Grade Separation (GS-16) Project
Project Location - Bensenville
N
Project Scope
New Two-Span Railroad Bridge
Retaining Walls
Culvert Work
Intersection Reconstruction/Widening
Drainage
Lighting
Traffic Signal Modernization
Landscaping
Letting Schedule
Advance embankment contract let in June
2011 – awarded Nov 2012
Estimated to begin Late Spring 2013
Bridge contract let January 18, 2013
Estimated to begin Late Spring 2013
Completion date August 29, 2014
Intersection Improvement contract targeted to
be let summer 2013
MOT
Temporary traffic signals/poles
Temporary pavement along north and
south side of IL 19
Build bridge abutments and pier
Temporary night time road closures along
IL 19 during CPR bridge girder erection
MOT
Posting of 12’-6” vertical clearance under
CPR bridge once beams are placed
Implement truck detour
Remove abandoned CPR grade crossing
in stages
Lower IL 19 profile
Speed limit reduced to 25 mph during
construction for safety
Truck Detour
Required when underclearance < 14’-9”
Goes into effect about 12 months into
Construction
Early Spring 2014
Truck Detour
Fully implemented when first beam is
erected
Removed once at grade crossing is removed
and profile is lowered
EB Truck Detour
Estimated 4 months
WB Truck Detour
1 additional month
Profile to be lowered in stages
Truck Detour Around O’Hare
TT
Irving Park Road
Mannheim Rd
York Rd
Touhy Ave
N
Short Term Truck Detour
Necessary during the intersection
improvement contract
Needed in two sub stages
1 week duration each
Limited turning movement due to work area
WB IL 19 to NB York Road
NB York Road to EB IL 19
Will be needed late summer/early fall 2015
Work Beyond Bridge Construction
Reconstruct/widen intersection
Drainage
Modernize traffic signals
Intersection lighting
Questions