Portfolio and key programme overview as at 16.03.12
Page 1 of 4
Portfolio Headlines
 The Programme Management Office function is under review, and it is noted that the PMO Portfolio Report informs the Board of the monthly progress of
the Trust’s key programmes in line with the monthly programme reports, but does not assure them. The Assurance for each programme sits with the
relevant Executive Director, or the Programme Director of the major redevelopment programmes.
 HDD1 Dry Run has taken place and feedback from internal auditors will inform next stage of process and staff engagement.
RAG key for programme delivery status
Key Programme Risks
RED –
not on target to deliver on time or within
budget, and/or significant risk of not delivering
AMBER – issues/risks identified in time/finance/
delivery which may affect delivery and/or milestones
GREEN – on target to deliver on time and/or within
budget
• St Bernards Redevelopment timescales issues, and interdependencies with local
services continues.
• Broadmoor Redevelopment enabling works and OBC decision delayed again
• Foundation Trust – HDD1 dry run will inform next steps
• Local services stakeholder engagement ongoing
• Recovery Programme trialling new template for reporting
Summary of Key Programmes
Programme
Foundation Trust Programme
Jan
Feb
Mar
Comments/Detail
  
  
Next draft of IBP complete and HDD1 dry run progressing with RSN
Tenon internal auditors. Feedback will inform next process.
  
Secondment for programme lead – recruitment delayed. All projects
reported as on target.
Recovery Programme
  
No major issues, and project leads to trial new reporting templates
which will report into the Recovery Programme Board.
St. Bernard’s Redevelopment Programme

The clinical lead to manage the relationship and work with local
services is now in post. Further work on design is progressing.
Decision dates imminent.
Local Services Programme
Specialist and Forensic Programme
Broadmoor Redevelopment Programme
Multiple projects progressing, including re-design of community and
in-patient services, enabling works, new business.
Dates for OBC and enabling works decision by DH have slipped
once again, now expected April/May 2012.