Transcript Chapter 1, Heizer/Render, 5th edition
Week #14-2
Operations Management
Material Requirements Planning (MRP) & ERP Chapter 14
Outline
GLOBAL COMPANY PROFILE: COLLINS INDUSTRIES
DEPENDENT INVENTORY MODEL REQUIREMENTS
Master Production Schedule
Bills of Materials
Accurate Inventory records
Purchase Orders Outstanding
Lead Times for Each Component
MRP STRUCTURE
Outline - Continued
MRP MANAGEMENT
MRP Dynamics
MRP and JIT
LOT-SIZING TECHNIQUES
EXTENSIONS IN MRP
Closed-Loop MRP
Capacity Planning
Material Requirements Planning II (MRP II)
MRP IN SERVICES
Outline - Continued
DISTRIBUTION RESOURCE PLANNING (DRP)
ENTERPRISE RESOURCE PLANNING (ERP)
Advantages and Disadvantages of ERP System
ERP in the Service Sector
Learning Objectives When you complete this chapter, you should be able to :
Identify or Define
:
Planning bills and kits Phantom bills Low-level coding Lot sizing
Learning Objectives - Continued When you complete this chapter, you should be able to :
Describe or Explain :
Material requirements planning Distribution requirements planning Enterprise resource planning How ERP works Advantages and disadvantages of ERP systems
Collins Industries
Largest manufacturer of ambulances in the world International competitor 12 major ambulance designs 18,000 different inventory items 6,000 manufactured parts 12,000 purchased parts MRP: IBM’s MAPICS
Collins Industries
Collins requires: Material plan must meet both the requirements of the master schedule and the capabilities of the production facility Plan must be executed as designed Effective “time-phased” deliveries, consignments, and constant review of purchase methods Maintenance of record integrity
Inventory Classifications Process stage Number & Value Raw Material WIP Finished Goods A Items B Items C Items Inventory Demand Type Other Independent Dependent Maintenance Operating
Dependent versus Independent Demand
Item Demand Source Material Type Method of Estimating Demand Planning Method Materials With Independent Demand Company Customers Finished Goods Forecast & Booked Customer Orders EOQ & ROP Materials With Dependent Demand Parent Items WIP & Raw Materials Calculated MRP
Requirements for Effective Use of Dependent Demand Inventory Models
Effective use of dependent demand inventory models requires that the operations manager know the: master production schedule specifications or bills-of-material inventory availability purchase orders outstanding lead times
Production
Capacity Inventory
Inputs to the Production Plan
Marketing
Customer Demand
Finance
Cash Flow
Procurement
Supplier Performance Aggregate Production Plan
Human Resources
Manpower Planning
Management
Return on Investment Capital
Engineering
Design Completion
The Planning Process
Aggregate production plan Change production plan?
Master production schedule Change requirements?
Material requirements plan Change master production schedule?
Change capacity?
Detail capacity plan No Realistic Yes Is capacity plan being met?
Execute capacity plans Is execution meeting the plan?
Execute material plans
Aggregate Production Plan
Months January Aggregate Production Plan (shows the total quantity of amplifiers Weeks Master Production Schedule (Shows the specific type and quantity of amplifier to be produced 240 watt amplifier 150 watt amplifier 75 watt amplifier 1 100 2 1,500 500 3 100 300 4 500 February 5 100 6 1,200 450 7 100 100 8 450
Typical Focus of the Master Production Schedule
Number of end items Make to Order (Process Focus) Assemble to Order or Forecast (Repetitive) Stock to Forecast (Product Focus) Schedule finished product Typical focus of the master production schedule Number of inputs Schedule orders Schedule modules Examples: Print shop Machine shop Fine dining restaurant Motorcycles, autos, TVs, fast-food restaurant Steel, Beer, Bread Light bulbs, Paper
Bill-of-Material
List of components & quantities needed to make product Provides product structure (tree) Parents: Items above given level Children: Items below given level Shows low-level coding Lowest level in structure item occurs Top level is 0; next level is 1 etc.
Product Structure for “Awesome” A
Special Bills-of-Material
Modular bills Modules are final components used to make assemble-to stock end items Planning bills Used to assign artificial parent Reduces number of items scheduled Phantom bills Used for subassemblies that exist temporarily
Bill-of-Material Product Structure Tree Handle Bars (1) P/N 1001 Bicycle(1) P/N 1000 Frame Assembly (1) P/N 1002 Wheels (2) P/N 1003 Frame (1) P/N 1004
Start production of D 1
Time-Phased Product Structure
2 weeks G 2 1 week 3 D Must have D and E completed here so production can begin on B 1 week D 2 weeks to produce 2 weeks B E 2 weeks E 1 week 1 week A 3 weeks C F 4 5 6 7 8
Material Requirements Planning (MRP)
Manufacturing computer information system Determines quantity & timing of dependent demand items
1 2 3 4 5 Gross Requirements 2 20 25 15 Scheduled Receipts Available Net Requirements Planned Order Receipts 5 25 23 30 33 33 8 7 7 Planned Order Releases 7
© 1995 Corel Corp.
MRP Requirements
Computer system Mainly discrete products Accurate bill-of-material Accurate inventory status 99% inventory accuracy Stable lead times © 1984-1994 T/Maker Co.
MRP Benefits
Increased customer satisfaction due to meeting delivery schedules Faster response to market changes Improved labor & equipment utilization Better inventory planning & scheduling Reduced inventory levels without reduced customer service
Structure of the MRP System
BOM Master Production Schedule Lead Times (Item Master File) Inventory Data MRP planning programs (computer and software) MRP by Period Report MRP by date report Planned order report Purchase advice Exception report Exception report Purchasing data
Gross Material Requirements Plan for 50 “Awesome A” Speaker Kits
MRP and The Production Planning Process
Forecast & Firm Orders Aggregate Production Planning Material Requirements Planning Capacity Requirements Planning Master Production Scheduling No, modify CRP, MRP, or MPS Realistic?
Yes Resource Availability Shop Floor Schedules
Master Production Schedule
Shows items to be produced End item, customer order, module Derived from aggregate plan Example
Item/Week Oct 3 Oct 10 Oct 17 Oct 24 Drills Saws 300 300 200 450 310 310 300 330
Derivation of Master Schedule Periods A 5 B Lead time = 4 for A Master schedule for A C 6 40 7 8 50 9 10 11 15 S B C Lead time = 6 for S Master schedule for S 8 9 10 40 11 20 12 13 30 Master schedule for S sold directly 1 2 10 10 3 Periods Gross requirements: B 1 2 3 4 5 6 7 8 10 40+10 = 50 40 50 20 15+30 = 45 Therefore, these are the gross requirements for B
MRP Dynamics
Supports “replanning” Problem with system “nervousness” “Time fence” - allows a segment of the master schedule to be designated as “not to be rescheduled” “Pegging” - tracing upward in the bill-of-materials from the component to the parent item That a manager can react to changes, doesn’t mean he/she should
MRP and JIT
MRP - a planning and scheduling technique with fixed lead times JIT - a way to move material expeditiously Integrating the two: Small bucket approach and back flushing Balanced flow approach
Lot-Sizing Techniques
Lot-for-lot Economic Order Quantity Part Period Balancing Wagner-Whitin Algorithm
MRP Lot-Sizing Problem: Lot-for-Lot Techniques
MRP Lot-Sizing Problem: EOQ Technique
MRP Lot-Sizing Problem: PPB Technique
Extensions of MRP
Closed loop MRP Capacity planning - load reports MRP II - Material Resource Planning Enterprise Resource Planning
Closed Loop MRP
Extensions of MRP Capacity Planning
Tactics for smoothing the load and minimizing the impact of changed lead time include: Overlapping - reduces the lead time, entails sending pieces to the second operation before the entire lot has completed the first operation Operations splitting - sends the lot to two different machines for the same operation Lot splitting - breaking up the order and running part of it ahead of the schedule
Initial Resource Requirements/Smoothed Resource Requirements
Extensions to MRP Enterprise Resource Planning
MRP II with ties to customers and suppliers
MRP and ERP Information Flows, Integrated with Other Systems
MRP in Services
Can be used when demand for service or service items is directly related to or derived from demand for other services restaurant - rolls required for each meal hospitals - implements for surgery etc.
Product Structure, Bill of Materials, Bill of Labor for Veal Picante
Distribution Resource Planning
DRP requires: Gross requirements, which are the same as expected demand or sales forecasts Minimum levels of inventory to meet customer service levels Accurate lead times Definition of the distribution structure