TURNER INDUSTRIES GROUP, LLC
Download
Report
Transcript TURNER INDUSTRIES GROUP, LLC
TURNER INDUSTRIES GROUP, LLC
LESSONS LEARNED
POST-HURRICANE TURNAROUNDS
Houston Business Roundtable
May 10th, 2006
REPRESENTATIVE TURNAROUNDS
Case 1 - 90,000 BPD refinery in Colorado
•Full plant outage 1st qtr 06’ - planned 42 days oil-to-oil
•350,000 direct man-hours (all contractors)
•Peak loading of approximately 1,000 directs
Case 2 - 200,000 BPD refinery in Louisiana
•FCCU, Alky, HDS & Sulfur Block 1st qtr 06’ - planned 32 days
oil-to-oil
•100,000 direct man-hours (Turner only)
•Peak loading of approximately 350 directs
CASE 1
350,000 direct man-hours with a total installed cost of
approximately $80MM (including Capital Projects)
Planned peak manpower loading of approximately 1,000
directs
Planned for 4th qtr 2005 (subsequently deferred to 1st qtr
2006)
HDS, Crude & SRU 3-year run-life to Spring 2008
AU, FCC, Cat-Poly, VRU & Amine 5-year run-life to Spring
2010
1,200 expense work items
ULSD project ($450MM)
FCC revamp adding a 3rd stage separator ($4MM)
CAPEX scope ($2MM)
The turnaround presented specific issues not representative of a
"typical" turnaround
(2) large capital projects with an anticipated peak manpower
at or around the turnaround time frame
TA hampered by a lack of availability with regard to plant
access, lay down areas, office locations, contractor trailers,
Owner personnel, contractors and craftsman
Local market is not conducive to heavy industrial
construction
The turnaround timing was during winter conditions
TA would reach an over maximum manpower density
To account for these factors, the estimated productivity factors
were increased over typical industry standards
50% productivity loss (30% outage factor and 20% nontypical outage factor)
10% contingency
15% allowance for scope growth
Concerned with ability to attract and retain craft labor
Instituted plan to over-man the turnaround in the initial stages
in order to assure retention for;
Scope growth
Contingency
Unanticipated productivity losses
Absenteeism & attrition
Recruiting issues
P3 schedule developed to account for resource loading
contingency
Developed schedule under normalized conditions (no
allowances or contingency)
Leveling techniques used to optimize the schedule to
front-end load resources (direct labor)
Added productivity factors to allow for reconciliation to
the final budgeted man-hours
Developed external Excel based spreadsheet used to
adjust to additional 25% man-power allowance
Re-allocated manpower in P3 via hard logic
Design craft wage rates to attract quality craft & supervision
Original wages were set for 4th qtr 05’ execution
TA execution window was deferred to 1st qtr 06’
Conducted an analysis of current, prevailing and anticipated
wage rates that would be required for the new TA timeframe
TA, originally targeted for 4th qtr 05’, was on the downward
side of the 4th qtr 05’ peak
New TA window would be in the midst of peak manpower
requirements in the Gulf South
This presented several critical (high risk) factors with regard to
contracting and labor
Description of Threat
Severity Probability
Lack of resources (general)
HIGH
MEDIUM
Lack of qualified crafts and their availability
HIGH
HIGH
Lack of resources in view of Colorado
HIGH
MEDIUM
Continual decline of qualified work force
HIGH
HIGH
Workforce attracted away from industrial
sector
Lack of specialty welders
HIGH
HIGH
MEDIUM MEDIUM
Impact of Threats
•Unable to attract craft
•Unable to adequately
staff
•Safety concerns
•Potential QA issues
•Increased personnel
turnover
•Schedule slippage
•Increased LPO
Additional risk to TA due to industry manpower requirements
Would need to implement new wage & compensation structure
Allow for “market-plus” condition w/ “Market” = Gulf
South
Ensures wage rates would be sufficiently higher than those
in the Gulf-South
Coupled with other incentives and completion bonuses
would allow us to attract and maintain quality craft &
supervision
However, Hurricane’s Katrina & Rita shifted the industry and
further exposed the TA
Projects & TA’s were shifting to 1st qtr 06’, already the predicted
peak
Increased industry peak manpower requirements above those
previously forecasted
Re-build effort attracted craftsman away from the industrial
sector
Developed risk model for three different wage rate / incentive
structures
Based on HBR data and contractor surveys
Survey contractors for current / relevant experiences with
post-hurricane wages
Optimize wage structure to remove profit motive
Ensure increase goes to craft
Develop flexible attractive wage & incentive structure for
current environment
Offer contingency for RLT approval
OPTION “0” - Maintain current wage & compensations structure
at pre-hurricane structure
Description of Threat
Probability
Consequence
Forces contractors to recruit non-familiar craftsman
HIGH
Safety, QA, productivity
Forces contractors to recruit less skilled craftsman to
match wage rates
Lower skill set equals decreased safety performance
Lower skill set equals decreased productivity
HIGH
Safety, QA, productivity
Will increased attrition and turnover (less dedicated
craftsman)
Increases recruiting time frame
HIGH LTI, Recordable, Fatality
MEDIUM Cost & schedule creep
(LPO)
MEDIUM Safety, QA, productivity
HIGH
Cost & schedule creep
(LPO)
OPTION “1” - Modify wage & compensation to “level 1”
Added approximately 10% to wages w/ an added safety &
completion bonus equivalent to 10% of base wage rate
Description of Threat
Increases TA cost
Probability
HIGH
Consequence
Approximate $1MM
Forces contractors to recruit non-familiar craftsman
MEDIUM Safety, QA, productivity
Forces contractors to recruit less skilled craftsman to
match wage rates
Lower skill set equals decreased safety performance
MEDIUM Safety, QA, productivity
Lower skill set equals decreased productivity
Will increased attrition and turnover (less dedicated
craftsman)
Increases recruiting time frame
LOW
LTI, Recordable, Fatality
LOW
Cost & schedule creep
(LPO)
MEDIUM Safety, QA, productivity
MEDIUM Cost & schedule creep
(LPO)
OPTION “2” - Modify wage & compensation to “level 2”
Added approximately 25% to wages w/ an added safety &
completion bonus equivalent to 25% of base wage rate
Recommended structure to drive risk profile to “low”
(schedule driven TA)
Description of Threat
Probability
Consequence
Increases TA cost
HIGH
Approximate $5MM
Forces contractors to recruit non-familiar craftsman
LOW
Safety, QA, productivity
Forces contractors to recruit less skilled craftsman to
match wage rates
Lower skill set equals decreased safety performance
Lower skill set equals decreased productivity
LOW
Safety, QA, productivity
LOW
LOW
Will increased attrition and turnover (less dedicated
craftsman)
Increases recruiting time frame
LOW
LTI, Recordable, Fatality
Cost & schedule creep
(LPO)
Safety, QA, productivity
LOW
Cost & schedule creep
(LPO)
Turnaround Results
Wages: The wage structure ended up below current Gulf Coast
norm as competition grew from other turnarounds and posthurricane rebuilding efforts
Wage rates were set at option “1” with safety &
completion bonus to be earned separate from wages
The execution team did not implement contingency for
raising wages to option “2”
Per diem and travel were paid
The safety & completion bonus were separated from wage
rates instead of earned in real time
Wages affected recruiting but did not affect retention
Manpower: The turnaround was 10-15% under-manned and 2025% under managed.
Contingency factor too low (10%)
Used incorrect resource profile as the basis for recruiting
Manpower profile based on estimated man-hours per logic
driven P3 schedule
No allowance for over-manning
No allowance for contingency or scope growth
Relaxed English speaking requirement to attract craft of
Hispanic decent and from Puerto Rico
Absenteeism: was report to be at approximately 10%
Although securing manpower was an issue, absenteeism &
attrition appeared to be a non-issue
Safety, Quality & Productivity: poor performance by all
standards
(4) recordable injuries on 500,000 direct man-hours
(including capital projects)
Weld rejection rate was high, especially on alloy piping
Leaks on start-up
Start-up delayed due to Capital Projects, expense work
completed on time
Contributing factors:
Competing turnarounds in Gulf Coast paying higher wages
than anticipated
Per diem for working locally (per diem never adjusted)
Contractors were stretched beyond their ability to provide
a “known” work force. Recruiting non-familiar craftsman or
craft from non-Gulf Coast regions
Inadequate allocation of QC resources (Owner driven)
Inordinate amount of late scope additions & discovery
items (added 150,000 man-hours)
Increased unit congestion above 1,500 directs vs. 1,000
planned
CASE 2
100,000 Turner direct man-hours with a total installed cost
of approximately $125MM (including Capital Projects)
Planned peak manpower loading of approximately 1,000
directs
TA premises set by Owner for a sequential unit turnaround
of the FCC, Alky, HDS and Sulfur units
FCC revamp executed by Cat Specialist
HDS & Sulfur units executed by GC
Turner-Industries expense and CAPEX related scope of
work in the FCC and Alky units.
The Owners planning premises made some allowances for typical
turnaround inefficiencies
Owner Alliance estimating manual plus 20% or Page &
Nations plus 40%
Expected significant scope growth through discovery
Mobilized contractor supervision and some craft early
To account for these factors, the Owner made allowance over their
typical standards
Allowance for discovery, analysis, recommendation & repair
in TA timeline
Concerned with ability to attract and retain craft labor
Manpower / resource profiles
Resource loading the P3 schedule with the total
estimated man-hours
Inclusive of productivity factors
Included indirects on an individual task basis
Levelized using a systems turnover based priority
Craft labor rates were estimated pre-hurricanes
Adjusted 1st qtr 06’
Subsequent analysis of the prevailing wages rates and
compensation structures for competing projects and
turnarounds forced several revisions to the compensation
structure
Initially the wages were set for the Gulf-Coast standard
plus $3.50 per hour with an additional $3.50 per hour
completion bonus
The final rate structure was set (2) weeks prior to the oilout date to include the total $7.00 per hour as part of the
base wage with an additional $3.50 per hour completion
bonus.
Turnaround Results
Wages: Owner set the wage rates at post-hurricane rates plus
additional incentives
Per diem was paid but no reimbursement was allowed for
travel
Wages proved to be sufficient to attract craft labor
Attrition was not due to wages
Per diem was not adequate to cover the lodging costs posthurricane($60 per day per diem versus $90 per day hotel costs)
Manpower: Turner was 10-12% under-manned in the initial
stages of the TA
Turner’s was able to satisfy their manpower needs pre-TA
Previously committed craftsman were either not showing up
or left while in process
Several factors contributed to the depletion of the recruited work
force;
The accelerated start of competing projects / turnarounds
plus escalating wages by competing projects
(3) day orientation cycle (unpaid)
Per diem proved to be inadequate for local housing market
post-hurricanes
Estimating standards used in 2004 and proved to be inaccurate for a 2006 TA
TA Execution was during peak manpower requirements in
the industry
No allowances for scope growth or discovery in resource
profile
Resource profile in P3 proved to be inaccurate;
Pipe resources (fitters & welders) were identified in the P3
schedule for only those activities that involved pipe welding
Other activities normally classified as piping activities were
classified as boilermaker activities
Gives a false measurement of the actual pipe fitters required
for the scheduled work.
Manpower concerns were alleviated by several factors:
Late turnover of systems from decommissioning pushed
schedule activities
Recruiting effort continued with provisions made for
securing non-traditional labor sources
Gained peak manpower earlier than scheduled
Turner was successful in achieving peak manpower within
their scheduled window (adjusted for late turnover)
Owner late in turning over discovery work items
Absenteeism: Estimated at 10-12%
Virus attack on TA (craft, staff & supervision)
An issue with the critical craft such as pipe fitters and
welders
For example: Resource profile calls for (4) welders, the
absence of (1) represents a 25% absent rate
Completion bonus not a factor at beginning of TA
Criteria helped as craft banked several weeks of bonus (no
more than 2 absences allowed)
Attrition was not due to wages
General malaise in industry
Safety, Quality & Productivity: acceptable performance
(1) recordable injury
High weld reject rate. Fit-up issues due to lack of qualified
pipe fitters lead to weld reject rates
Mechanical craft with productivity ranging from a low of .85
to a high approaching 1.00 (<1.00 poor)
Piping craft productivity is forecasted at a .65
No leaks delaying systems start-up
Instituted strict QC program to follow flange make-up
Increased QC staff above previous “normal”
Other contributing factors;
Productivity factor used for estimating and resource loading
was too low for current condition of labor market
Added requirements of post-BP environment increases travel
time and complicates logistics
A factor of 40% is to low for a turnaround of this magnitude
and complexity
Crew mixture of foreman to craft was set by Owner on a 121 basis, revised to a 10-1 ratio but this still proves to be too
high in a turnaround environment
Owner late in turning over discovery work items
Improper interpretation of Page unit rates
Page is base rate “plus” inefficiencies for non-TA
construction activities
No account made for 2-year difference in labor market and
post-hurricane environment
Lessons Learned
Wages & incentives;
Proved to be insufficient for recruiting in a labor market not
in view of the Gulf-South, proved effective in recruiting for
Gulf-South work
Wages had limited impact on retention as competition
increased
Incentives proved effective in retaining craft toward end of
TA as they start seeking ROF
Recognize the market & set attractive per diem
Possibly include incentives in bare wages
Estimating
Revise estimating standards to account for current
environment. History does not apply.
Plan for contingency wage increases
Historical issue of under-estimating contingency & scope
growth
Anticipate the added requirements of the post-BP
environment (increase in travel time and complicated logistics)
Increase indirect staffing required to plan, monitor and
coordinate craft (supervision, QC, etc.)
Planning
Develop discovery work within first TA 30% of duration
Front-end load manpower, back-end load scope to first 50%
duration
Develop TA schedule to allow for over-manning in first 50%
of duration
Include allowances in resource profile as well as timeline
Management:
Craft supervision has increased responsibility for planning,
productivity & QA/QC. Decrease ratio of craft to foreman to
6-8:1
Anticipate additional QC staffing to assure tightness