Transcript Document

PPP in Affordable Housing with specific
reference to JNNURM
Rakesh Bangera
Head – Analytical Team
CRISIL Risk and Infrastructure Solutions Limited
28 January, 2010
PCNTDA’s experience on…
• Developing a 53 hectare township to;
– Cater to all sections of the society
– Provide social and physical infrastructure services
• Utilizing support from JNNURM for constructing 5040 BSUP housing
units and making PCNTDA area slum free
• Providing PCNTDA with 2275 units of affordable housing stock for EWS
and middle income sections of the society
– In addition to schools, hospitals and public amenities
• Protecting PCNTDA from conventional construction contract risks
• All packaged in one contract through a unique PPP structure
2.
PCNTDA is a Development Authority
•
Established in 1972 by Government of Maharashtra
•
Mandated to develop 43 sq kms of peri-urban areas towards the north
of Pune Metropolitian area
•
Till date it has actively acquired and developed about 11 sq kms in a
planned manner
•
Has developed infrastructure integrated seamlessly with neighbouring
Pimpri Chinchwad Municipal Corporation
3.
The Project
4.
The Project
PPP Structure
Process Adapted
Outcome
Project Highlights
•
Area: 53 hectares
•
Located in a prime area, adjacent to auto and auto ancillary
establishments
5.
•
Well developed by internal roads and with a proper laid water network
•
Allowable FSI is 1 as per Development Control Regulations
Genesis for conceptualizing this project
•
In normal course, PCNTDA would have constructed BSUP units through
conventional construction contracts; exposing itself to
•
•
–
Cost overruns – escalations and variations
–
Delayed decision making – time overruns
–
Other issues like QA and QC for limited capacities within its system
JNNURM and Govt of Maharashtra’s support enabled this PPP project
–
MoUHPA funds for 5040 tenements
–
Increase in plot FSI from 1 to 2.5 to exploit real estate potential from Govt of Maharashtra
In addition, PCNTDA addressed its mandate of construction of affordable
housing stock aimed to stabilize the real estate market prices
6.
Project Objective and why private sector
•
Plot had good real estate potential to attract interest from private sector
•
PCNTDA wanted private sector to
–
To bring in project construction and management efficiencies
–
Implement the project on a fast track basis
–
Generate funds for PCNTDAs contribution for BSUP through exploitation of real
estate
–
•
Provide social and physical infrastructure towards integrated development
All packaged in one contract to reduce the risk of exposure to multiple
contracts and fine tuning of cash flows between them
7.
The PPP Structure
8.
The Project
PPP Structure
Process Adapted
Outcome
Project scope for PPP developer
•
Master planning for 53 hectares
•
Construction of common physical and social infrastructure
•
Development, construction and marketing of 7.95 lakh square meters of
integrated real estate space
–
•
Handover a part of it as affordable housing to PCNTDA [Bidding Parameter]
Construction and hand over of 5040 housing units under the BSUP
scheme to PCNTDA,
–
PCNTDA shall pay Rs. 225 crores as grant linked to housing units handover
schedule
9.
Contract Structure
GoI
GoM
Beneficiary
Rs. 75 crs
Rs. 148 crs
Rs. 13 crs
• Lease Rights for 99 years on completion of development milestones
Grant of Rs.
236 crs
• Grant of Rs. 225 crores on completion of development milestones for BSUP units
• Development Rights after approval of Master Plan
PCNTDA
Developer
• Rs. 50 crores upfront payment and Rs. 100 crores performance security
• Completion of 5040 BSUP units within 2 years
Revenues
• Completion of affordable housing units units within 4 years
• Completion of Social and Trunk Infrastructure within 5 years
Sub- Lease
Occupant
10.
Developer’s Key Obligations
•
Upfront payment of Rs. 50 crores
•
Submission of Performance Security of Rs. 100 crores
•
Master Planning and obtaining its approval from PCNTDA
•
Development
and
handover
of
affordable
housing
units
and
infrastructure as per the contract timelines
•
Construction as per Master Plan and Specifications specified in
development agreement
•
Undertaking eco-friendly initiatives part of the agreement
–
Rain water harvesting, use of solar power, environment-friendly materials and vermicomposting
11.
PCNTDA’s Key Obligations
•
Payment of Grant of Rs. 225 crores as per schedule linked to handover
schedule
•
Accept BSUP Facilities/ Affordable Housing units on its completion;
subject to quality specifications as laid out in development agreement
12.
•
Transfer of Lease Rights in phases linked to construction milestones
•
Facilitate clearances of Govt. agencies on reasonable effort basis
Process Adapted by PCNTDA
13.
The Project
PPP Structure
Process Adapted
Outcome
Partnered with Transaction Advisors
• CRISIL Risk and Infrastructure Solutions Ltd.
– In association with Creations and Omkar Associates
• Project development stages comprised of
– Market feasibility studies
– Project conceptualization
– DPRs for JNNURM
– PPP project structuring
– Drafting of development and lease agreements
– Transaction documentation; RFQ and RFP
– Managing the bid process
• Overall strategic support to PCNTDA and Marketing the project to the
private sector
14.
Making the process transparent and attractive to the private sector
• CRISIL adopted a three stage process;
– Assessment of technical and financial capabilities
– Detailed presentation of bidders to Evaluation Committee on master plan
 Committee comprising of Divisional Commissioner ( Pune Division), Collector (Pune )
and Commissioner PCMC
– Selection of successful bidder on an objective bidding parameter
 Highest Carpet area of developed affordable units to be transferred free of cost to
PCNTDA
• Successful Bidder quoted a constructed carpet area of 1,30,599 square
meters of affordable housing units to PCNTDA i.e. 2275 housing units
15.
The Project Outcome
16.
The Project
PPP Structure
Process Adapted
Outcome
The Project Outcome
Type of housing unit created
No. of units
BSUP housing
5040
Affordable housing [Carpet area 53 sqmtr]
1917
Affordable housing [Carpet area 73 sqmtr]
358
Total
7369
1 School and Hospital for BSUP
1 School and Hospital for general public
Other Infrastructure
Physical infrastructure
Development of public amenities and reservations
17.
Other benefits
• Covered cost escalation risk of about Rs. 65 crores
• Variations and other engineering risks
• Developed physical and social infrastructure of about Rs. 120
Crs
• Getting land parcels slum free and making it available for future
exploitation
18.
Key takeaways
•
JNNURM funding was utilized not just for constructing BSUP units but
leveraged for developing an integrated township
–
With schools hospitals and all sections of the society living together
•
PPP helped bridge the funding requirements
•
PPP was enabled by increasing plot FSI from 1 to 2.5 for the Project
•
PCNTDA will handover affordable housing stock for other EWS and
middle income groups
•
All risks of cost-overrun, delays, variations and price escalations were
transferred to the Developer through an efficient contract
19.
Stakeholders’ Experiences
Mr. Dilip Band, Divisional Commissioner, Pune Division says:
“…. This project has elicited valuable private participation and will be instrumental in
providing affordable housing to the poor. We appreciate the efficient and transparent
manner in which CRISIL has executed this process, right from project conceptualization to
selection of the private developer”.
Mr. Rajendra Chourse, Senior Vice- President (Projects), D B Group says: “….
Being one of the bidders, we can say that the PCNTDA tender was well-researched, planned
and structured. The process of PCNTDA tendering from offer to finalization was wellcoordinated, efficiently executed and above all transparent”.
Ms. Anita Arjundas, Managing Director & CEO, Mahindra Lifespaces says:
“… The project concept was interesting. While PCNTDA’s specifications aimed to ensure
that high quality houses are built, higher FSI entitlement aimed to reduce costs, enabling
developers to offer quality affordable housing options to people. The low amount of upfront
payment also helped in view of the current real estate market. CRISIL managed the bid
process efficiently. They were highly responsive to our queries which helped us in putting
our bid together in record time”.
20.
Thank You
21.