Transcript Slide 1
LNA progress 4th SKADS Workshop, Lisbon, 2-3 October 2008 LNA progress Dr Danielle Kettle 1 Current work overview • LNA designs to perform system tests of 2 PAD and validate 2PAD front-end concept • Concentrating on differential designs but have 1 singleended design in fabrication • Characterising devices at various possible operating temperatures (including commercial devices) • Testing and test plan issues • Array cross-coupling 4th SKADS Workshop, Lisbon, 2-3 October 2008 LNA progress Dr Danielle Kettle 2 Device characterization • Measuring and characterizing devices in terms of small signal and noise parameters • Range of temperatures: 350K – 77K • On-wafer and packaged tests • Current devices under test: – 70nm GaAs mHEMT – 100nm InP pHEMT – 0.5um GaAs pHEMT E-mode – 0.5um GaAs HEMT D-mode 4th SKADS Workshop, Lisbon, 2-3 October 2008 LNA progress Dr Danielle Kettle 3 LNA Design I • Single-ended MMIC LNA using 70nm mHEMT process at OMMIC – Bandwidth 300 MHz – 3 GHz – Simulated noise temperature ~ 22K – Simulated gain ~ 35 dB – Delivery due October 2008 4th SKADS Workshop, Lisbon, 2-3 October 2008 LNA progress Dr Danielle Kettle 4 LNA Design II / III • Differential LNA – 2 designs – Using COTS components – FHC40LG and ATF35143 (lower noise resistance) (commercial GaAs HEMTs / pHEMT) – Input impedance designed for antennas developed by UoM and ASTRON – Prototype I measured at room temperature – Construction of prototype II underway – measurements scheduled for end of October 2008 Personnel responsible for LNA design MUST consider integration with antenna AND packaging issues 4th SKADS Workshop, Lisbon, 2-3 October 2008 LNA progress Dr Danielle Kettle 5 Array cross-coupling • Noise implications of antenna array cross-coupling – Investigating fundamental principles – Developing ADS model – Performing measurements on commercial packages LNAs 4th SKADS Workshop, Lisbon, 2-3 October 2008 LNA progress Dr Danielle Kettle 6 Conclusion • Transistor modeling and optimization (still) crucial! • Noise budget leaves not much room in 35K target • Closer cooperation and system noise tests required • And, Steve T, we indeed want to work in phase! 4th SKADS Workshop, Lisbon, 2-3 October 2008 LNA progress Dr Danielle Kettle 7