HE UTTAR PRADESH FIRE
PREVENTION AND FIRE
SAFETY RULES 2005
MINIMUM STANDARDS
MEANS OF ACCESS

• Width of street on which building abuts

shall be min 12 M

• The road shall not terminate on dead end.

• Open space around building should not be

used for parking.

• Main passage should not be less than 4.5M

and gate arch not less than 5M height.
UNDERGROUND / OVER
GROUND STATIC TANKS

Water replenishment min 1000 lpm.

In case of tank in pathway. Covering slab
should withstand min 22.5 ton vehicular
load.

Water tank should feed the domestic water
tank by overflow.

FB inlet 4/2 way at street level connected
with static tank. 150 mm pipe.
AUTOMATIC SPRINKLER
SYSTEM

BASEMENT CAR PARK IF AREA
EXCEED 200 SQ M

ANY ROOM / COMPARTMENT

EXCEEDING 1125 SQ M

DEPARTMENT STORE EXCEEDING
750 SQ M

ALL FLOORS BUILDING OVER 30M
FIRST AID HOSE REELS


Should be provided with 30 M long hose
pipe on every floor.

Min dia of hose should be 19mm.

Connected with riser / down comer.
FIRE EXTINGUISHER

A-Fires in Ordinary combustibles (Wood, Vegetable
fibres, rubber, plastics, Paper and the likes). Gas expelled

Water and Antifreeze type extinguishers and Water
Buckets.

B-Fires in flammable liquids, paints, grease, solvents and
the likes. Chemical Extinguishers of Carbon dioxide type
and Dry Powder type and Sand Buckets.

C-Fires in Gaseous substances under pressure and
liquefied gases. Chemical Extinguishers of Carbon di
oxide and Dry Powder type.

D-Fires in reactive chemicals, Active metals and the
likes. Special type of Dry Powder, Extinguishers and sand
buckets
FIRE EXTINGUISHER





One 9-litre water/sand bucket shall be provided for every 100 sq. m of the floor area or part
thereof and one 9-litre water type extinguisher shall be provided to six buckets or part thereof
with a minimum of one extinguisher and two buckets per compartment of the building.
Acceptable replacement WATER BUCKETS Water type Extinguishers For each 9 litre
Extinguisher For one bucket For two buckets Dry Sand1 bucket 3 bucket ---Carbon-di-Oxide
Extinguishers(IS: 2878)03 Kg.09 Kg09 KgDry Powder Extinguisher(IS: 2171)02 Kg 05 Kg
05 Kg(In one or more extinguishers)
For rooms containing electrical transformers, switchgears, motors and/or electrical apparatus
only, not less than two 2 Kg dry powder or carbon dioxide type of extinguishers shall be
provided within 15 m of the apparatus.
Where motors and/or other electrical equipments are installed in rooms other than those
containing such equipments only, one 5 Kg dry powder or carbon di oxide extinguisher shall
be installed within 15 m of such equipments in addition to the requirement of rules 4.1.3.2
and 4.1.3.4 for this purpose, the same extinguisher may be deemed to afford protection to all
apparatus within 15 m thereof.
Where electrical motors are installed on platforms, one 2 Kg dry powder or carbon di oxide
extinguisher shall be provided on or below each platform.
COMPARTMENTATION

ALL FLOORS SHALL BE
COMPARTMENTED WITH AREA NOT
EXCEEDING 750 SQ M BY A
SEPERATION WALL WITH 2 H FIRE
RATING
Automatic Fire Detection system /
Manually operated alarm System

Automatic Fire Detection system /
Manually operated alarm systems is to be
provided in all the buildings as per the
provisions laid in NBC.
PUBLIC ADDRESS SYSTEM

In large and hi rise building PA system
linked with the automatic fire alarm system
should be provided.
ILLUMINATED EXIT WAY
MARKING SIGNS

All the exits should be clearly marked.

Illuminated signage should be fixed at all
exit routes and points to assist in effective
evacuation of people in case of emergency.
ALTERNATE SOURCE OF
ELECTRIC SUPPLY

All hi rise buildings should have provision
of alternative source of power supply for
emergency lights and pumps.
WET RISER / DOWN COMER

Wet Riser / Down comer to be provided as
per the provision laid in NBC.
SET BACK

All buildings should have necessary set
back clear of all construction as per NBC.
FIRE DRILL

All high rise buildings should practice Fire
Drill for fast and effective evacuation in
case of emergency.
MAINTAINANCE OF FIRE
FIGHTING SYSTEM

The Fire protection system should be
regularly maintained by competent agency
so that they are operative in case of
emergency.
STAFF TRAINING FOR
OPERATION OF FIRE FIGHTING
SYSTEM

All high rise should have trained staff to
operate the fire protection system.
EVACUATION PLAN AND
DRILL
PERIODICAL FIRE SAFETY
AUDITS

PERIODIC RENEWAL OF FIRE
CLEARANCE AFTER
DEPOSITING PRESCRIBED FEES
To be done as per requirement of Fire
Department