SMOS L1 Processor Prototype V 1.6.1 Status

Download Report

Transcript SMOS L1 Processor Prototype V 1.6.1 Status

SMOS SODAP
Status
Michele Zundo
ESA/ESTEC
EOP-PEP
SMOS KP 0
09-Dec-2008
ESAC December 2009
1
Commissioning KP 0
Presentation Summary
•
•
•
•
•
•
SODAP Scope
SODAP Tasks
SODAP Team
SODAP Timeline
SODAP Procedures
SODAP Execution:
– SODAP Week 0
– SODAP Week 1, 2
•
•
•
SODAP Outcome
SODAP Observation
Conclusion and Recommendations
ESAC December 2009
2
Commissioning KP 0
SODAP Scope
• Switch On and Data Acquisition Phase
• Lesson learnt. Insure before instrument
commissioning starts the following:
1.
2.
3.
4.
5.
Basic Instrument Health check
Verification Space to Ground Links XB
End to End functional data flow verification
Communication Scenario Verification
Opportunistic feed to processor and DPGS
PLM-Health Check + SODAP-RF
ESAC December 2009
3
Commissioning KP 0
SODAP Tasks
For both ESAC and SVALSAT :
• Check RF-links and budget
• Verify XB masks and behaviour at high low
elevation and identify operational constraints.
• Confirm correctness timing of station and PLM
XB scheduling
• Exercise the different scenarios foreseen in
Communication Baseline Doc
• Exercise autonomous downlink and OBSW
reset
• Verify Data delivery to DPGS
ESAC December 2009
4
Commissioning KP 0
SODAP Team(1)
ESAC December 2009
5
Commissioning KP 0
SODAP Team(2)
+ Insa DPGS Operation Team at ESAC
ESAC December 2009
6
Commissioning KP 0
SODAP Timeline (1)
ESAC December 2009
7
Commissioning KP 0
SODAP Timeline (2)
ESAC December 2009
8
Commissioning KP 0
SODAP Procedures (1)
Described in:
• Plan for RF activities during SMOS SODAP
SO-PL-ESA-GS-6515
• SMOS SODAP-RF Procedure Issue 0 Draft 2
SO-GS-ESA-TP-6623
ESAC December 2009
9
Commissioning KP 0
SODAP Procedures (2)
ESAC
ESAC December 2009
10
Commissioning KP 0
SODAP Procedures (3)
SVALSAT
ESAC December 2009
11
Commissioning KP 0
SODAP Week 0
ESAC December 2009
12
Commissioning KP 0
PLM-Health Check
• Also known as Pre-SODAP
• Implemented week 0 following switch-on
• All OK. See Presentation by FOS
ESAC December 2009
13
Commissioning KP 0
SODAP Week 1-2
RF and scenarios
ESAC December 2009
14
Commissioning KP 0
Preliminary outcome ESAC (0)
ESAC December 2009
15
Commissioning KP 0
Preliminary outcome ESAC (1)
ESAC December 2009
16
Commissioning KP 0
Preliminary outcome SVAL (2)
ESAC December 2009
17
Commissioning KP 0
Preliminary outcome (3)
ESAC December 2009
18
Commissioning KP 0
Preliminary outcome (4)
ESAC December 2009
19
Commissioning KP 0
Preliminary outcome (5)
ESAC December 2009
20
Commissioning KP 0
Preliminary outcome (6)
•
All 27 tests executed.
•
More than 50 Gbyte data acquired and analysed.
•
135 XB passes have been scheduled
•
Functional chain OK (timing, dependency on elevation) i.e.
no operational constraint identified.
•
Timing setting tuned at LOS
•
Different setting of stuffing data with good results (TBC)
•
SVAL XB tracking using SB for initial lock tested
ESAC December 2009
21
Commissioning KP 0
Preliminary outcome (7)
•
ESAC links budgets and behavior at different elevation
ESAC December 2009
22
Commissioning KP 0
Preliminary outcome (8)
•
SVALSAT RF links budgets and behavior at different
elevations
ESAC December 2009
23
Commissioning KP 0
Preliminary outcome (9)
SVALSAT Conclusion
•
The Eb/No observed is between 15 and 20 dB over all passes
taken. This shows that there is a large system margin. At 15 dB
Eb/No the IF input level is -40 dBm and the antenna tracking
receiver SNR is about 17.5 dB. The threshold SNR for antenna
autotrack is 10 dB. This means that there is a system margin of
7.5 dB.
ESAC December 2009
24
Commissioning KP 0
Preliminary outcome (10)
•
Data continuity checked, major
problems observed since data is
lost on-board on MM partition 3
ESAC December 2009
25
Commissioning KP 0
Observations working list(1)
•
Informal working list of observations to be changed to
formal at subsystem level OBS/AR/NC/SPR if/as
needed.
•
List will be cleaned up at end of SODAP
•
Major issues from SODAP point of view are:
•
Missing Packet detected (problem with on-board
MM writing) (see presentation from FOS)
•
Duplicated/lost XB_DOWNLINK to SVALSAT
•
Occasional crashes of DAS acquisition
•
Inconsistent performance of E2E WAN transfer
ESAC December 2009
26
Commissioning KP 0
Observations working list(2)
ESAC December 2009
27
Commissioning KP 0
Preliminary Conclusions
• The System can deliver XB data to support
IOCP
• Both ESAC and SVAL scenario feasible
ESAC December 2009
28
Commissioning KP 0
Recommendations
(both Short and long
term)
1. Initiate IOCP with NRT Communication scenario 2
orbit overlap
2. Address problem in acq. part of DAS to make it robust
or consider alternate procurement.
3. Initiate implementation of OBSW modifications to cope
with MM write error and partition disabling issues
4. Complete performance evaluation of NRT WAN link.
5. Decouple XB station commanding from data
dissemination
ESAC December 2009
29
Commissioning KP 0
Thanks
•
Thanks to the all Team for hard work and long hours
ESAC December 2009
30
Commissioning KP 0