Application of Radioactivity and the Law to Contaminated
Download
Report
Transcript Application of Radioactivity and the Law to Contaminated
Application of Radioactivity and the Law
to Contaminated Land and Demolition
Projects
Gareth Walker, BSc, PhD, MRSC
Contents
July 17, 2015
Introduction to legislation
Introduction to contamination land
assessment, and demolition &
decommissioning projects
Three case studies
2
Overview of Legislation
Main legislation for this presentation
Nuclear Installations Act 1965
Radioactive Substances Act 1993
Including Exemption Orders
Ionising Radiation Regulations 1999
Environmental Protection Act 1990, Part IIA
Site Waste Management Plan Regulations
2008
DEFRA policy on Low Level Waste
Management (2007)
July 17, 2015
3
Why Undertake an Assessment?
July 17, 2015
Obligation & Liability management
Obligated to comply with legislation
If they fail to comply, are they liable?
What is the extent of the liability?
4
Types of assessments
July 17, 2015
Will be focussing on contaminated land and
demolition/decommissioning assessment
Assessed through
Contaminated land characterisation
Risk assessment
Remediation options and cost assessments
Waste management
Materials characterisation
5
Case Studies
Contaminated land assessment
Sellafield characterisation
Radiological risk assessment at Hunterston A
Demolition and decommissioning assessment
July 17, 2015
Working in partnership with Serco Assurance
Waste management during decommissioning
and demolition at Bradwell
6
Considerations Prior to Contaminated Land
Assessment
Aim of the assessment
Contaminant
Source
Pathway
Receptor
July 17, 2015
Leads to a potentially significant pollutant linkage
Does the pollutant linkage represent an
unacceptable risk?
7
Sellafield
July 17, 2015
8
Drilling at Sellafield – Overview
July 17, 2015
Installation of boreholes
Vertical holes (up to 60 m)
Understanding ground profile (geology)
Collection of soil and groundwater samples
Spatial understanding from soil analysis
Contaminant transport
Source identification and understanding
Pollutant linkages (radiological and chemical)
Conceptual model building
9
Characterisation at Sellafield
July 17, 2015
Elements of legislation driving this project
NIA65
RSA93
IRR99
Drilling boreholes into land with unknown
concentrations, isotopes and forms of radioactive
contamination
Fission products
Daughter isotopes
Chemical properties
Mobility by dissolved phase/colloidal transport
10
Drilling at Sellafield
July 17, 2015
11
Summary - Sellafield
July 17, 2015
Worker safety paramount – drillers, engineers and
general site staff
Must maintain nuclear and environmental safety
Source terms must be defined
Pathways and receptors must be defined
Potential liability relating to contaminated land must be
understood
12
Radiological Risk Assessment - Overview
July 17, 2015
Hunterston A is in the process of decommissioning and
moving towards de-licensing parts of the site
Driver is to put the site into a care and maintenance
period
Assessment of risk to people and the environment
arising from land quality issues at Hunterston A
Through this assessment, understanding the liability
associated with potentially contaminated land
13
Radiological Risk Assessment - Overview
July 17, 2015
Used land quality data gathered between 2000 and
2008
Review of data and comparison to current legislation
NIA65
RSA93
EPA90, Part IIA
Guidance (statutory)
Establish the extent of risk, if any, to people and the
environment
Does the site have a liability it needs to address?
14
Radiological Risk Assessment – Part IIA
Contaminated Land Report (CLR) -11 framework
followed to assess risk
Tiered approach
Generic qualitative risk assessment (GQRA)
July 17, 2015
Phase 1 completed in early 1990s
Characterisation completed
Areas of Potential Concern (APCs) identified
Potentially significant pollutant linkages identified
Conservative approach
Screens each APC through risk assessment
process – further work required?
15
Radiological Risk Assessment – Part IIA
Developed a qualitative risk table
Based on the MoD Defence Estates methodology,
and input from other consultancies to Defence
Estates
In consultation with Magnox North
Assesses pollutant linkage based on
Magnitude of potential consequence (i.e. Severity)
Magnitude of probability (i.e. Likelihood)
RISK = SEVERITY X LIKELIHOOD
July 17, 2015
16
Radiological Risk Assessment – Part IIA
DESCRIPTORS FOR SEVERITY OF CONSEQUENCE OF CONTAMINANT
SOURCE-RECEPTOR LINKAGE
July 17, 2015
17
Radiological Risk Assessment – Part IIA
DESCRIPTORS FOR PROBABILITY OF CONSEQUENCE OCCURRING
July 17, 2015
18
Radiological Risk Assessment – Part IIA
DESCRIPTORS OF RISK SIGNIFICANCE
Likelihood:
Severe
Moderate
Potential
consequence:
Mild
Negligible
Very
likely /
certain
Likely
Very High Very High
Unlikely
Very
unlikely
High
Medium
High
High
Medium
Medium
Low
Medium
Medium
Low
Very low
Low
Low
Very low
Trivial
RISK = SEVERITY X LIKELIHOOD
July 17, 2015
19
Radiological Risk Assessment – Part IIA
July 17, 2015
Apply to each individual APC
This will define:
Is more work required?
What work is required?
When can you stop?
20
Radiological Risk Assessment - Summary
Using this risk assessment approach allowed:
An assessment that is compatible with current law
and guidance
England & Wales – human health only
Scotland – also, water and ecological environments
July 17, 2015
Significance of pollutant linkages to be assessed in
a consistent manner across the NDA land-holding
Potential contaminated land liability to be better
understood, more readily prioritised and therefore
managed
21
Considerations Prior to Demolition and
Decommissioning Assessment
July 17, 2015
Legislation and guidance requires quantification of
waste and materials for site-wide Integrated Waste
Strategy (IWS) or Site Waste Management Plan
(SWMP)
The correct characterisation of items and materials will
form part of an IWS or SWMP
Location and extent of chemical and radioactive
contamination must be identified
22
Waste Classification
Waste classification and fate
July 17, 2015
Intermediate Level Waste – remains at site creating
the waste
Low Level Waste – shipped to the LLWR at Drigg
Very Low Level Waste – hazardous waste landfills
with RSA93 licence
Exempt waste – no regulatory control; free release
All waste removed from the site must be, as far as is
reasonably achievable, re-used or recycled, with
minimum final disposal
23
Waste Management During Decommissioning
July 17, 2015
24
Waste Management During Decommissioning
July 17, 2015
25
Waste Management During Decommissioning
July 17, 2015
26
Waste Management During Decommissioning
July 17, 2015
27
Waste Management During Decommissioning
Waste Management During Decommissioning
- Summary
July 17, 2015
Context for determination of a site strategy for the
management of decommissioning wastes and items is
determined by Site Waste Management Plan regs
Previously required an IWS (EGG01)
Waste management plans should be developed “with
appropriate regulatory and stakeholder involvement”
and should take into account current best practice
e.g. Nuclear Industry Code of Practice
Current decommissioning policy for nuclear sites in
under review
SD:SPUR / SAFESPUR / SAFEGROUNDS /
CoRWM
29
Summary
Obligation and liability management
Legislation – grey areas; overlap; changes
On-site as opposed to off-site
July 17, 2015
Complex sites
Long histories; many stakeholders
Pollutant linkages
Characterise; Assess; Mitigate
Waste management
During characterisation
During remediation
During demolition & decommissioning
30
Acknowledgements
July 17, 2015
Sellafield contaminated land team
Hunterston A (Magnox North & Hugh Richards)
Bradwell (Magnox South)
31
Application of Radioactivity and the Law
to Contaminated Land and Demolition
Projects
Gareth Walker, BSc, PhD, MRSC