Transcript Document
Alternative Project Delivery Mechanisms
The J. K. Spruce Experience Katherine Yates Assistant General Counsel
Overview
• J.K. Spruce #2 planned as early as 1986. • Authorized to proceed without permit in 2004.
• Chose Design-build methodology.
• Issued Two Phase RFP.
• Two Offerors Responded/Awarded July 2005.
• Issued LNTP’s in August 2005 and full NTP in April 2006.
• Provisional acceptance expected no later than March 2010.
Traditional Process
• Chapter 252 of Local Gov. Code governed procurement activities.
• Design-Bid-Build was only available method.
• Bids advertised, opened and awarded publicly.
• Award based on Lowest responsible bidder.
New Processes
• Chapter 271, Subchapter H added in 2001.
• Authorized “best value” determination.
• Five new methods for project delivery: – Competitive sealed proposals – Design-build – Construction manager-agency – Construction manager-at-risk – Job-order contracting
Design-Build process
• Single entity provides design and construction.
• Two phase procurement process: – Phase One RFQ based on qualifications, references, past experience.
– Phase Two RFP based on schedule, implementation plan, technical approach, cost.
• Award to best value offeror.
Design-Build Advantages
• Fast-track schedule and construction • Single point of contact.
• Cost savings due to value engineering.
• Less owner administrative burden during construction phase.
• Potential for minimization of change orders.
Initiation of CPS Energy Process
• Board Resolution selecting “best value” process.
• Engage Owner-Engineer to develop Design Criteria Package.
– Functional specification and conceptual layout.
– Desired equipment margins.
– Quality and performance guarantees.
– Transmission access.
– Geotechnical and environmental information.
• Engaged the services of a surety consultant • Joint development of RFPP/RFP and evaluation matrices.
• Pre pre-bid meeting held with interested parties.
Phase One-RFPP
• RFPP advertised and sent to attendees.
• Pre-bid meeting held with Site visit.
• Evaluation criteria: – Ability to bond penal value of $250 million.
– Financial status.
– Reputation in industry.
– Past experience.
– Resumes of proposed project team. – References.
• Two offerors qualified to proceed to Phase Two.
Phase Two
• Offerors given the RFP.
• Agreement to reimburse losing entity of up to $1 million for preparation costs.
• Evaluation criteria: – costs – Implementation plan – Project schedule – Safety record – Workforce and training plans – Costing methodology – Initial Design drawing and schematics
(con’t.) Phase Two
• Interviews conducted to clarify exceptions and technical response.
• Offerors asked to resubmit responses based on discussion and to provide pricing to remove exceptions.
• Signed agreement “fixing” responses for evaluation.
• Evaluation and recommendation of selected offeror.
• Negotiations with selected offeror and award based on reaching satisfactory contract.
Post Award
• Limited Notices to Proceed: – LNTP #1- Early planning and engineering for procurement of long lead time items.
– LNTP #2- Vendor engineering.
– LNTP #3- Preparatory site construction work – LNTP #4- Material and Equipment purchase release – LNTP #5- Controls upgrade • Full Notice to Proceed upon issuance of permit.
Keys to Success
• Clear and comprehensive Design Criteria package.
• Effective integration of proposed Design-Build Team.
• Full and consistent communication. • Owner involvement.
Commercial Considerations
• Testing and commissioning done by third party.
• Contract price.
• Payment and performance bonds.
• Construction risks.
• Bidding stipend.
• Bonus for early completion.
• Payment of prevailing wage.
• Use of a Local Government Corp.