garden grove usd – la quinta high school
Download
Report
Transcript garden grove usd – la quinta high school
65 schools
Infrastructure Upgrades
Health and Safety
Technology Upgrades
$253 million State Funding
$250 million local bond – June 2012
21 schools completed
1
Group IV – 27 Elementary Schools
6 Schools started December 2013
13 Schools start Spring/Summer 2014
6 Schools start Spring/Summer 2015
2 Schools start Summer 2016
Interim Housing
Group IV – Elementary Schools
Setting Portables now for Summer 2014
Group V – Intermediate and High Schools
Setting 122 Portables in July for Fall 2014
2
3
4
Student Restroom
5
6
Group V
9 Intermediate Schools
7 High Schools
Combined into 7 contracts
7
8
9
Air Conditioning
Seismic Repairs
Lighting Upgrades
Window Replacement
Seismic Replacement - La Quinta High
Seismic Replacement - Pacifica High
105,000 square feet each
SAB Conceptual Approval
Submit to DSA June 2014 (fast tracked)
10
GARDEN GROVE UNIFIED SCHOOL DISTRICT
LA QUINTA HIGH SCHOOL – WESTMINSTER, CA - AB-300 BUILDING REPLACEMENT
BLDG
“L”
(DEMO)
BLDG
“C”
(DEMO)
GARDEN GROVE USD – LA QUINTA HIGH SCHOOL
EXISTING BUILDINGS TO BE REPLACED
NEW STUDENT DROP-OFF / VISITOR PARKING
STAFF PARKING
STAFF PARKING
CLASS
ROOM
AUDITORIUM
CLASS
ROOM
CLASS
ROOM
CLASS
ROOM
STUDENT PARKING
MEDIA
CENTER
CLASS
ROOM
CAFETERIA
CLASS
ROOM
GARDEN GROVE USD – LA QUINTA HIGH SCHOOL
PROPOSED NEW SITE PLAN
NEW
STUDENT
DROP-OFF
GARDEN GROVE USD – LA QUINTA AND PACIFICA HIGH SCHOOLS
CLASSROOM BUILDING TYPICAL SECTION AND ELEVATIONS
GARDEN GROVE USD – LA QUINTA AND PACIFICA HIGH SCHOOLS
MEDIA CENTER BUILDING SECTION AND ELEVATIONS
GARDEN GROVE USD – LA QUINTA AND PACIFICA HIGH SCHOOLS
CAFETERIA BUILDING SECTIONS AND ELEVATIONS
GARDEN GROVE USD – LA QUINTA AND PACIFICA HIGH SCHOOLS
AUDITORIUM BUILDING SECTION AND ELEVATIONS
GARDEN GROVE USD – LA QUINTA AND PACIFICA HIGH SCHOOLS
AUDITORIUM BUILDING PERSPECTIVE