Transmission Services Agreement
Download
Report
Transcript Transmission Services Agreement
Transmission Services Agreement
rpc
A business of
Pwc
Agenda
Why have a Transmission Services Agreement (“TSA”)?
Where does the TSA fit within TWBP commercial arrangements?
Content of TSA
Next steps
2
pc
Why have a Transmission Services Agreement?
KEPCO owns the electricity transmission assets…
… and KPX, as system operator, operates these assets…
… so some form of arrangement between KEPCO and KPX is needed
“… to establish the contractual and operational framework under which
KEPCO provides transmission assets to KPX.”
3
pc
Why have a Transmission Services Agreement
(2)?
We believe that the current MOCIE notification which requires KEPCO to
provide transmission assets to KPX will not be sufficient going forward – for
example, the current notification does not address
roles and responsibilities for transmission system planning
detailed provision of information and access to systems (e.g. SCADA,
analysis datasets, rating information)
inspection of assets
rights / obligations for testing of new infrastructure
rights / obligations in force majeure situations
performance and operating standards (other than for protection assets)
general terms (e.g. modifications, disputes, confidentiality etc.)
It does not provide for any incentive mechanism for asset availability
The contents of the draft Korean TSA and concepts used are consistent with
international practice - in particular, we have drawn on the Australian and
Brazilian TSAs and on wider international experience on incentive regimes
4
pc
Where does the TSA fit? (1)
The TWBP commercial arrangements are intended to conform to the best
practice document structure for a liberalised electricity market…
Legislative framework
Regulatory documents
Market agreements
Technical codes
5
pc
Where does the TSA fit? (2)
There are three key documents in the market agreements and technical
codes category…
T
Proposed changes to any
of the documents must be
reviewed to check for
inconsistencies, and must
be approved by MOCIE
SO
G PSB T
D SO
TSA
Market Code
• Bilateral governance
• Multilateral governance
• MOCIE approval
• MOCIE approval
• Provision of assets to
SO
• Maintenance /
inspection rights
• Physical operation of
network
• Co-ordination of
network expansion
• Availability incentives
• Market Governance
• Pool Rules
• System operation and
security
• Revenue and
operational metering
• Settlement rules
• Retail market
operations
G PSB T
D SO
Grid Code
• MOCIE approval
• Connection
• Network planning and
expansion
• Network pricing
Each agreement deals with a consistent set of commercial and technical issues
– e.g. the technical details of information to be provided by KEPCO to KPX on
transmission assets is set out in the TSA under which KEPCO agree to provide
the assets
6
pc
Where does the TSA fit? (3)
The TSA is therefore a key part of the overall commercial
arrangements for the TWBP environment
it provides the contractual framework for the provision of transmission
assets to the system operator
its effective operation influences the overall efficiency of the operation of the
market
As such, in common with the market code and grid code
KEC / MOCIE have a valid interest in the terms of the TSA, particularly in
relation to the promotion of overall efficiency
compliance with the terms of the TSA should be a legal requirement set
down by KEC / MOCIE
modifications to the TSA going forward should be approved by KEC /
MOCIE
7
pc
Content and purpose
The Transmission Services Agreement:
Lists the assets to be operated by KPX
Sets out rights and obligations for maintenance and inspection
Sets out rights and obligations for physical asset operation
Defines rights and obligations for network planning and new
connections
Sets out governance procedures
Provides an incentive regime for asset availability
The current draft of the TSA represents drafting instructions to lawyers – it
is not the final version of the agreement
8
pc
Provision of relevant assets
KEPCO agrees to provide all “relevant assets” for commercial use and
operational control by KPX, on an exclusive basis, subject to the terms
of the TSA
The “relevant assets” are all transmission assets owned or maintained
by KEPCO save those listed in Schedule 1 of the TSA
The relevant assets may be changed according to the procedure set
out in the TSA when
new transmission assets are commissioned
the capability of assets changes
assets are retired
9
pc
Maintenance obligations and inspection rights
KEPCO is required to
maintain its relevant assets (and associated equipment) in accordance with
the technical requirements of the Market Code
ensure all personnel are appropriately accredited
KPX may inspect the KEPCO facilities according to the procedures set
out in the TSA to verify compliance
10
pc
Physical operation of assets
KEPCO must ensure that KPX always has access to information and
systems necessary for physical operation, including
SCADA data
analysis datasets
technical asset information (set out in Schedule 3)
KEPCO is required to comply with switching instructions (incl. for
reactive plant) from KPX in accordance with the Market Code
KPX is required to set out standards / principles for protection system
configuration; for its own protection equipment, KEPCO is required to
implement these standards
KPX, with KEPCO, must develop a black start plan, and comply with
the Market Code in the event of a total or partial shutdown
11
pc
Network expansion planning
The process of network expansion planning in the TSA is divided into
indicative planning and detailed planning
Indicative network planning
Detailed network planning
Forecasting possible G & L growth
over next 10 years
Development of detailed
requirements for transmission
augmentation
Analysis of existing and future
transfer capabilities
Statement of high level
requirements for transmission
augmentation
Other operational and economic
information of use to prospective
market participants
Analysis of technical options for
augmentation
Full specification of detail of
optimal augmentation option
Scheduling of augmentation
projects across system
This separation is consistent with international practice – e.g. the
processes followed by NEMMCO in Australia and NGC in the UK
12
pc
Network expansion planning (2)
KPX is required to
ensure that, for long term planning purposes, KEPCO has access to system
models and information used for operational planning
provide an indicative expansion plan to KEPCO
KEPCO is required to provide justification where it has not taken into
account information provided by KPX in its detailed expansion plan
KPX and KEPCO are required to publish their respective plans
13
pc
New connections
KEPCO is required to
provide information to KPX on proposed new connections, and provide
justification where it has not taken into account comments by KPX
keep KPX informed of changes to existing connection details
KPX must agree KEPCO proposals for testing of new assets prior to
their connection to the relevant assets
programme of testing
confirmation that assets meet performance / operating requirements
confirmation of detail of safety measures
14
pc
Governance and general terms
KEC shall arbitrate between KPX and KEPCO in any disputes under
the TSA (assuming the dispute resolution procedures in the Market
Code do not apply)
The TSA can only be modified following a proposal from KEPCO or
KPX, and proposed modifications must be approved by MOCIE
The TSA contains force majeure and confidentiality conditions
15
pc
Incentive regime on asset availability
The regime is intended to ensure that the assets are provided in a way
which is consistent with overall economic efficiency in the market
provide incentives to ensure assets are available and well maintained
provide incentives to commit to (and implement) timely outages
ensure that some portion of the cost to the market of amending generation /
load schedules to manage transmission constraints resulting from
transmission outages is borne by KEPCO
The incentive regime in the TSA mirrors international practice
UK: distribution companies
Brazil: Transmission Concessionaires
16
pc
UK: Distribution incentive scheme
Ofgem (UK regulator) recently introduced an incentive scheme for
distributors to penalise those companies which fail to meet targets for
number of interruptions
length of interruptions
quality of telephone response to customers
The scheme will initially run for 3 years (from April 2002)
Discos can be penalised by up to 2% of their annual regulated revenue
(c. £4m per company per annum) for failure to meet targets
They can earn additional revenue in the final year if they exceed
targets
17
pc
Brazil: ISO – Transmission owner scheme
The TSA between ONS (the Brazilian ISO) and the Transmission
Concessionaire contains an incentive scheme for asset availability
ONS pays the TC 1/12 of its annual allowed revenue per month - the
allowed revenue for transmission assets includes:
Direct and indirect costs of transmission network services
Availability of equipment to compensate reactive power
Ancillary services
The payment from ONS is reduced by a factor based on the duration of
planned and unplanned outages
The per minute reduction in payments for unplanned outages is higher
than that for planned
planned outages: R$ 10/minute
unplanned outages: R$ 150/minute for first 300 minutes, R$ 10/minute
thereafter
18
pc
Brazil: ISO – Transmission owner scheme (2)
No reduction is made for outages which
are less than one minute in duration
result from network improvements
are requested by ONS or third parties for operational or safety reasons
are caused unintentionally by ONS
result from force majeure
The reduction in payments will be capped as follows
for each year, the reduction will be no more than 25% of allowed revenue
for each month, the reduction will be no more than 50% of the monthly
allowed revenue, with the remainder being carried over to the following
month (subject to the yearly maximum)
The reduction rates per minute do note vary by time or asset class
In the first 6 months of operation, ONS calculates the reduction in
payments, but it is not applied
19
pc
Detail of incentive regime in draft Korean TSA
The TSA defines a concept of “permitted outages”
notified to KPX at least 4 weeks prior to commencement
end on time
For each year, and for each class of asset, there is a maximum
duration and frequency of permitted outages
Outages not notified more than 4 weeks in advance do not count
against this maximum duration / frequency but do count as nonpermitted
For all non-permitted outages, KEPCO is required to pay KPX a sum
defined by a schedule to the agreement (to be defined)
20
pc
Incentive regime – worked example
Suppose for asset class j that the permitted off-peak outage duration was
10 hours and the permitted off-peak outage frequency was 5
Asset class J
Cumulative
duration for
threshold
purposes
Cumulative
frequency for
threshold
purposes
Penalty
incurred?
Outage of 2 hours notified on time
2
1
No
Outage of 1 hour notified on time
3
2
No
Outage of 2 hours not notified on time
3
2
2 x value
Outage of 10 hours notified on time
13
3
3 x value
Outage of 5 hours notified on time
18
4
5 x value
21
pc
Incentive regime options
There are a number of possible options around the incentive scheme as
currently specified – for example
it could be “turned off” for the early period (e.g. first year?) of market
operation, particularly if the regulatory regime for transmission is not
well developed at that stage
the specification of the outage thresholds and the penalty values could
be more or less detailed (e.g. by class of asset, by time period etc.)
some types of outages could be taken out of the regime (e.g. outages
caused by KPX or resulting from force majeure)
the regime could be “two sided” – it could offer KEPCO
an upside if they take fewer outages than planned
penalties if they take more outages than planned
22
pc
Next steps
The current draft of the TSA
has been developed by KPX / PwC
represents drafting instructions to lawyers
To reach a finalised and enforceable agreement
the agreement will need to be reviewed by KPX, KEPCO and KEC / MOCIE,
and possible refined so that each are comfortable with its content
the drafting needs to be legally reviewed
KEC / MOCIE need to ensure that the legal market framework requires
compliance with the TSA
23
pc
rpc
TM
PwC Consulting refers to the management consulting
services businesses of the member firms of the worldwide
PricewaterhouseCoopers organisation.
2001 PricewaterhouseCoopers. All rights reserved.
A business of
Pwc