JAXA SLE-SM Prototype Development and Test Schedule

Download Report

Transcript JAXA SLE-SM Prototype Development and Test Schedule

JAXA SLE-SM/UM Prototype
Implementation Status
25.April.2007
Telecon
Nobuhiro Yagi
[email protected]
SMWG-JAXA April 2007
1
1.JAXA SLE-Service Management Status
 JAXA is now developping the SLE-SM/UM prototype according Red-1
version (March 2006) .
 The development of the SLE-SM/UM prototype is scheduled to
complete by 11 Sep 2007.
2.JAXA SLE-Transfer Service Status
 Up-grade to RAF(911.1-B-2) and F-CLTU(912.1-B-2) is under way.
 Up-grading to the RAF & F-CLTU is scheduled to complete by 30
Aug 2007.
SMWG-JAXA April 2007
2
3.Documents
 For data-interface testing,
- The Draft TEST PLAN FOR JAXA-JPL SLE INTEROPERABILITY
TEST was made and sent to JPL on 20 April .
- The test plan Includes the SLE transfer services(RAF & F-CLTU)
interface testing,
because JAXA/Tukuba’s SLE equipment have not conected to JPL
- JAXA would like JPL to review the draft test plan .
 For Shawdow Track testing ,
- JAXA is now developping the TEST PLAN FOR JAXA-JPL
SHADOW
TRACK TESTING .
- The development of the TEST PLAN is scheduled to complete
by 22 June 2007.
SMWG-JAXA April 2007
3
4.Service Agreement
 The Draft Service Agreement was made and sent to JPL on 20 April .
 Some parameters need to be defined.
ie.JPL RF equipment Characteristic ,JAXA spacecraft
modulation
type:PCM/PSK-PM
SMWG-JAXA April 2007
4
5.Issues to be determined in the near futuer
 JAXA proposes to conduct a communication test .
-ICMP,SNTP level
 Produce ICD level information
- selection of the line for Transfer services (ISDN,capacity)
- exchange of network infomation ie.IP address
- voice communication
- security for Service Management message
- Email rule for Service Management message (contents, subjects)
SMWG-JAXA April 2007
5
Schedule of JAXA SLE-SM/UM prototype development & testing with JPL (tentative)
year
month
2007
April
SLE-SM/UM
prototype
development
with Red-1
SLE-Transfer
Service
RAFand CLTU
up-grade with
version-2
Shawdow Track
Testing
SMWG-JAXA April 2007
may
june
july
Aug
Sep
Oct
▲(11 Sep)
data interface testing
▲(30 Aug)
data interface testing
(1 Oct)▲
Shawdow Track
6