Arvada’s TOD Vision
Our team’s development proposal was conceived in response to the Project
Vision and Goals contained in the Request for Qualifications. The Vision and
Goals appropriately identify the qualities of a new, vibrant urban place that
generates transit ridership and sound economic development, including:
•
•
•
•
•
Urban
Pedestrian Oriented
Mixed Use
Vibrant
Multi modal
Olde Town TOD
•
•
•
•
•
Quality design
Connected
Distinct character
Less surface parking
Sustainable
Option A Program
RTD Stand Alone Garage
• 400 Parking Spaces at Wadsworth/Grandview
(3 levels)
• Bus Facility on Tiller Lot Site
Apartments
• 250 Residential Units
• 182 Micro Residential Units
Hotel at Vance
• 108 Hotel rooms
Retail
• 46,000 SF
Olde Town TOD
Option B Program
RTD Bus Station with Public Parking
• 400 – 700 Parking Spaces
• 8 Stall Bus Facility
Hotel at Vance
• 105 Hotel Rooms
Apartments
• 300 Residential Units
• 162 Micro Residential Units
Retail
• 28,500 SF
Olde Town TOD
Theatre
Transit Plan
Option B Perspective – 432 Parking Spaces and 8 Stall Bus Facility; Optional Bridge to Platform
Olde Town TOD
Theatre
Option B LEVEL 1 - 43 SPACES
Olde Town TOD
432 SPACES TOTAL
Theatre
Option B3 Perspective - 690 Parking Spaces and 8 Stall Bus Facility; Optional Bridge to Platform
Olde Town TOD
Theatre
Option B3 LEVEL 1 - 42 SPACES
690 SPACES TOTAL
OPTION B – 432 SPACES
Transit Plan
OPTION B3 – 690 SPACES
Early Phase
•
Block 1- Multi-modal transit facility
at the Station.
•
Block 2 and/or 3 - At grade “microhousing” and multi-family
development along 56th Avenue.
•
Block 6 - Small retail or commercial
office development along
Wadsworth
•
Block 4 - Limited service hotel use
along Vance
•
May incorporate interim surface
parking solution
Olde Town TOD
Later Phase
•
Block 4 – Limited Service Hotel
Use along Vance
•
Block 5 - Multi-family housing on
a parking podium along
Grandview and Wadsworth.
•
Accommodate parking for
adjacent uses as required if land
being used for interim surface
parking
Olde Town TOD
Communication, Outreach & Feedback
Stakeholders
• City of Arvada
• Arvada Urban Renewal Authority
• RTD
• Trammell Crow Company
• Community and Neighborhood Groups
Information and Feedback
• www.OldeTownTOD.org
• NotifyMe alert system – sign up on web site
• Print Media Communications – Arvada Report and local newspapers
• Community Meetings to Review Plans and Entitlement Progress
• Update City Council, AURA Board and RTD as requested
• Process for Approvals
–
–
Transit Features
9-acre Site
Olde Town TOD
Milestone Schedule
As of November 1, 2013
EOC Agencies Initiate Partnership – 2010
RFQ Issued – March 1, 2013
RFQ Response – April 8, 2013
RFP Response – May 24, 2013
EOC Interviews – June 10, 2013
Executed Exclusive Negotiating Agreement (ENA) – July 26, 2013
Define Transit Element Concept Alternatives – September 3, 2013
Approve Transit Element Concept Alternative – September 30, 2013 (Pending)
Master Developer Completes Site Due Diligence – November, 2013
Finalize Finance Plan for Transit Elements – January, 2013
Master Developer Finalizes Land Use Program – January, 2013
Arvada and Master Developer Finalize Site Infrastructure Plan – January, 2013
Complete Site Master Plan, Zoning and Design Guidelines – March, 2014
Execute Joint Development Agreement (JDA) – March, 2014