PLANNING FOR WIND AND QUEUE
MANAGEMENT
Turkish Electricity Transmission
Corporation(TEIAS)
prepared by
Gül Okan & Nurhan Ozan
1
400 kV Network
BULGARİSTAN
KARADENİZ
DIMODICHEV
HABİPLER
BABAESKİ
HAMİTABAT ALİBEYKÖY
İKİTELLİ
FILIPPI
KAPTAN
AMASRA
BOYABAT
SAMSUN
DGKÇ
BORASCO
ÇARŞAMBA
Y.TEPE
BEYKOZ PAŞAKÖY
EREĞLİ
OSMANCA
Z.KÖY
ÇANKIRI
ÜMRANİYE
ADA-GEBZE
TEPEÖREN
İÇDAŞ
KARABİGA
ADAPAZARI
BAĞLUM
ÇAYIRHAN
SİNCAN
GÖKÇEKAYA
İÇDAŞ
BURSA
GÖLBAŞ
BALIKESİR
ÇAN
TEMELLİ
I
TUNÇBİLEK
UNIMAR
GÜRCİSTAN
AHALTSIKHE
A.ALANI
D.PAŞA
BATUM
AMBARLI
SOMA
HOP
A
BORÇKA
GUMRI
DERİNER
ARKUN
K.KALE
DGKÇ
İSPİR
ORDU-2
AKINCI
İÇANADOLU
DGKÇ
SEYİTÖMER
AĞRI
SİVAS
DEÇEKO
KANGAL
BABEK
D.BEYAZIT
ERZURUM
VAN
KEBAN
İRAN
KARAKAYA
MANİSA
YEŞİLHİSAR
HİLVAN
KONYA
IŞIKLAR
ÇETİN
DİYARBAKIR
BATMAN
DENİZLİ
YEDİGÖZE
AYDIN
YATAĞAN
SİİRT
ILISU
SİLOPİ TES
V.ŞEHİR
G.ANTEP
ADANA
OYMAPINAR
KEMERKÖY
ATATÜRK
ANDIRIN
KAVŞAK
SEYDİŞEHİR
BAZARGAN
KHOY
ELBİSTAN
ALİAĞA
YENİKÖY
IĞDI
R
HORASAN
ÖZLÜCE
KAYSERİ
KOCATEPE
UZUNDERE
ERMENİSTAN
KARS
YUSUFELİ
KALKANDERE
TİREBOLU
H.UĞURLU
KAYABAŞI
ERZİN
BİRECİK
PS3
Ş.URFA
KIZILTEPE
CİZRE
ZAKHO
ERMENEK KAYRAKTEPE
AKSA
VARSAK
MERSİN
IRAK
İSKENDERUNİSDEMİR
MUSUL
TEİAŞ-APK 2010
TS (PLANLANAN)
HATAY
HALEP
TS (MEVCUT)
HES (PLANLANAN)
AKDENİZ
SURİYE
HES (MEVCUT)
TL (MEVCUT)
TL (PLANLANAN)
220 kV EİH
154 kV EİH
2
Profile of System (end of 2010)
NUMBER OF SUBSTATIONS:
400 kV
154 kV
66 kV
TOTAL
184 (35020 MVA)
1034 (58015 MVA)
54 (637 MVA)
1272
INSTALLED CAPACITY (93672 MVA)
LENGTH OF TRANSMISSION LINES (km):
400 kV
14,623
154 kV
31,932
220 kV
84,5
66 kV
508,5
154 kV Cable 170,9
380 kV Cable
22,3
TOTAL
47,148
3
Generation & Demand (for the year of 2010)
Installed Capacity
48.500 MW
BREAKDOWN OF INSTALLED CAPACITY
35.000
30.000
Hydro+Renewable
34.4 %
Hydro 32.1 % & Renewables 2.7 %
Thermal
65.2 %
25.000
THERMAL
20.000
WIND
HYDRO
15.000
10.000
5.000
Annual Consumption 208 TWh
0
THERMAL
Peak Demand
WIND
HYDRO
33.500 MW
(13 August 2010)
4
Topics
•
•
•
•
•
Brief history of interconnection queue
Challenges while planning
Tariff Policy
Queue Management
Future Efforts
5
Brief History of Queues
•
•
•
•
First WPP commissioned in: 1998
Number of the wind pp’s in operation are: 39 and total capacity: 1320 MW
Current Licensed wind generation: 3483 MW
Date: 1th November 2007
Number of the wind pp’s: 722
Total capacity: 78.000 MW
•
According to the system available capacity for connecting wind generation which is
equal to 8474 MW a bidding code was prepared by TEIAS which includes the
requirements for the applications.
•
According to the bidding document the wind owner which will get the right to use the
open capacity has to pay an amount to TEIAS for 20 years since connecting to the
system which is equal the amount which will be calculated for per kwh generation of
the wind power plant.
6
Wind power plant application areas
7
Recent Situation for Wind Generation in Turkey
• 3483 MW of wind applications has been licensed by EMRA
• 1320 MW is in Operation
• 2283 MW is Underconstruction
• 8488 MW is under evaluation
• The amount of the available wind generation capacity can be
connected to the system until 2013 is 12000 MW
• In the strategy document it is foreseen that the total wind
generation capacity will reach to 20.000 MW until 2023.
8
The available wind generation capacity around 8488 MW is under
evaluation
9
Marmara & Thrace Region available wind generation capacity ~ 2745
MW is under evaluation
10
Aegean Region available wind generation capacity around 2499 MW is
under evaluation
11
Hatay Region available wind generation capacity around 190 MW is under
evaluation
12
Challenges while planning
• Available system reserve
• The required reinforcements for connecting WPP’s into power system.
• The difficulty to guess their production time of wind power plants.
• Who pays the investments and how it will be recovered
• Beside load flow, voltage profile, short-circuit and contingency studies; the
%5 of the short circuit power of the substation which WPP will be
connected is applied as a restriction criteria in order to keep the overall
system security by now.
• Detailed dynamic studies for determining the connection capacities are
going on.
13
INCENTIVES FOR RENEWABLE POWER PLANTS
The Turkey’s Parliament approved a new law 29 December 2010 on
regulating the renewable energy resources market in Turkey. The
incentives which are applied for Renewable Power Plants with the new law
guarantees a price of:
• Hydro PPs and WPPs are paid at system marginal price, but minimum 7.3
US$ /MWh is guaranteed
• Geothermal PPs are paid at system marginal price, but minimum 10.5 US$
/MWh is guaranteed
• Biogas PPs and Solar PPs are paid at system marginal price, but minimum
13.3 US$ /MWh is guaranteed
• Those tariffs shall be valid for the PPs which came into service between 18
May 2005 to 31 December 2015 and will be applied for 10 years.
• After 31 December 2015, new tariff shall be given by the Government but
the new tariff shall not exceed the tariff above.
Queue Management
•
Process:
1.
2.
3.
4.
5.
6.
7.
The available capacity for connecting wind generations are
published by TEİAS.
WPP applications are forwarded to EMRA (Turkish Regulatory
Agency) for these capacities.
These applications are forwarded to TEIAS for studying connection
opportunities.
TEIAS gives its comment concerning the availability.If the application
is alone in the substation, EMRA gives license to those applications.
If there are multiple applications, bidding process is done by TEIAS
to determine the owner of the capacity.
After taking license the investor sign a connection agreement with
TEIAS.
Project will be approved by MENR after the realization of the project
System Usage Agreement will be done with TEIAS.
15
Queue Management
• Principle of connection cost sharing in between TSO and
investor:
If the investor pays for the connection line then the TSO will pay back to
the investor this amount in 10 years from the investment budget.
Otherwise, TSO will put the required investment for the connection of the
power plant in it’s yearly investment plan and these procedures takes
approximately 3-5 years for bidding (plus constructing period)
16
Planning Process by TEIAS
• Turkish Electricity Transmission Corporation responsible from the WPP
integration studies and to define the available capacity for connecting wind
generation
• According to the results of load flow, contingency analyses and short
circuit power calculations, the estimation for capacity for each substation
and each region which will be available for connecting wind generation are
defined by TEIAS
• Concentrated small wind generations in one region are collected in one
substation (example: Çeşme Region)
• We have a specific grid code which defines the connection criteria for wind
generation but it will be revised for future power system conditions.
17
ÇEŞME REGION WIND PROJECTS: 460 MW
21 km 380 kV 3 Cardinal
380/OG Çeşme
HAVZA SS
380/OG
125 MVA
380/154 kV
Uzundere SS
380/OG
150 MVA
31 km 154 kV 2x1272 MCM
10 km
OG
10 km
26 km
30,75
11 km
154/OG
50 MVA
154/OG
50 MVA
OG
OG
Ovacık RES
Urla RES
18 MW
~
12 km
~
Mordoğan RES
MW
~
17 km
13,8
Karadağ RES
16,25MW
154/OG
50 MVA
5 km
16 MW
10 km
Alaçatı RES
~
Yaylaköy RES 15 MW
9 km
14 MW
Seferihisar RES
Germiyan RES
16 MW
10,8 MW
~
11 km
Urla RES
13 MW
6 km
Korkmaz RES
MW
Demircili RES
~
~
13 km
Seferihisar RES
~
~
4 km
Sarpıncık RES 32 MW
16 MW
~
~
9 km
15 MW
Çeşme RES
~
~
Mordoğan RES
MW
14 km
Zeytineli-2 RES
49,5 MW
~
7 km
~
~
Karaburun RES
120 MW
154/OG URLA
HAVZA SS
OG
OG
~
16,2 km 380 kV 2 Cardinal
380/OG kV
Karaburun SS
55 km 380 kV 3 Cardinal
40 MW
18
SS TOTAL CAP: 211,55 MW
SS TOTAL CAP: 139,55 MW
SS TOTAL CAP: 109 MW
24
Future Efforts
• The wind forecast system has been developed by Turkish State
Meteorological Service which is available to provide information about the
wind forecasts for different heights and for 48 hours with 4 km. solubility all
around Turkey. The trial tests are going on in order to improve the system.
• Specific monitoring system for wind generation will be installed and the
procedures are going on with consultant company
19