Mitchem, Sean - Edison Electric Institute
Download
Report
Transcript Mitchem, Sean - Edison Electric Institute
DC Fast Charging and Impacts to the
Grid
Sean C. Mitchem
Southwest Research Institute
®
Southwest Research Institute (SwRI )
®
San Antonio, Texas
About 3000 Employees
1,200 acre facility
Research, Development,
Test, and Evaluation
Multidisciplinary Expertise
Non-Profit
Confidential
SwRI develops the technology that makes the
world “work”!
2
PEVs as Grid Resources
How can a PEV act as a grid resource?
Frequency regulation
Demand charge mitigation
Peak shaving
How does a PEV act as a grid resource?
Through careful, thoughtful planning…
Dedicated, continuous systems engineering…
Outline
DC Fast Charge
SPIDERS program
Vehicle aggregation as key to V2G
SPIDERS performance testing
Fast responding regulation
Grid impacts, benefits, and mitigations
Wrap-up
DC Fast Charging
Direct current from charger to vehicle
Converter/inverter located in charger, not vehicle
Power from 0-60kW
Based on current converter technology
480V 3-phase, 100-200 amp service
SAE Standard is up to 100kW, 500VDC 200amp
Charge times typically < 1 hour
Battery sizes 20 – 110kWh
Keys to Successful DC/FC Deployment
Integrated system
Aggregation
Value proposition important
Energy management (fleet)
Energy management (facility)
Ancillary services (fleet owner value proposition)
What’s not considered?
Utility Impact!
Power always there and available
Can push it back onto grid without any consequences
Develop a secure microgrid utilizing renewables and PEVs
The SPIDERS Microgrid at Fort Carson
• 1.1 MW Critical Load, 1 MW
Priority Load
• 3.25 MVA diesel backup
generation (three units)
• 2 MW Solar Array
• 5 Non-tactical PEVs with DC
Fast Charge V2G Capability
Intended to provide cost reduction and
revenue generation through demand
response, peak shaving, and providing
ancillary services.
SPIDERS Phase II Schedule
75% Design – September 2012
95% Design – November 2012
Break Ground – January 2013
EVSE Installation – June 2013
System Acceptance Testing – August 2013
Technical Demonstration – September 2013
Operational Demonstration – October 2013 (third party evaluation)
Grid Services – Economic Demo – November 2013
Project Final Reports – December 2013
SPIDERS PEV Components
Boulder EV
50 kW
80 kWh
• Smith EV
• 40 kW
• 60 kWh
• Coritech DC EVSE
– 83 kVA BiDirectional
– SAE DC Combo
SAE DC/FC
(What’s Significant for V2G)
J1772 – SAE EV & PHEV Conductive Charge Coupler
Definition for DC Fast Charging with Off-Board Charger
Bi-Directional Power Flows
PLC Communications
One plug for AC and DC connections
Variable charge/discharge control
Increases power flows significantly
3.3 – 6.6/19.2 kW for AC Level 1 & 2
0 - 100 kW for DC fast charging
DC/FC Vehicle Interface for SPIDERS
First operational deployment of SAE J1772 Bi-Directional Fast
Charger
Standard around SAE J1772 Combo Connector and
communications standards
Importance of common connectivity
Integration with 2 PEV manufacturers
Aggregation of Vehicles
Present vehicle fleet as a single generation resource / load
resource entity
Hide details of PEV management from grid
Balance grid opportunities with PEV driver needs
Take advantage of
DC charge / discharge times
Frequency of PEV idle times
Manage real power and reactive power
Reactive Power Management
Use EVSEs to assist in kVAR control – positive $$
Done with or without PEVs connected
Savings realized through
Reduction of facility PF penalty when grid tied
Reduced fuel costs when in microgrid mode through more
efficient gen set operation
Aggregator manages reactive power in similar manner to real
power
Capacity Testing
kVAR
400
MAX
CAPACITY
350
300
250
200
150
100
50
kW
0
-300
-250
-200
-150
-100
-50
0
50
100
150
200
250
-50
-100
-150
-200
-250
-300
-350
-400
MAX TARGET
VEHICLE
CAPACITY
300
Time Response Testing
September 17th
September 18th
150.0
200
EVS-KW
100.0
100
0
10:55
50.0
11:02
11:09
11:16
11:24
11:31
11:38
11:45
11:52
12:00
0.0
11:42
-100
-50.0
-200
EVS-KVAR
-300
-400
EVS-KVAR
EVS-KW
-100.0
-150.0
11:45
11:48
11:51
11:54
11:57
12:00
12:02
12:05
Summary of SPIDERS
System engineering key to program results to-date
Operational deployment of five 55 kW DC/FC using SAE
standards
PEV fleet aggregated into single source for microgrid / grid
controller interface
+/- 275 kW
+/- 375 kvar
Fast Frequency Regulation
(Another example of PEVs as a grid resource)
Fast responding regulation service (FRRS)
Use of fast-acting (less than 1 second to full response)
resources to counter frequency variations
Being implemented in all US ISOs – FERC Order 755 and 784
ERCOT FRRS Pilot Feb 2013 to Feb 2014
Use of PEV delivery fleet to provide FRRS Reg-Up service
AC Level II chargers
10-12 kW max load
Monitor grid frequency and automatically provide service
.09Hz deviation from 60Hz
Implement full bid capacity
FRRS Program
Project team – Center for the Commercialization of Electric
Technologies, Frito-Lay, ERCOT, Southwest Research Institute
Objectives
Aggregate PEV fleet to respond to FRRS Reg-Up
No impact to fleet operational schedule
Characterize available performance/revenue generation
FRRS program participation – November 2013
Wrap-up
System engineering key to success
V2G value proposition important, stakeholder appreciation
V2G through DC/FC using SAE Combo Connector with
two vehicle platforms
Aggregation of PEV kW and EVSE kvar
The system is on the ground, installed, tested, and works!!!
FRRS – another V2G opportunity
Utility Impacts of DC Fast Charging
Sudden 20-50kW variable loads can be significant on local
distribution
Multiple DC/FC loads even greater problem
Ft. Carson is a potential 250kW load
Most DC/FC loads will be during peak times, not nights
Individual DC/FC loads of more concern than fleet loads
Fleets can be controlled with aggregation
Individual loads mean unpredictable usage
Most aggregation ideas focus on pricing advantages, not loads
Would wait until evening to charge, but would charge all at
once rather than spreading them out over several hours
DC/FC Benefits to Grid
Controllable Load Resources
Regulation-type Services
Demand Services
Short-term Reserves
Distribution voltage support through reactive power
management
Solar feeding variable power at unity power factor
Short-term reverse power flows
Utilize for congestion management
Increased storage capability for renewables
Mitigation of V2G Impacts
Pricing incentives specific to PEVs
TOU
Special pricing (on separate meter)
Reactive power incentive
Other? (based on aggregated load?)
Factoring aggregated PEV capacity in SCED decisions
Utility aggregation control
Specific control signals for aggregated PEV fleets
Utilization of reactive power capabilities (where available)
Aggregation of aggregators
New ancillary services
FRRS
Summary
V2G is here now, and is increasing
AC systems mostly providing demand response
PEV Frequency regulation being tested in PJM
Fleet DC/FC implemented in Colorado Springs
Fleet Fast FR being built in ERCOT region
Extensive charger infrastructure in CA, Washington state
Utilities need to plan now for impacts and develop
mitigations
T&D can benefit from increase in grid storage capabilities
For More Information Contact:
Sean C. Mitchem
Principal Analyst
Southwest Research Institute
210-522-2698
[email protected]