Transcript Document
ENUMCLAW REGIONAL HOSPITAL BULLETIN CONSTRUCTION BULLETIN April 26th , 2010 The following activities are scheduled for the week of April 26th, 2010 Our painters are mobilizing on site this week to begin painting on Level 1 from North to South this week. A weekly update of construction activities at Enumclaw Regional Hospital. Jobsite Contact: Roofers will continue up on Level 3 with the roof membrane system and, with some help from mother nature, will finish up this week. We received the balance of our wall cover inspections for Level 1 last week releasing the drywallers to cover up the remainder of the floor this week. MEP wall rough-in is wrapping up on Level 1 and has a good jump on Level 2. This work will be progressing from North to South on Level 2 this week (see picture below). Bill Johnson Project Superintendent 206.786.3640 [email protected] Allison Parker Project Engineer 360.802.3848 [email protected] Fun Facts: - 37,876 CY dirt hauled offsite - 21,164 CY structural fill imported and placed -5,525 CY concrete poured to date Note: All site visits must be scheduled in advance through Cindy Stephan at (360) 272-4017 or [email protected] SAFETY ALERT: Please note that for the safety of the community and construction personnel, it is necessary to heed flagger’s directions at all times.