New Ideas in Utility & Railroad Coordination
SCOD Annual Meeting
Indianapolis
Utility Reimbursement
TCA 54-5-804
Chapter No. 86 PUBLIC ACTS, 2003 1
CHAPTER NO. 86
HOUSE BILL NO. 900
By Representatives Head, Shepard, Borchert, Mike Turner, Hackworth, Eldridge,
Coleman, Maddox, McMillan, Pinion, McDonald, Tindell, Rinks, Fitzhugh, Harmon,
McDaniel, McCord, Russell Johnson, Overbey, Harrison, Cobb, Fraley, Hargrove,
Gresham, Bittle, Vincent, Wood, Hood
Substituted for: Senate Bill No. 588
By Senators Williams, Cooper, McNally, Fowler
AN ACT to amend Tennessee Code Annotated, Title 4; Title 54 and Title 55, relative to
transportation.
BE IT ENACTED BY THE GENERAL ASSEMBLY OF THE STATE OF TENNESSEE:
SECTION 1. Tennessee Code Annotated, Title 54, Chapter 5, Part 8, is amended by
deleting § 54-5-802 in its entirety and by substituting instead the following language:
Section 54-5-802. As used in this part, unless the context otherwise requires:
[Definitions]
2
Chapter 86 Eligibility
If the Project is Qualified under Chapter 86,
TCA 54-5-804 effective September 1, 2003
For a Utility to be Eligible:
 Project let for Contract Bid after September 1, 2003.
 Utility must submit plans within the 120 to 165 days
 Utility must have a permit for facilities on public ROW
 Utility must execute a relocation agreement with the State
> Relocate Prior to the Letting
> Included in the State highway Construction Contract
3
Chapter 86
Policy
Qualified projects are:
- Grade & Drain w/ROW acquisition
- Bridge replacement on State system
Projects which are NOT qualified:









Local Interstate Connectors (LIC)
Resurfacing (State or Federal funded)
State Industrial Access (SIA)
Minor intersection w/no ROW acquired
Bridge Repair
Safety
Maintenance
Signal Installation
Minor projects w/limited funding
4
Chapter 86
Policy
Changes
Compliance
Documentation
• Municipally owned
• Utility District
• Utility Cooperatives
Chapter 86 Scorecard
Construction
MOVE
IN
Fiscal Year
MOVE PRIOR
CH86
ADDED
COST
Total
CH86
Constr
Compl
Constr
Late
Utility
Delay
Total
Projects
Let
**
2003 – 2004
24
33%
48
66%
$ 7.6 million
72
28
12
2
$502,121,270
2004 – 2005
45
43%
60
57%
$ 24.1 million
105
37
11
1
$614,523,988
2005 – 2006
40
53%
36
47%
$ 13.5 million
76
23
2
0
$815,798,596
2006 – 2007
15
38%
25
62%
$ 6.7 million
40
6
0
0
$225,304,474
2007 – 2008
61
51%
58
49%
$33.7 million
119
2008 – 2009
70
57%
52
43%
$ 39.0 million
122
$743,175,729
* 2008-2009 FY based on current project schedule through end FY
** Total Projects Let data includes maintenance projects, but removes special Mowing, and Emergency lettings for the months that CH86 has been in effect.
6
Work Schedule
7
QUESTIONS?