WILDCAT CREEK TRUNK SEWER RELOCATION PROJECT
Download
Report
Transcript WILDCAT CREEK TRUNK SEWER RELOCATION PROJECT
2006 Sewer Smart Summit
WVSD SANITARY SEWER REHABILITATION PROGRAM
Presented by
Peter V. Sevcik, P.E.
West Valley Sanitation District
Campbell, California
West Valley Sanitation District
Special District formed in 1948 to provide sewer
service in western Santa Clara Valley
29 square mile service area with 120,700
customers and 44,500 connections
District facilities include 426 miles of sewer
mains and 250 miles of laterals
Average age of pipe in system estimated at
approximately 45 years, some as old as 90+ years
Majority of pipe 6 inch diameter vitrified clay
Condition Assessment
2000 Basin Rehabilitation Strategic Plan
–Prioritized the order in which areas were to be televised
based on dry weather flow data and maintenance history
In-House CCTV Inspection Program
–District is in the process of televising entire system
–Identifying pipe that needs to be replaced or
rehabilitated
–Annual goal to televise 200,000 feet
–930,000 feet televised since 2001
Project Planning
Review of CCTV Inspection
–Engineer reviews digital CCTV data and video
–Group project areas by sub-basin and prioritize by
severity of defects identified
–Approximately 12,000 to 15,000 feet per project
Plans and Specifications
–In-house with consultant assistance
Geotechnical Report
–Determines whether trenchless methods possible
Project Planning
Opportunity to optimize system configuration
Annual capital expenditure of $2,500,000 for
rehabilitation not including trunk sewers
CIP funding built into rate structure
103,000 feet rehabilitated to date at a cost of
$11.3 million
Starting in FY 06-07, annual capital expenditure
increasing to $4,000,000 per year
Rehabilitation Options
Utilized by WVSD
Cured-In-Place Pipe (CIPP)
Pipe Bursting
Pipe Reaming
Horizontal Directional Drilling (HDD)
Cured-In-Place Pipe
Resin-saturated tube inserted into existing pipe
Tube is expanded and cured by steam or hot water
Final product is pipe within a pipe
Existing sewer laterals are reinstated internally
with a remote controlled cutter
No excavation required
No change in pipe capacity
Pipe Bursting
Utilizes a heavy-duty winch to pull a cracking
head that breaks the existing pipe into pieces
New pipe is simultaneously pulled into the newly
formed void
Allows use of larger diameter pipe
Excavation limited to entrance and exit pits as
well as lateral connections
Can also be used to replace lower lateral
Pipe Reaming
Utilizes a horizontal directional drilling machine
and modified cutter head
Grinds existing pipe into smaller pieces that are
carried out with other excess materials by drilling
fluid to exit pit
New pipe is simultaneously pulled into place
Allows use of significantly larger diameter pipe to
replace existing pipe
Excavation limited to entrance and exit pits
Horizontal Direction Drilling
Utilizes a horizontal directional drilling machine
to install a new pipe where no pipe currently exists
Process starts with pilot hole drilled to desired
grade
Hole is then enlarged by back reaming while new
pipe is simultaneously pulled into place
Not recommended for gravity sewers with a
design slope of less than 1.5%
Rehabilitation Benefits From
Collection System Viewpoint
Reduced potential for SSOs
Reduced O&M costs
Potential to increase capacity
Improved customer service
Continued protection of water quality
Questions?
Peter V. Sevcik, P.E.
West Valley Sanitation District
408-378-2407
[email protected]