Transcript Slide 1

EE535: Renewable Energy:
Systems, Technology &
Economics
Project Financing
Cost of Energy Drivers
1. Capital Costs (and the cost of borrowing the
money)
2. Fuel Costs
3. Operation and Maintenance (O&M) Costs
4. Decomissioning Costs
Simple Payback Time
• Payback Time = Number of years taken to
recover capital outlay
• Simple Annual Method
– Calculate the cost per unit energy on an annual basis
– Capital is first annuitized (considered to be repaid in
equal amounts over the project lifetime)
– Average fuel and O&M costs added to annual
payments
• Average Cost of Energy:
Cost per unit of energy = (annual capital repayment + average running costs) / average annual energy output
Discounted Cash Flow
• For capital intensive power projects, analysis based on
discounted cash flow (DCF) is typically used
• Related to the time preference for cash
• We can forego the use of a euro today in order to have
a euro plus an additional sum in the future
• A sum of money today (e.g. €100 today has a future
value of €260). OR The present value of €260 in 10
years time at a certain interest rate is only €100).
• Inflation must also be included
Real Interest Rate = Monetary Interest Rate – Rate of Inflation
Value of a sum in n years at a discount rate of r is given by: Vn = Vp(1 + r)n
Present value of a sum received or paid in the future is given by: Vp = Vn / (1 +r)n
Choice of Discount Rate
Annuitized Value of Capital
•
The Discount Rate (or real interest rate) is the rate used to discount future
cash flows to their present values is a key variable in the DCF process.
Determined by the company in the light of risk, inflation, etc
•
The annuitized value of capital costs (annual repayment in € ) (or equivalent
annual cost EAC) for various discount rates and capital repayment periods
is calculated by first calculating the loan repayment factor :
• A = (1 – 1/(1+r)n) / r
•
EAC = NPV / A
•
Where NPV is the Net Present Value, which is the summation of all the
present values of future income and expenditures
•
NPV = Rt / (1 + r)t
– Where Rt is the net cashflow at time t, r is the discount rate
Net Present Value
•
•
For projects that take several years to build and may
be subject to periodic refurbishment, a full net present
value calculation is required
Process:
1.
2.
3.
4.
5.
Itemise the capital and running costs for each year of the project
life
Calculate the separate Present Value of all these annual costs
using an appropriate discount rate, and sum to give the NPV
Itemise the output for each year over the project life
Calculate the NPV of all these annual outputs, expressed usually
in kWh
Calculate the unit cost in pence per kWh as:
Net Present Value of Costs (cent) / Net Present Value of Output (kWh)
Net Present Value
•
NPV is an indicator of how much value an investment or project adds to the
firm.
•
With a particular project, if Rt is a positive value, the project is in the status
of discounted cash inflow in the time of t. If Rt is a negative value, the project
is in the status of discounted cash outflow in the time of t.
•
Appropriately risked projects with a positive NPV could be accepted. This
does not necessarily mean that they should be undertaken since NPV at the
cost of capital may not account for opportunity cost, i.e. comparison with
other available investments. In financial theory, if there is a choice between
two mutually exclusive alternatives, the one yielding the higher NPV should
be selected.
•
A decision should be based on other criteria, e.g. strategic positioning or
other factors not explicitly included in the calculation.
NPV > 0
Adds Value to Company
NPV < 0
Subtracts Value from Company
NPV = 0
the investment would neither gain nor lose value for the firm
Exercise
• A company must decide whether to introduce
erect a new wind turbine. The project will have
startup costs, operational costs, and incoming
cash flows over six years. This project will have
an immediate (t=0) cash outflow of €100,000
• Other cash outflows for years 1-6 are expected
to be €5,000 per year. Cash inflows are
expected to be €30,000 each for years 1-6. All
cash flows are after-tax, and there are no cash
flows expected after year 6. The required rate of
return is 10%.
• Is this a good investment for the company?
Solution
Year
Cashflow
Present Value
0
(30000 - 5000) / (1 +0.1)^0
-100000
1
(30000 - 5000) / (1 +0.1)^1
22727
2
(30000 - 5000) / (1 +0.1)^2
20661
3
(30000 - 5000) / (1 +0.1)^3
18783
4
(30000 - 5000) / (1 +0.1)^4
17075
5
(30000 - 5000) / (1 +0.1)^5
15523
6
(30000 - 5000) / (1 +0.1)^6
14112
NPV
8882
NPV = € 8,881.52 is positive so probably a good investment!
Internal Rate of Return
• The internal rate of return on an investment or potential investment
is the annualized effective compounded return rate that can be
earned on the invested capital.
• In more familiar terms, the IRR of an investment is the interest rate
at which the costs of the investment lead to the benefits of the
investment. This means that all gains from the investment are
inherent to the time value of money and that the investment has a
zero net present value at this interest rate.
• Because the internal rate of return is a rate quantity, it is an indicator
of the efficiency, quality, or yield of an investment. This is in contrast
with the net present value, which is an indicator of the value or
magnitude of an investment.
• An investment is considered acceptable if its internal rate of return is
greater than an established minimum acceptable rate of return.