MSC PC-PC Transfer System (PPTS)

Download Report

Transcript MSC PC-PC Transfer System (PPTS)

BEST, U-LAN, and C-LAN
Program Brief
OVERVIEW
This Briefing is UNCLASSIFIED
1
BEST/INMARSAT
Bandwidth Efficient Satellite System
• Functional Connectivity Requirement
– BEST functionality to be relocated to the
New Comm Shelter.
– Provide Primary SIPRNET Connectivity
– Provide Backup NIPRNET Connectivity
– SMIS (MSC) U-LAN and C-LAN
Connectivity to be relocated to New Comm
Shelter.
– BEST Bandwidth will be used for Exercise.
2
BEST
Bandwidth Efficient Satellite System
• SIM
– Relocate BEST/LAN rack from
Communications/Radio Room to
Comm Shelter.
• ISS
– Power up BEST rack.
– SOVT BEST rack to include
NIPRNET and SIPRNET connectivity.
– Provide Training for BEST Operation.
3
U-LAN
• ISS
– Relocate Marine COT SMIS NIPRNET workstation to
Shelter.
– Relocate Marine Communications/Radio Room SMIS
NIPRNET workstation to Shelter.
– Configure SMIS NIPRNET Network
– Test all SMIS NIPRNET workstations using the new
connections on NIPRNET in the Shelter.
– Install KVM switches on the two (2) SMIS NIPRNET
workstations in the Marine Admin. Space for NTCSS
Compatibility/Backup.
4
C-LAN
• SIM
– Install SMIS C-LAN Fiber Backbone.
– Install Seven (8) C-LAN Wyse terminals (4 in hold 6, 1
in Marine Admin, 1 in Marine COT, 2 in Comm
Shelter).
– Install dedicated C-LAN printer for C-LAN server in
Shelter.
• ISS
– Relocate the SMIS C-LAN workstation from the Marine
Communications/Radio Room to the Shelter.
– Configure SMIS C-LAN server.
– Configure SMIS C-LAN Wyse terminals.
– SOVT C-LAN.
– Configure C-LAN client accounts.
5
– Train C-LAN administrator and users.
6
POA&M
• BEST and NIPRNET SOVT – Two (2)
days once Bandwidth is established.
• C-LAN and SIPRNET Configuration/
SOVT
– Five (5) days from end of C-LAN HM&E.
• Possible delays – Availability of BEST
Bandwidth and SIM HM&E.
7
Issues
– Determine SMIS SIPRNET workstation requirement for
in the Marine Communications/Radio Room to the
Shelter.
– Validate SMIS U-LAN Workstation Requirements
– Validate SMIS C-LAN Workstation Requirements.
• Need to Coordinate the Thin-client Workstation
Installation for Designated Containers
– Validate SMIS SIPRNET Email Account Requirements
– Provide Personnel List for Training for BEST/U-LAN/
C-LAN and Availability for Training.
– Bandwidth Limitation is an Issue. Limited to what is
available at time of Exercise.
– Need to Address all IA Issues
8
QUESTIONS?