Hydropower Development Policies of Nepal: A Brief Assessment

Download Report

Transcript Hydropower Development Policies of Nepal: A Brief Assessment

Hydropower Development Policy
&
Regulatory Framework
Keshab Dhoj Adhikari
Senior Divisional Engineer
Ministry of Water Resource
23 September 2008
1
What Constitute HP Policy
• Hydropower Development Policy2001
• Water Resources Strategy-2002
• Electricity Act 1992 & Rules 1993
• Periodic plans, annual budget
speech, EPA & EPR, custom & tax
provisions, etc.
2
What Constitute HP Policy contd…
Other relevant Acts & Regulations
• Foreign Investment and Technology
Transfer Act
• Company Act
• Electricity Tariff Fixation Regulation,
etc.
3
Other important Acts on anvil
• Electricity Act and Rules
(proposed)
• Nepal Electricity Regulatory
Commission Act (proposed)
4
Institutions currently involved
• MoWR and DoED
• Electricity Tariff Fixation
Committee
– Ministry of Environment, Science
and Technology
–Ministry of Forest and Soil
Conservation
5
Objectives of HP-2001
• Generate electricity at low cost;
• Provide reliable and quality electricity at a
reasonable price;
• Combine electrification with the economic
activities;
• Extend rural electrification; and
• Develop hydropower as an export
commodity
6
Key Policy Provisions (HP-2001)
• ‘Competition’ emphasized
• BOOT model; first sector to adopt one
(not under the BOOT ACT)
• In case of multipurpose projects, GoN
may participate
• Environment- 10% d/s release (min)
• Facilitate property acquisition
7
Key Policy Provisions (HP-2001) contd…
•
•
•
•
Water rights guaranteed
Various provisions for RE
No expropriation
Foreign exchange facility for dividend
and loan
• Additional 5 year term (max) for
projects at risk
8
Other Important Aspects of Policies
Terms of License
• Survey License for 5 years
• Generation License
– Internal consumption 35 years
– Export Oriented 30 years
– In case of reservoir 5 years extension on the
basis of construction period
– Captive Plant as it remains in operation
– Transmission and Distribution 25 years with
ten years renewable
9
Some Important Aspects of Policies (contd..)
Transfer of Projects
• Every hydropower project has to be
transferred to the government, free of costs,
after the completion of license period
• Licensee has to involve the government in the
operation of the project two years prior to the
completion of license period
10
Some Important Aspects of Policies (contd..)
• Utilization of Local Resources
• Developers are encouraged to– utilize Nepalese labour, skill, means and
resources to the maximum extent possible and
have to give priority to utilize local labour
– carry out works in such a way so as to transfer
technology to the Nepalese citizens
11
Private Sector Participation
Ever since Hydropower Development
Policy 1992 was formulated, Government
hasn’t turned back and made adequate
policy commitments for the enhanced
participation of private sector.
12
Emerging Institutions
• Independent Electricity Regulatory
Commission (NERC) to replace ETFC with
enhanced regulatory role
• Existing vertically integrated utility(ies) to be
unbundled
• One agency will be allowed to do business
either generation or transmission or
distribution
• Separate Rural Electrification Fund
13
Establishment of Grid Authority
• Operation and control of the National Grid
shall be in accordance with the Grid Code
• A Licensee may transmit the electric powers
inside or outside the country by obtaining
access to the National Grid
• No discrimination in accessing grid
14
Special provisions in new EA
• >100 kW developer-registered firm; <100 kW
individual and firm
• After completion of submission, award of
license
– Survey within 21 days
– Cap. <10 MW within 60 days
– 10 MW<Cap.<50 MW within 90 days
– Cap.> 50 MW within 120 days
– T & D within 90 days; Trade within 45 days
15
Special provisions in new EA
• A developer to get license either for
generation or for transmission or for
distribution except in special cases
• Security deposit for construction license
• Duration
– Survey license initially for 2 years and extension
up to a total maximum of 5 years
– Generation 35 years for domestic consumption;
30 years for export
16
Special provisions in new EA
• Duration contd..
– 15 years for thermal
– 35 years for captive hydro and in case of captive
thermal till the industry is operated
– May be extended by 5 years, at the most, for
storage projects
– May be extended by 5 years, at the most, if the
project suffers from serious geological and
hydrological uncertainties
– 25 years for transmission, distribution and
trading
17
Provisions in new EA
• National Grid
– GoN, in consultation with NERC, to declare national grid
and its codes
– Indiscriminate access to grid
• Power purchase & import/export
– Price to be set on the basis of fixed percentage of avoided
cost or average tariff or ROE
– Also by bidding following a NERC declared procedure
– NERC may declare other methods once power whole sale
market is established
18
Provisions in new EA
• Import/Export
– Trade license for power import and export
– No separate export license needed for export
oriented generation licensee
– GoN may ask for selling 10%(max) of energy for
domestic consumption
• Royalty (as per HP-2001)
– Applicable only for > 2 MW projects
– Currency of royalty payment same as the
currency of power purchase
19
Water rights & environment
• Water rights ensured for generation period
• Downstream release of 10% of mean
monthly flow or as stipulated in approved EIA
report whichever is greater
20
Land acquisition, resettlement
• Govt. land and forest area to be provided on
lease
• Govt. to facilitate acquiring private land and
property
• Developers to compensate for land and
properties thus acquired
• Developers to prepare and implement R&R
plan
21
Tax Exemption
• custom duty 1% of cost of imported material
and equipment and NO VAT
• Above exemption only for the construction
period and applicable for spare parts also
• No income tax for > 2MW
• Income tax holiday for first 10 years after
commissioning and first 7 years incase of
transmission and distributio
22
Other incentives
• 15% tax on the annual income for generation
companies
• Expatriates to get other incentives like
foreign exchange, duty free and visa facilities
• Protection from change in law regarding tax
exemption for the entire license period
23
Some other important provisions
• No expropriation
• All power projects to be considered as
Priority Projects and incentives to be
provided accordingly
• A bonus of 2% of net income (not exceeding
annual salary) for the employees; the surplus
in welfare fund
• Annual Reports to be submitted to NERC and
DOED
24
Draft NERC Act
• NERC- 5 man strong commission (including at
least a woman)
• GON appoints Chairperson and members of
NERC
• Recommendation Committee
– VC (NPC), Coordinator
– Power sector expert from private sector (GON
nominee), Member
– MOWR Secretary, Member
25
Draft NERC Act
• Eligibility criterion- Master degree in
Economics or Commerce or Management or
Accounts or Law or Engineering and a
minimum of 10 years experience in relevant
field
• 5 year term and can be reappointed for one
more term
26
Roles and responsibilities
• Technical aspect
– Regulate for maintaining safety and quality
– Formulate policy and action plan for the
reliability and effectiveness of power system
– Prepare O&M procedure code
– Prepare and enforce Grid code and distribution
code
– Review LCGE and see whether a project fits it
(not applicable for <10 MW)
27
Roles and responsibilities
• Tariff fixation
– Declare bases of tariff
– Determine wholesale price
– Determine PPA process and buy back rate for 1 to
10 MW plants
– Fix wheeling charge and retail tariff
– Review and provide consent to PPAs, etc.
28
Roles and responsibilities
• Maintain competition and protect
consumers’ interest
– Avoid monopoly or find out ways and means to
avoid monopoly
– Regulate merging, sale of plant, acquisition or
takeover, etc.
• Capacity building and enhancing good
governance in companies
• Advise GoN in related matters
29
Roles and responsibilities
•
•
•
•
•
Monitoring and inspection
Dispute resolution
Impose fines- up to Rs. 500,000.00
Public hearing in the process of tariff fixation
Employ a NGO to advocate on behalf of
consumers
• NERC may review its own doing
30
Some other provisions in NERC Act
• NERC will get 1% of revenue from companies
(except generation)
• Appeal in Appellate Courts
31
32