May 2013 Facilities Presentation

Download Report

Transcript May 2013 Facilities Presentation

Capital Outlay Program & Facilities
Maintenance Overview
Board of Commissioners
Session 351
May 28, 2013
Jeff Florin
Deputy Executive Director, Operations
Virginia Port Authority
Agenda
 NIT Gate Improvements
 NIT Outbound Corridor
 NIT OCR Portals
 NIT Truck Canopy
 PMT Rail Upgrades
 APMT Trench Drain Repairs
 APMT Reefer Plugs
 Craney Island Eastward Expansion
2
NIT Gate Improvements
 Security, interchange, and transfer zone
automation, personnel shifted to remote
facility
 Automation, appointment system and
remote processing
 Improves cargo velocity, safety & efficiency
 Estimated combined project cost: $10 M
 Includes $4.1 M software
3
NIT Gate Improvements
Project 2
OCR Portals
Project 3
Truck Canopy
Completed Chassis
Service/Customer
Service Areas
Project 2
OCR Portals
Project 1
Outbound Corridor
Completed
Transfer Zone
4
NIT Outbound Corridor
 Surface asphalt complete
 OCR Portal construction underway
 Estimated project cost : $2.2 M
 Contractor: EV Williams
 Project is currently 75% complete
 Project completion by September 2013
5
NIT Outbound Corridor
6
NIT OCR Portals
7
NIT Truck Canopy
 Infrastructure for gate automation
 Estimated project cost : $300,000
 Bids received May 21st
 Project completion by October 2013
8
NIT Truck Canopy
9
PMT Rail Upgrades
 Replacement and upgrade to Class I
railroad standards of the East and West
rail leads into PMT
 On hold pending tunnel contractor work
 Estimated project cost : $900,000
 Contractor: H&B Railroad
 Project completion by October 2013
10
PMT Rail Upgrades
East
rail lead
West
rail lead
11
APMT Projects
Reefer plug
installation
Trench drain
repairs
12
APMT Trench Drain Repairs
 Localized repairs of APMT storm drains
 Demolition complete; vault repairs in progress
 Estimated project cost : $150,000
 Contractor: Eastern Waterproofing &
Restoration of VA Co, LLC
 Project is 25% complete
 Project completion TBD
13
APMT Trench Drain Repairs
14
APMT Reefer Plugs
 Installation of 60 reefer plugs
 Discussions with APM ongoing
 Estimated project cost : $1.3 million
 Bids due June 18th
15
Craney Island Cross Dikes Stage 2A
 Stage 2A is complete
 Placed 1.54 MCY of sand on south and division
cross dikes to +5 feet MLLW
 Congressional action
 WRDA amendment authorizes USACE to convey
the Eastward Expansion to VPA
 Next steps
 Bid package for PVD installation on cross
dikes will be advertised in June
16
Craney Island Cross Dikes Stage 2A
17
Craney Island Cross Dikes Stage 2A
18
Thank You