New Bangkok International Airport
Progress Information & Schedule Analysis
FOR Air traffic Control Tower
2003. 6. 18
KOICA(NESDB)
INFORMATION OF NBIA’S CONTROL
TOWER & NAVAIDS
●
IMPLEMENTING AGENCY : Aeronautical Radio of Thailand
Ltd. ( other government agencies)
● INVESTMENT BUDGET : 2,307 Million Baht
● SCOPE OF WORK ( including Design, Manufacture,
Installation, Test & Commissioning Duration )
1. Construction of ATC Complex : 2003. 4 ~ 2005. 2
2. Provision of surveillance system : 2003. 6 ~ 2005. 6
3. Provision of navigation aids : 2003.12 ~ 2005. 6
4. Provision of aeronautical radio system
5. Provision of communications network : 2003. 5 ~2005.5
6. Provision of flight data
7. Provision of airline services equipment
8. Air traffic operation and communications
●
PROGRESS STATUS : Under bidding process
as of Jun. 2003
ATCT
LLZ/DME
Air Navigation System of IIA
TVOR/DME
GP
ASR/MSSR
TDWR
TRACON
LLWAS
Surveillance Radar of IIA
Meteorological Radar of IIA
In case of NBIA
In case of NBIA
Implementation by
Aeronautical Radio of
Thailand Ltd.
Implementation by
Department of
Meteorology
Design & Construction &
Test :Jun.2003~Jun.2005
Design & Construction &
Test :Jan.2003~Jun.2005
Control Tower of IIA
CONSTRUCTION PERIOD
1997.07 ~1999.10( 28 MONTHS)
INSTRUMENT & EQUIPMENT
INSTALLATION PERIOD
1999.11 ~2000.06( 8 MONTHS)
H = 100.4 M
MAJOR FACILITIES & TEST
- Structural Stability for Strong
Earthquake : install. Of HMD
- Perfect Stormproof Test for
Violent Breeze at 60m/s
Incheon International Airport
Control Tower Outcome
Opening Date
100
42 MONTHS
AIRPORT OPERATION
READINESS : 6 MONTHS
Progress
EQUIP INSTALL. & TEST
: 8 MONTHS
CONSTRUCTION
: 28 MONTHS
0
DESIGN & BIDDING
: 16 MONTHS
Duration
Incheon International Airport
Control Tower Outcome
Incheon International Airport
Control Tower Outcome
Incheon International Airport
Control Tower Outcome
Incheon International Airport
Control Tower Outcome
Opening Date
100
42 MONTHS
AIRPORT OPERATION
READINESS : 6 MONTHS
Progress
EQUIP INSTALL. & TEST
: 8 MONTHS
CONSTRUCTION
: 28 MONTHS
0
DESIGN & BIDDING
: 16 MONTHS
Duration
COMPARISON BETWEEN NBIA AND OTHERS
AIR TRAFFIC CONTROL (ATC) TOWER
DESCRIPTION
NBIA
INCHEON
Height (meter)
130
100
Period
‘03.5~’05.6
Duration
26 months
Const.Method
N/A
MIDWAY
45(150f) 78(260f)
97.7~’00.6 94.10~96.4
36
O’HARE
18
93.6~95.7
26
Reinforced Pre-cast Reinforced
AIR TRAFFIC CONTROL TOWER SCHEDULE
COMPARISION BETWEEN NBIA AND IIA
100
90
80
70
60
50
40
30
20
10
0
READINESS
6 MONTHS
(NOV. 02 ~ SEP 05)
EQP. INSTALL. & TEST
20 MONTHS
26 MONTHS
DESIGN & CONSTR.
6 MONTHS
TENDER & AWARD
1997
100
90
80
70
60
50
40
30
20
10
0
3 MONTHS AIRPORT OPERATION
NBIA OPEN AIRPORT: 29 SEP. 2005
1998
1999
2000
2001
2002
2003
IIA OPEN AIRPORT: 29 MAR. 2001
2004
2005
6 MONTHS
AIRPORT OPERATION
READINESS
8 MONTHS
EQP. INSTALL. & TEST
28 MONTHS
36 MONTHS
CONSTRUCTION
16 MONTHS
1992
1993
1994
1995
1996
1997
1998
1999
‘2000
DESIGN & AWARD
THE ROLE OF CONTROL TOWER
●
●
●
●
The control tower as the most important facility for air
control is equipped with communication intelligence
systems.
All sorts of facilities such as control facilities play the
most significant role for the safety of aircraft and
passengers
Without ATCT functions, we can’t do start up and
commissioning the whole NBIA integrated system as
airport operational readiness
ATCT progress delay impacts directly opening date of
NBIA