Nessun titolo diapositiva

Download Report

Transcript Nessun titolo diapositiva

ITA/AITES
ITA/AITES – Training Course
TUNNEL ENGINEERING
CONVENTIONAL TUNNELLING PART 2
Prepared by
Harald Wagner
ITA AITES - Vice President
D2 Consult Ltd. Linz, Austria
Seoul - 2006
1/39
1/38
1
Index
Introduction – Principles of Conventional Tunnelling
2
Strategy of Project Development
3
Geological / Geotechnical Design
4
Construction Monitoring
5
Conclusions
Training Course “Conventional Tunnelling - Part 2”
2/39
Content
1




Purpose, scope of work
Principles of conventional tunnelling method
Strategy of project development
Design principles and stages
 Ground investigation
 Geological and geotechnical evaluation
 Detail design (incl. monitoring)
 Contract model and document
 Organisation of project execution
 Management (supervision, risk, safety, claims, etc.)
ITA WG 19 Guidelines
Training Course “Conventional Tunnelling - Part 2”
3/39
1
Principles of Conventional Tunnelling
View the ground as a load-bearing element of support.
The ground reactions is measured, stability confirmed by
monitoring
Requirement for rapid rigid support or slim deformable support
is identified
Contract to allow most economical type of support installation
Conventional tunnelling based on rock classification system
(stand-up time)
Rock class agreed between Contractor and Engineer at the
excavation face
Training Course “Conventional Tunnelling - Part 2”
4/39
1
Tunnelling Operation Equipment
Training Course “Conventional Tunnelling - Part 2”
5/39
Strategy of Project Development
2
The project development stages of a tunnel project are
subdivided into 4 different stages:
–
–
–
–
conceptual design
preliminary design
tender design (detailed design, phase 1)
construction design (detailed design, phase 2).
Training Course “Conventional Tunnelling - Part 2”
6/39
2
Conceptual Design
Design documents include:
– Scope and verification of design basis
– Alignment studies and selection of preferred alignment
– Geotechnical characterisation
– Tunnel construction with respect to environmental aspects
– Preliminary cost estimate
– Preliminary construction programme.
– Ventilation concept (for transportation projects only).
Training Course “Conventional Tunnelling - Part 2”
7/39
2
Forepoling in Soft Ground
Training Course “Conventional Tunnelling - Part 2”
8/39
2
Preliminary Design 1
The preliminary design includes:
– Designers contribution to site investigation
– Evaluation of site investigation and lab testing results
– Portal location, slope and structure design
– Cross section development, geotechnical requirements
– Decision on tunnel advance methods
– Tunnel waterproofing and drainage concepts
Training Course “Conventional Tunnelling - Part 2”
9/39
2
Preliminary Design 2
The preliminary design includes:
– Particular requirements regarding operation and safety
– Construction concepts, water and power supply, roads, deposit
– Land acquisition documentation, building restrictions
– Detailed construction programme
– Revised cost estimate
Training Course “Conventional Tunnelling - Part 2”
10/39
2
Shotcreting at the Face
Training Course “Conventional Tunnelling - Part 2”
11/39
Tender Design
2
–
–
–
–
–
–
–
Detail design of all structures
Incorporation of latest project developments
Results of additional site investigations
Update of geotechnical prognosis
Support measures drawings
Distribution of support classes
Detailing of auxiliary construction methods
Training Course “Conventional Tunnelling - Part 2”
12/39
2
Final (Construction) Design
– Aim of conventional tunnelling contracts is adaptation
of detailed design to requirements of excavation and
support and to geotechnical conditions on site.
– Production of design drawings to be used for
construction (e.g. formwork drawings, reinforcement
drawings and schedules, fabrication drawings etc.).
Training Course “Conventional Tunnelling - Part 2”
13/39
2
Invert Reinforcement
Training Course “Conventional Tunnelling - Part 2”
14/39
3
Geological / Geotechnical Design
Phase 1: Design
Determining of
– Rock Mass Types (RMT)
– Rock Mass Behaviour Types (BT)
– Excavation classes determination based on BT and E&S
method
The design should also contain
– Baseline Construction Plan
– Results to be summarized in Geotechnical Report
Training Course “Conventional Tunnelling - Part 2”
15/39
3
Geological / Geotechnical Design
Phase 2: Construction
– Geotechnical relevant rock mass parameters to be
collected, recorded, and evaluated to determine the
Rock Mass Type
– Monitoring data together with Rock Mass Type allows
the behaviour type to be determined
– Excavation and support measures following criteria of
Baseline Construction Plan and Safety Management
Plan.
Training Course “Conventional Tunnelling - Part 2”
16/39
3
Final Lining Reinforcement
Training Course “Conventional Tunnelling - Part 2”
17/39
3
Geological / Geotechnical Design
Design Structuring
Step 1:
Determination of Rock Mass Types
Step 2:
Determination of Rock Mass Behavior Types
Step 3:
Determination of Excavation and Support
Step 4:
Geotechnical Report-Baseline Construction Plan
Step 5:
Determination of Excavation Classes
Training Course “Conventional Tunnelling - Part 2”
18/39
3
Geotechnical Report – Content 1
− Summary of geological / geotechnical investigations,
interpretation of results
− Rock Mass Types and associated key parameters
− Rock Mass Behaviour Types, influencing factors
− Analyses performed
− Geotechnical model on which BT is based
Training Course “Conventional Tunnelling - Part 2”
19/39
3
Geotechnical Report – Content 2
– Report on determination of excavation and support
– Relevant scenarios, analyses, results
– Baseline Construction Plan
– Detailed specifications to BCP
–
(system behaviour, measures on site, warning criteria)
– Report on excavation classes, distribution
Training Course “Conventional Tunnelling - Part 2”
20/39
3
Top Heading / Bench Excavation
Training Course “Conventional Tunnelling - Part 2”
21/39
3
Baseline Construction Plan - Content
Summary of geotechnical design containing
– Geological model with distribution of RMT and BT
– Sections for construction to be specifically observed
– Excavation and Support Types (round length, excavation
sequence, support quality and quantity, etc.)
– Measures to be determined on site (support ahead of the
face, face support, ground improvement, drainage, etc.)
– System Behaviour (behaviour during excavation,
deformation characteristics, utilization of supports, etc.)
– Warning criteria and safety management plan
Training Course “Conventional Tunnelling - Part 2”
22/39
3
Geotechnical Safety Management Plan
Covering following topics
– Design concept for determination of excavation and
support
– Criteria for assessment of stability based on knowledge of
ground conditions during design
– Monitoring concept with all technical and organizational
provisions to allow a continuous comparison between
expected and actual conditions
Training Course “Conventional Tunnelling - Part 2”
23/39
3
Tunnel Face in Hard Rock
Training Course “Conventional Tunnelling - Part 2”
24/39
3
Baseline Construction Plan - Content
Construction structured into
– Step 1 – Determination of encountered Rock Mass Type
– Step 2 – Determination of Rock Mass Behaviour Type
– Step 3 – Determination of Excavation and Support
– Step 4 – Verification of System Behaviour
Training Course “Conventional Tunnelling - Part 2”
25/39
4
Construction Monitoring
– State of the Art Data Evaluation
– The problems experienced when tunnelling through poor
rock and fault zones are well known all over the world.
– Proper modelling during design, continuous and adequate
monitoring of behaviour of rock mass and support structure
forms basis for on site decisions.
Training Course “Conventional Tunnelling - Part 2”
26/39
4
Survey in Construction
Training Course “Conventional Tunnelling - Part 2”
27/39
4
Monitoring Scheme in Section
Training Course “Conventional Tunnelling - Part 2”
28/39
4
Displacement History Plots
Value of Information
– Assuming continuous face advance, displacement rate
over time has to decrease
– Displacement acceleration indicates destabilisation,
unless there are ongoing construction activities in the
monitored tunnel section (e.g. bench and invert
excavation, or shaping activities)
– Stabilisation is reached after bench and invert excavation
Training Course “Conventional Tunnelling - Part 2”
29/39
4
Typical Displacement History Diagram
Typical displacement history diagram, showing expected behaviour and
indication of destabilisation
Training Course “Conventional Tunnelling - Part 2”
30/39
4
Final Displacements
Final displacements extrapolated from few readings, using
previous experience and including the actual geological situation
Training Course “Conventional Tunnelling - Part 2”
31/39
4
Deflection curves
Value of Information:
– When showing several deflection curves on the same plot,
comparison of displacements along tunnel is possible
– Information on the longitudinal extent of tunnel
deformation behaviour is provided
– Trends of relative decreasing or increasing rock mass
behaviour can be verified
Training Course “Conventional Tunnelling - Part 2”
32/39
4
Extrapolation of Deflection Curves
The extrapolation of deflection curves to the tunnel face and the addition of the resulting
difference ("pre-displacements") to the measured values
Training Course “Conventional Tunnelling - Part 2”
33/39
4
Typical plot of deflection curve
Typical plot of deflection curves when excavation approaches a "weak" zone
(schematically)
Training Course “Conventional Tunnelling - Part 2”
34/39
4
Trend Lines
Value of Information
– Trend lines provide an overview of displacement
development along tunnel axis, used for extrapolation
beyond face
– Trend lines used to determine appropriate support type
and quantity for comparison of similar deformation
behaviour.
– Trend lines with increasing displacement tendency can
indicate critical situations and must be analysed
– Trend line shows settlement behind face.
Training Course “Conventional Tunnelling - Part 2”
35/39
4
Trend Line of Settlement
Trend line of settlement when tunnelling in homogeneous rock mass and
when passing a fault zone (schematically)
Training Course “Conventional Tunnelling - Part 2”
36/39
5
Conclusions
 Ground is viewed as integrated element of support
 Ground reactions are measured to confirm stability
 Ground should be kept undisturbed
 Rapid rigid support or slim deformable support
 Type of support to allow most economical design
 Tunnelling on ground classification system
 Agreement between Contractor and Engineer at face
Training Course “Conventional Tunnelling - Part 2”
37/39
5
Thanks for your Attention
Training Course “Conventional Tunnelling - Part 2”
38/39
ITA/AITES
Clause de non-responsabilité pour les rapports des groupes de travail de l'AITES
L’Association Internationale des Travaux en Souterrain (AITES) publie ce rapport, conformément à ses Statuts, pour faciliter les échanges d’informations afin :
d’encourager l’utilisation du sous-sol au profit du grand public, de l’environnement et du développement durable;
de promouvoir les progrès dans la planification, le projet, la construction, l’entretien, la réhabilitation et la sécurité des tunnels et de l’espace souterrain en
rassemblant et confrontant les informations, ainsi qu’en étudiant les questions qui s’y rapportent.
Cependant, l’AITES décline toute responsabilité en ce qui concerne les informations publiées dans ce rapport.
Ces informations :
sont exclusivement de nature générale et ne visent pas la situation particulière d’une personne physique ou morale;
ne sont pas nécessairement complètes, exhaustives, exactes ou à jour ;
proviennent parfois de sources extérieures sue lesquelles les services de l’AITES n’ont aucun contrôle et pour lesquelles l’AITES décline toute responsabilité ;
ne constituent pas un avis professionnel or juridique (si vous avez besoin d’avis spécifiques, consultez toujours un professionnel dûment qualifié).
Disclaimer for the reports of ITA working groups
The International Tunnelling Association (ITA) publishes this report to, in accordance with its statutes, facilitate the exchange of information, in order:
to encourage planning of the subsurface for the benefit of the public, environment and sustainable development
to promote advances in planning, design, construction, maintenance and safety of tunnels and underground space, by bringing together information thereon and
by studying questions related thereto.
However ITA accepts no responsibility or liability whatsoever with regard to the material published in this report.
This material is:
information of a general nature only, which is not intended to address the specific circumstances of any particular individual or entity;
not necessarily comprehensive, complete, accurate or up to date;
sometimes collected from external sources over which ITA services have no control and for which ITA assumes no responsibility;
not professional or legal advice (if you need specific advice, you should always consult a suitably qualified professional).
39/39