Capital Outlay Program & Facilities
Maintenance Overview
Board of Commissioners
Session 351
May 28, 2013
Jeff Florin
Deputy Executive Director, Operations
Virginia Port Authority
Agenda
NIT Gate Improvements
NIT Outbound Corridor
NIT OCR Portals
NIT Truck Canopy
PMT Rail Upgrades
APMT Trench Drain Repairs
APMT Reefer Plugs
Craney Island Eastward Expansion
2
NIT Gate Improvements
Security, interchange, and transfer zone
automation, personnel shifted to remote
facility
Automation, appointment system and
remote processing
Improves cargo velocity, safety & efficiency
Estimated combined project cost: $10 M
Includes $4.1 M software
3
NIT Gate Improvements
Project 2
OCR Portals
Project 3
Truck Canopy
Completed Chassis
Service/Customer
Service Areas
Project 2
OCR Portals
Project 1
Outbound Corridor
Completed
Transfer Zone
4
NIT Outbound Corridor
Surface asphalt complete
OCR Portal construction underway
Estimated project cost : $2.2 M
Contractor: EV Williams
Project is currently 75% complete
Project completion by September 2013
5
NIT Outbound Corridor
6
NIT OCR Portals
7
NIT Truck Canopy
Infrastructure for gate automation
Estimated project cost : $300,000
Bids received May 21st
Project completion by October 2013
8
NIT Truck Canopy
9
PMT Rail Upgrades
Replacement and upgrade to Class I
railroad standards of the East and West
rail leads into PMT
On hold pending tunnel contractor work
Estimated project cost : $900,000
Contractor: H&B Railroad
Project completion by October 2013
10
PMT Rail Upgrades
East
rail lead
West
rail lead
11
APMT Projects
Reefer plug
installation
Trench drain
repairs
12
APMT Trench Drain Repairs
Localized repairs of APMT storm drains
Demolition complete; vault repairs in progress
Estimated project cost : $150,000
Contractor: Eastern Waterproofing &
Restoration of VA Co, LLC
Project is 25% complete
Project completion TBD
13
APMT Trench Drain Repairs
14
APMT Reefer Plugs
Installation of 60 reefer plugs
Discussions with APM ongoing
Estimated project cost : $1.3 million
Bids due June 18th
15
Craney Island Cross Dikes Stage 2A
Stage 2A is complete
Placed 1.54 MCY of sand on south and division
cross dikes to +5 feet MLLW
Congressional action
WRDA amendment authorizes USACE to convey
the Eastward Expansion to VPA
Next steps
Bid package for PVD installation on cross
dikes will be advertised in June
16
Craney Island Cross Dikes Stage 2A
17
Craney Island Cross Dikes Stage 2A
18