ENUMCLAW REGIONAL HOSPITAL
BULLETIN
CONSTRUCTION BULLETIN
April 26th , 2010
The following activities are scheduled for the week of April 26th, 2010
Our painters are mobilizing on site this week to begin painting on Level 1 from
North to South this week.
A weekly update of construction
activities at Enumclaw Regional
Hospital.
Jobsite Contact:
Roofers will continue up on Level 3 with the roof membrane system and, with some
help from mother nature, will finish up this week.
We received the balance of our wall cover inspections for Level 1 last week releasing
the drywallers to cover up the remainder of the floor this week.
MEP wall rough-in is wrapping up on Level 1 and has a good jump on Level 2. This
work will be progressing from North to South on Level 2 this week (see picture
below).
Bill Johnson
Project Superintendent
206.786.3640
[email protected]
Allison Parker
Project Engineer
360.802.3848
[email protected]
Fun Facts:
- 37,876 CY dirt hauled offsite
- 21,164 CY structural fill
imported and placed
-5,525 CY concrete poured to
date
Note: All site visits must be
scheduled in advance through
Cindy Stephan at (360) 272-4017 or
[email protected]
SAFETY ALERT:
Please note that for the safety of the community and construction personnel, it is
necessary to heed flagger’s directions at all times.