained imperfect competition?
• Railtrack: forced into administration?
Newbery - ACCC
12
Number of privately financed greenfield generation projects
80
70
number closed
60
East Asia & Pacific
50
40
SSA
30
SA
MENA
20
ECA
10
EAP
LAC
0
1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005
Newbery - ACCC
13
Real GB electricity prices and costs
35
7000
Price control
Profit maximising
Tacit
Collusion
plant
withdrawal
25
£(2001)/MWh
6000
20
5000
4000
NETA
15
HHI
30
Restraint
3000
Electricity
10
2000
coal cost
gas cost
5
1000
Coal HHI
0
0
1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004
David Newbery Data from J
Bower and C Humphries
14
Railtrack - the counterexample?
• Hatfield crash - 4 dead
network replacement - massive disruption
• track costs underestimated
• recent price control inadequate
• put into administration by Govt.
– Railtrack boss failed to ask for revenue increase
• Network Rail emerges as a PPP
– or has it been renationalised?
Newbery - ACCC
15
4,500
13,500
4,000
12,000
3,500
10,500
3,000
2,500
9,000
Privatisation
7,500
2,000
6,000
1,500
4,500
1,000
Investment (LH scale)
500
0
3,000
1,500
0
Source: A Smith
Newbery - ACCC
16
Total opex + capex
Hatfield crash
19
63
19
65
19
67
19
69
19
71
19
73
19
75
19
77
19
79
19
81
19
19 83
85
/
19 86
87
/
19 88
89
/
19 90
91
/
19 92
93
/
19 94
95
/
19 96
97
/
19 98
99
/
20 00
01
/
20 02
03
/0
4
Investment £ millions (2002/3 prices)
British Rail Investment (constant prices)
Regulatory or political risk?
• Regulator was open to request for increased
revenue to finance higher revealed costs
• Political pressure forced Railtrack CEO to
accept administration
– concerns over corporate manslaughter?
– City timetable too tight for rescue?
• But investment continues apace
– Government finances but cannot control!
Newbery - ACCC
17
Rail Industry Cash Costs per Train Kilometre
Post-privatisation
25.0
21.7 a
22.5
Hatfield accident
£ Per Train Km, 2001/02 Prices
20.0
19.3
Previous peak = 16.5
17.5
15.0
12.5
Unit cost average
(1963 to 2001/02) = 15.0
10.0
7.5
5.0
2.5
4
/0
2
20
03
01
/0
/0
0
20
99
/9
8
19
19
97
/9
6
95
/9
4
19
19
91
93
/9
2
0
19
89
/9
88
19
7/
6
19
8
/8
83
19
85
19
81
19
79
19
77
19
75
19
73
19
71
19
69
19
7
19
6
19
65
19
63
0.0
(a) Note: preliminary estimates for 2002/03 and 2003/04 are based on rises in Network Rail costs since 2001/02. Other industry costs are assumed
constant in real terms, as data is not yet fully available beyond 2001/02. See Smith (2004), Institute for Transport Studies Working Paper, no. 585;
also forthcoming in the Journal of Transport Economics and Policy.
- ACCC
Source:Newbery
A Smith
18
RPI-X regulation
• intended to mimic competitive market
• originally designed for BT to provide better
incentives than RoR (Littlechild)
• high powered incentives if price delinked
from future cost
Problems with quality and credibility would it deliver investment?
Newbery - ACCC
19
British experience
• Gas, electricity, water: early investments
easy to approve
– issue was predicting efficient cost to allow
• Telecoms: easy to finance investments
– hard to determine access price
• Mobile - competitive, initially unregulated
– CPP users agree excessive access charges
• Rail: much investment -hard to judge value
Newbery - ACCC
20
Evolving regulatory certainty
• Networks subject to RPI-X & quality standards
• Well defined methodology for setting Po, X:
– RAB, WACC, financial adequacy, benchmarking
– works well when investments obviously needed
– problematic for speculative investments
=> remove from cap (but for how long?)
• Regulatory commitment + appeals process
– Control changed by agreement, agreement overruled only if in the public interest
Newbery - ACCC
21
British Electricity Distribution Investment
2000
1800
£ millions (2003/4 prices)
1600
1400
1200
1000
Company forecast
800
Regulator's allowance
600
Actual investment
400
200
Newbery - ACCC
Source: Green
/5
'04
/4
'03
/3
'02
/2
'01
00
/1
0
99
/0
98
/9
97
/8
96
/7
95
/6
94
/5
93
/4
92
/3
91
/2
90
/1
89
/9
0
0
22
T & D Reliability
Average Transmssion System Availability (%)
DNOs supply interuptions (min/year)
Source: National Grid
Source: OFGEM
Average Security
Average Availability
96.5
260
96
95.5
210
95
94.5
160
94
110
93.5
93
60
92/93 93/94 94/95 95/96 96/97 97/98 98/99 99/00 00/01 01/02 02/03
Newbery - ACCC
1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000
23
Airports - not all regulated
• Each airport faces varying competition
• Regulator ill-equipped to forecast demand
• How to set charges and assess efficient plan
when expansion exceeds control period?
–
–
–
–
Pre-funding aligns with scarcity pricing
“constructive engagement” with users
separate price control for each London airport
consider removing price control from Stansted:
competes with unregulated Luton
Newbery - ACCC
24
User engagement
• for well-informed users encourage private
agreements?
– Can work (e.g. airports)
– Problematic with many users
• and if objectives differ (e.g. low cost airlines vs
incumbent airlines)
– what about refusal to supply?
– Or facilitating tacit collusion?
Competition policy needed to prevent abuse
Newbery - ACCC
25
Merchant transmission investment
• Hard to get regulators to think cross-border
– US fails to invest in transmission
• Project may be risky
– hard to justify charging other consumers
– risky to investor if high profits clawed back by
regulation, but losses not compensated
=> exempt from regulation for period
Newbery - ACCC
26
Increasing EU cross-border capacity
• New investment can be exempted from rTPA
– if investment enhances competition
– for maximum of 15 years? (up to NRAs)
– but not exempt from Art 6.3 (must offer), 6.4 (UIOLI)
UIOLI could reduce profitability of IC
withholding can enhance price differences, profits
Could aversely affect whether built or what size
Newbery - ACCC
27
Gas pipelines
• Typically built with long-term ToP contracts
• Investment financed on guaranteed revenues
• Maturity and liberalisation shift balance from
securing investment to efficient use
• evolution via nTPA to rTPA resisted
– US demonstrates gains from unbundling
– EU Energy Sector Inquiry finds refusal to supply
Newbery - ACCC
28
Transit pipelines deny access
Source: Energy Sector Inquiry 2005/2006 fig 27
Newbery - ACCC
29
Withdrawing from regulation
• where promoting competition feasible
– regulators like to self-perpetuate
– objective is to replace regulation if possible
• Oftel advocated facilities-based competition
– even if raised costs by 20%
=> local loop unbundling costly, penetration rose
• withdrew from regulating fixed line
• EU moving to competition remedies
Newbery - ACCC
30
EC Communications Directives
• markets effectively competitive where no
operator has Significant Market Power (SMP)
• NRAs can only impose ex ante regulation if
– market review finds SMP that is likely to persist
• regulation must be
– justified in relation to Directive’s objectives
– appropriate, necessary, proportionate
=> regulation to mimic competition?
– But benefits must exceed regulatory costs
Newbery - ACCC
31
Mobile call termination
• Initially unregulated:
– dynamic market, MNOs not making profits
– mark-up on termination subsidises handsets
• under Calling Party Pays no competition in
market for termination => SMP => regulate!
=> Lengthy dispute on how to set the mark-up
Receiving Party Pays or bill-and-keep removes
need for regulation
Newbery - ACCC
32
Conclusions on Regulatory Risk
• Inevitable for essential facilities
• Vexatious claims to bolster dominance or to
seek better negotiating position?
• Objective: restrain abusive market power
and regulatory inefficiency/opportunism
– encourage user agreements, regulatory holidays
– clarity, case law, precedent, guidelines and
benchmarking to reduce opportunism
– trusted dispute resolution procedures
Newbery - ACCC
33
Regulatory Risk
David Newbery
Eighth ACCC Regulatory Conference
The evolution of regulation
26-27 July 2007
Gold Coast, Queensland
http://www.electricitypolicy.org.uk
Regulating essential facilities
• Cost of regulation: less investment, innovation
• Benefit: efficiency not competition test?
– Competition is a (powerful) means to the end
– increasing competition abroad perverse?
• Ex ante risk should be reflected in ex post
WACC - but hard to estimate
– option value approach proposed for US railroads
• Regulatory holidays support risky stand-alone
investments - but what of increments?
Newbery - ACCC
35