Transcript Document
LHC Status - SUSY 2010 - Bonn 24.08.2010 Status of the LHC 6 months of beam operation in 2010 J. Wenninger CERN Drawing by Sergio Cittolin 1 24.08.2010 LHC Status - SUSY 2010 - Bonn Outline Introduction 2 The Large Hadron Collider LHC Installed in 26.7 km LEP tunnel Depth of 70-140 m Lake of Geneva LHC Status - SUSY 2010 - Bonn CMS, Totem Control Room LHCb ATLAS, LHCf 24.08.2010 ALICE 3 LHC layout and parameters 8 arcs (sectors), ~3 km each 8 long straight sections (700 m each) beams cross in 4 points 2-in-1 magnet design with separate vacuum chambers → p-p collisions RF Nominal LHC parameters Beam energy (TeV) 7.0 No. of particles per bunch 1.15x1011 No. of bunches per beam 2808 Stored beam energy (MJ) 362 Transverse emittance (μm) 3.75 Bunch length (cm) 7.55 - β* = 0.55 m (beam size =17 μm) - Crossing angle = 285 μrad - L = 1034 cm-2 s-1 4 LHC accelerator complex ≥ 7 seconds from source to LHC Beam 1 Beam 2 TI8 TI2 LHC proton path The LHC needs most of the CERN accelerators... 5 LHC challenges The LHC surpasses existing accelerators/colliders in 2 aspects : The energy of the beam of 7 TeV that is achieved within the size LHC Status - SUSY 2010 - Bonn constraints of the existing 26.7 km LEP tunnel. LHC dipole field 8.3 T A factor 2 in field HERA/Tevatron A factor 4 in size ~4T The luminosity of the collider that will reach unprecedented values for a hadron machine: LHC pp ~ 1034 cm-2 s-1 Tevatron pp 3x1032 cm-2 s-1 SppS pp 6x1030 cm-2 s-1 A factor 30 in luminosity Very high field magnets and very high beam intensities: Operating the LHC is a great challenge. 24.08.2010 There is a significant risk to the equipment and experiments. 6 LHC dipole magnet 1232 dipole magnets. B field 8.3 T (11.8 kA) @ 1.9 K (super-fluid Helium) Operating challenges: o Dynamic field changes at injection. o Very low quench levels (~ mJ/cm3) 2 magnets-in-one design : two beam tubes with an opening of 56 mm. 24.08.2010 LHC Status - SUSY 2010 - Bonn 7 Stored energy Increase with respect to existing accelerators : • A factor 2 in magnetic field • A factor 7 in beam energy 24.08.2010 LHC Status - SUSY 2010 - Bonn • A factor 200 in stored beam energy Damage threshold 8 Collimation To operate at nominal performance the LHC requires a large and complex collimation system o Previous colliders used collimators mostly for experimental background conditions. 24.08.2010 LHC Status - SUSY 2010 - Bonn 1.2 m beam Ensure ‘cohabitation’ of: o 360 MJ of stored beam energy, o super-conducting magnets with quench limits of few mJ/cm3 Almost 100 collimators and absorbers. Alignment tolerances < 0.1 mm to ensure that over 99.99% of the protons are intercepted. Primary and secondary collimators are made of Carbon to survive large beam loss. 9 24.08.2010 LHC Status - SUSY 2010 - Bonn Outline LHC energy 2010/11 10 LHC target energy: the way down When All main magnets commissioned for 7TeV operation before installation 7 TeV Why 2002-2007 Design 12 kA LHC Status - SUSY 2010 - Bonn Detraining found when hardware commissioning sectors in 2008 – 5 TeV poses no problem – Difficult to exceed 6 TeV Machine wide investigations following S34 incident showed problem with joints Commissioning of new Quench Protection System (nQPS) 5 TeV Summer 2008 Detraining 9 kA 3.5 TeV 6 kA 1.18 TeV Late 2008 Spring 2009 Nov. 2009 Joints nQPS 24.08.2010 2 kA 450 GeV 11 LHC target energy: the way up When Train magnets – 6.5 TeV is in reach – 7 TeV will take time 24.08.2010 LHC Status - SUSY 2010 - Bonn Repair joints Complete pressure relief system What Commission nQPS system 7 TeV 6 TeV 3.5 TeV 2014 ? Training 2013 Stabilizers 2011 nQPS 2010 1.18 TeV 2009 450 GeV 12 LHC Status - SUSY 2010 - Bonn Ramp rate At the start of the run the ramp rate had to be limited to 2 A/s (1.2 GeV/s) for magnet protection reasons. o Ramp duration 0.45-3.5 TeV: 46 minutes Since mid-July the rate for down-ramps and magnet pre-cycles (magnetic history reset) were increased to nominal value of 10 A/s (6 GeV/s). Ramp speed with beam will be increased to 10 A/s (6 GeV/s) in September. o Ramp duration 0.45-3.5 TeV: 16 minutes 3500 GeV 2 A/s 10 A/s 24.08.2010 450 GeV 13 24.08.2010 LHC Status - SUSY 2010 - Bonn Outline LHC performance targets and achievements 14 Collider luminosity N 2kb f N 2kb f L F F * 4s xs y 4b e 24.08.2010 LHC Status - SUSY 2010 - Bonn Parameters: – Number of particles per bunch – Number of bunches per beam – Beam sizes at the collision point – Betatron function (focusing) at IP – Normalized transverse emittance s b* e – Revolution frequency – Crossing angle factor f Collision rate is proportional to luminosity kb Intensity Interaction Region Beam quality (emittance) F~1 “Thus, to achieve high luminosity, all one has to do is make (lots of) high population bunches of low emittance to collide at high frequency at locations where the beam optics provides as low values of the amplitude functions as possible.” PDG 2005, chapter 25 15 Collimation performance Present stage collimation system sets limit to total intensity. Collimator settings Assumptions: Max. loss rate of 0.1%/s assumed (0.2h lifetime). o Ideal cleaning. LHC Status - SUSY 2010 - Bonn o Performance degradation: Deformed jaws. o Tilt & offset & gap errors. o Machine alignment. o Machine stability Tight coll. settings are a challenge at early stage. o Intermediate coll. settings make use of aperture to relax tolerances. o Imax ~61013 protons per beam at 3.5TeV with intermediate collimator settings (about 20% nominal intensity) 24.08.2010 30 MJ stored beam energy 16 Goals for 2010-2011 2009 Repair of Sector 34 No Beam 2010 1.18 nQPS TeV 6kA B 3.5 TeV Isafe < I < 0.2 Inom β* ~ 3.5 m 2011 Ions 3.5 TeV ~ 0.2 Inom Ions β* ~ 3.5 m Beam Beam Goal for the 2010-11 run: Collect 1 fm-1 of data/exp at 3.5 TeV/beam. To achieve this goal the LHC must operate in 2011 with L ~ 21032 cm-2s-1 ~ Tevatron Luminosity which requires ~700 bunches of 1011 p each ~ 7x1013 p (stored energy of ~30 MJ – 10% of nominal) Implications: Strict and clean machine setup. Machine protection systems at near nominal performance. 17 Commissioning phases 24.08.2010 LHC Status - SUSY 2010 - Bonn Phase 1: low intensity commissioning of the LHC. o Low intensity single bunches. No/very limited risk of damage. o Commissioning of the protection systems. Phase 2: operation without crossing angle. o Bunches with large spacing (> 1 - 2.5 ms). o Up to around kb=50 bunches. o Simplified operation in the interaction regions. o Machine protection system running in. Phase 3: operation with crossing angle. o Bunches with close spacing (≤ 150 ns). o Aim for ~400 bunches in 2010. We are at end of phase 2 18 Commissioning steps in 2010 Restart with beam. Feb. 28th Commissioning to 3.5 TeV. March 24.08.2010 LHC Status - SUSY 2010 - Bonn o Low intensity beams. First collisions at 3.5 TeV. March 30th Squeeze (b* reduction) commissioning. Mid April o Increase number of bunches to 13 per beam. o b* = 2 m for collisions (injection 10 /11 m). Bunch population N = 31010 p ~ 30% of nominal. Switch to nominal bunch intensity. Luminosity ~N2 o Back off in b* to 3.5 m. o Mid-April – mid-May June Gain ~ 10 Loss ~ 0.6 Increase number of bunches up to 49 per beam. July - August Bunch population N = 9-101010 p. o Stability run in August with 25 bunches/beam. o 19 Peak luminosity performance Peak luminosity = 9.51030 cm-2s-1 24.08.2010 LHC Status - SUSY 2010 - Bonn (48 bunches/beam, 36 colliding bunches) 36 colliding pairs 8 colliding pairs/IR 20 Integrated luminosity Integrated luminosity ~ 2.2 pb-1 (23.08.2010) 24.08.2010 LHC Status - SUSY 2010 - Bonn Figures : status 16th Aug 2010 21 Availability About 30% of time in physics data-taking. o A lot commissioning still on-going ! o Min. turn-around time collisions to collisions ~4 hours. 3.5 TeV 24.08.2010 LHC Status - SUSY 2010 - Bonn Energy Lumi 01 – 21 August 2010 6.51030 cm-2s-1 22 24.08.2010 LHC Status - SUSY 2010 - Bonn Outline LHC beam operation 23 Machine Protection Extensive testing of the machine protection system was performed, mostly in March/April 2010. o 20’000 signal enter the beam abort system. about 10% of the beams above injection energy are dumped by the operators ! 24.08.2010 LHC Status - SUSY 2010 - Bonn Only Beam dumped from hardware Machine Protection tests Beam dump by operator Beam interlocks Beam dumps > 450 GeV 24 Beam dump Dump block Complex beam dumping system commissioned. Beam swept over dump surface (power load) 24.08.2010 LHC Status - SUSY 2010 - Bonn Dilution kickers Extraction septum magnets Extraction kickers 25 Aperture and collimation 24.08.2010 LHC Status - SUSY 2010 - Bonn With collisions the aperture limit of the LHC is in the strong focusing quadrupoles (triplets) that are installed just next to the experiments. o Hierarchy of collimators must be preserved in all phases to avoid quenching super-conducting magnets and for damage protection. o b* is presently limited to 3.5 m by aperture and tolerances. Exp. Collimation hierarchy Primary 6σ Secondary 8.8 σ Triplet Tertiary 18 σ Dump Protection 15 σ 10.5 σ 26 Collimation Collimator alignment is made with beam and then monitored from the loss distribution around ring. Beam cleaning efficiencies ≥ 99.98% ~ as designed 24.08.2010 LHC Status - SUSY 2010 - Bonn TCT = tertiary coll. 27 Magnet quenches A local o loss of some ~107 protons/s may lead to a quench at 3.5 TeV. Compared to 51012 stored protons. far no quench was observed at 3.5 TeV thanks to the excellent performance of the collimation system for absorbing lost protons and to the fast reaction of the loss monitors. 24.08.2010 LHC Status - SUSY 2010 - Bonn So In only 5 occasions did some beam escape and was lost locally around super-conducting elements. o Beam loss detection system dumped the beams in time before a magnet could quench. o Events are under investigation... Possible cause are dust particles! The absence of problems with beam loss and quenches is good news for increasing the beam intensity ! 28 Beam Optics Beam optics is within specifications and reproducible over 3 months. o A stable machine is essential to reach high intensity and minimize frequent setup overhead, in particular for collimation. 24.08.2010 LHC Status - SUSY 2010 - Bonn Relative beam size error (Db/b) 10% Specification: 0.2 29 Beam Emittance 24.08.2010 LHC Status - SUSY 2010 - Bonn Beam emittances below nominal can be produced and injected into the LHC (e = 2 mm rad as compared to 3.5 mm rad design). This provides margin for emittance blow-up due to various noise sources – great value for a machine in early phase of operation. Momentum and magnetic fields at the LHC are sufficiently strong for the protons to emit visible light that can be used to image the beams in real-time. The energy loss per turn is 7 keV at 7 TeV, 0.4 keV at 3.5 TeV. Beam emittances in collisions are now mostly at design or below – the only exception being beam 2 in the vertical plane. 30 Noise on the beam The beams are periodically excited by an unknown noise source (‘hump’) of varying frequency – affects mostly beam2 in vertical plane. o Amplitude ~ mm. When the frequency coincides with the beam eigen-modes (‘tunes’) it leads to emittance blow-up. Time Horizontal plane LHC Status - SUSY 2010 - Bonn Beam 1 1 hour Beam 2 Tune Noise hump Beam 1 Beam 2 Vertical plane 4.08.2010 Noise hump Frequency/Rev. frequency 31 Beam-beam interaction of the beam-beam force are visible on the lifetime of the various bunches. o Also sensitive to tune working point. o This will become even more complicated with trains of bunches. - black - red - blue - green witness bunches (zero collisions); bunches colliding in IP 1 5 and 2 (3 collisions); bunches colliding in IP 1 5 and 8 (3 collisions); bunches colliding in IP 2 and 8 (2 collisions). fill 1264 - beam 1 Intensity 10 loss (%) fill 1264 - beam 2 10 Beams in collision Beam1 losses [%] 6 4 0 20 Beam2 8 2 24.08.2010 Beams in collision 8 losses [%] LHC Status - SUSY 2010 - Bonn Effects 6 4 2 30 40 50 time [min] 60 70 0 20 30 40 50 time [min] 60 70 32 Lifetimes Beam intensity lifetimes with colliding beams: o Dip to 2-5 hours in first minutes. o Progressive increase to ~100 hours. Luminosity LHC Status - SUSY 2010 - Bonn o lifetimes: Around 20-30 hours due to emittance growth. Lifetime (h) Beams in collision 300 200 24.08.2010 100 33 Present LHC parameters 24.08.2010 LHC Status - SUSY 2010 - Bonn N 2kb f N 2kb f L F F * 4s xs y 4b e Parameter Present Nominal N (p/bunch) 11011 1.151011 48 2808 2.5-5 3.75 3.5 0.55 6.51030 1034 kb (no. bunches) e (mm rad) b* (m) L (cm-2s-1) Limited by Machine protection Aperture, tolerances Squeezing at the IP (b*) is limited by aperture and tolerances. o Beams are larger at 3.5 TeV ~ 1/. o sx = sy = ~45-60 mm - nominal value is 15 mm at 7 TeV. The number of bunches is limited by machine protection and by the fact that LHC is not yet operated with bunch trains. o Bunch separation is large (>1 ms), no crossing angle at the IR. 34 24.08.2010 LHC Status - SUSY 2010 - Bonn Outline Outlook for 2010/11 and conclusions 35 Fall 2010 reach the target of 1032 cm-2s-1 an intensity increase of factor 10 is required until end of October (start of Pb ion run). To LHC Status - SUSY 2010 - Bonn o But the most important is the slope of the increase! 6 12 12 24 24 24 48 48 96 144 Switch to bunch trains 192 240 288 24.08.2010 24 336 36 Fall 2010-2011 To reach the target of 1032 cm-2s-1, o the intensity must be increased very rapidly, o bunch train operation must be commissioned (1-2 weeks). 24.08.2010 LHC Status - SUSY 2010 - Bonn >> Achievable integrated L is ~ 25-50 pb-1 in 2010. The goal is quite ambitious given the time left before the Pb ion run, but the main point is not the exact final luminosity, but rather that no problems or show-stoppers are encountered on the way. o So far there are no limitations. prospects for a very good run in 2011, 1 fm-1 of data, will be very high with a problem-free intensity (luminosity) increase in 2010. The o But the most important is the slope of the increase! 37 Summary and outlook 2011 Main beam commissioning phase of the LHC ended in June when operation with ~ nominal bunch intensities was established. The LHC is now operating for physics data taking, with some interleaved commissioning activities in view of higher intensity. LHC Status - SUSY 2010 - Bonn Efficiency for physics data taking ~30% with peak luminosities of 9.5x1030 cm-2s-1 Machine protection and collimation systems perform well, and one can anticipate a luminosity increase towards few 1031 to 1032 cm-2s-1 in 2010. Final value for 2010 will depend on machine availability and length of commissioning bunch train operation. A long run at 1032 cm-2s-1 or above is in sight for 2011. 24.08.2010 1 fm-1 of integrated data is in reach. 38