Transcript Slide 1

2012 ARIPPA Technical Symposium
Steam Turbine Generator Maintenance for
Optimized Availability
David Branton, CEO
Turbine Generator Maintenance, Inc.
Steam Turbine Generators
some statistics and history
80% of all electricity in the world is generated by steam turbines driving
electrical generators:

10,632 TWH [terrawatt (1012) hours] – World

3,244 TWH – U.S.

1,485 TWH – China (expected to be 6,560 TWh by 2030)
The first practical steam turbine generator was designed and built by Sir
Charles Parsons in 1884 and generated 7.5 MW. Generation principles
remain the same.
GE’s first production steam turbine generator was introduced in 1901 and
was rated at 500 KW; just two years later a 5000 KW unit went into
commercial service for Commonwealth Edison.
Designing a Maintenance Plan
Requirements
Maximum unit availability
No unplanned outages
Predictable maintenance costs
Options
Maximum efficiency
Maximum power output
Qualitative Tools
Running Assessments
Periodic Minor Inspections
Objective Based Major Inspections
Maintenance Issues
The turbine and generator are the largest single investment in a fossil power
plant and in many manufacturing and refining facilities. Proper maintenance is
required to maintain efficiency (cost of production) and availability (the amount
of time the unit is able to operate).


Efficiency issues

Steam leakage into the environment

Steam path steam leakage

Blade/nozzle erosion/deposits
Availability issues

Lubrication failures

Steam path failures

Control system malfunctions

Protective device malfunctions
Maintenance Planning
Maintenance planning considerations

Steam pressure/temperatures

Type of duty cycle

Speed of turbine and generator

Extraction, backpressure, condensing considerations

Over temperature/pressure operation

Environment of facility

Quality of water/steam

Expectations of plant
There is no “one size fits all” maintenance plan.
Maintenance Planning
Maintenance planning considerations

Major inspections provide opportunities for availability and efficiency improvements
with minimum outage impact if planned properly.

Major Inspection outages can be better scheduled with qualitative rather than
subjective data

Availability of the turbine and generator and reliability of critical auxiliaries
can be optimized:

Periodic Running Assessments combined with data trending and analysis

Periodic minor (3-5 day) outages to inspect critical areas for issues
A combination of Running Assessments and Focused Minor
Inspections can assure availability and optimize major inspections.
Turbine Generator Maintenance
Outage Cycle
Running Assessments
Critical parameters
Vibration/Noise
Turbine inlet temperature fluctuations
Stage performance
Steam chemistry
Bearing temperatures
Pedestal expansion/lubrication/cleanliness
Electrical system grounding
Motor loading
Gland system integrity
Air in-leakage
Lubrication backup integrity
Lubrication cleanliness
Overspeed protection
Generator partial discharge and rotor flux probe
Data must be monitored, collected, trended, analyzed,
and used for outage planning
Running Assessments - Vibration Trending
Running Assessments – Grounding Brushes
Turbine Availability issue
Running Assessments – Oil System Integrity
According to the International Association of Engineering Insurers
• The highest frequency of turbine generator failures in the
10 – 400 mw range has been lube oil incidents
 Dirt and/water contamination
 Loss of oil pressure
Running Assessments – DC Backup
Turbine Availability issue
Running Assessments
Generator Rotor Windings
Shorted Turns in Pole A - Coil 5, Pole B - Coils 6 and 7
Magnetic Wedges in Coil 1 – note small signal
Minor Inspection Scopes
Bearing Inspections – every two years
Critical inspections for availability
Standard Scope should include
Coupling alignment checks
Disassembly and inspection of thrust bearing
- including total rotor travel and thrust clearance
Disassembly and inspection of journal bearings
- including UT and LPT
Oil system including the oil reservoir, pumps/motors, oil coolers
Maintenance oil flush
Backup oil system integrity
Turbine shaft grounding maintenance
Check and calibrate protective devices including overspeed,
bearing temperatures and vibration
Generator borescope and electrical tests
Minor Inspections – Bearing Inspections
Uneven wear
Varnish deposits
Minor Inspection – Electrical Discharge
through the Thrust Bearing
Minor Inspection Scopes
Valve inspections – every two years
Critical inspections for safety, efficiency, and control
Standard Scope should include:
 Disassemble, clean, and inspect steam side
- Include all stop and control valves
- Include all non return valves
- Seat integrity and contact
- Stem and stem seal integrity
 Disassemble, clean and inspect control side
 Check valve set points and travels
 Perform protective systems inspections and calibration checks
 Perform borescope inspections of steam inlet/nozzle
 Perform generator borescope and maintenance tests
Minor Inspections – Valve Inspections
Minor Inspections – Valve Inspections
LP Governor valve seat damage
Outage Implementation Major Inspections
Proper planning can significantly reduce planned outage inspections.
Based on the turbine configuration, a major inspection can be completed in
2 – 6 weeks based on unit size.
The turbine-generator is almost always the critical path, and any generator
maintenance/repair must be placed in the same outage window.
Factors critical to achieving minimum outage durations:
 Planning for the outage should begin after the last major inspection
and developed over a maintenance cycle of Running Assessments
and Minor Inspections. Most turbine and generator replacement parts
can be sourced from non-OEM suppliers with less lead time.

Develop contingency repair plans – identify potential scopes of work,
identify repair resources, and develop repair schedules.

Contract experienced turbine generator teams that understand the
unit and have the skills and tools necessary to handle the anomalies
and with minimum impact to the schedule.
Major Inspection Findings Averting Forced Outage
HP Turbine

Nozzle box movement

First stage rotating buckets

Nozzle migration

Turbine wheel corrosion
LP Turbine
•
Last row blade migration
Generator
•
Rotor winding short
•
Stator core overheating
Major Inspection – Steam Path
Heat shield weld failure in stage 4
Major Inspection – Steam Path
Locking pin failure in rotating stage 1
Major Inspection – Steam Path
Missing seals
Major Inspection – Steam Path
Nozzle migration downstream
Major – Steam Path
Last row blade migration
Major Inspection – Steam Path
Curtis stage severe damage
Downstream side
Upstream side
Steam Turbine Design Types
Advantages and Disadvantages – Reaction vs. Impulse


Reaction designed turbines start out at a higher efficiency – less leakage
Impulse design turbines have fewer stages
Tip Leakage
Root Leakage
Fig. C-F. Reinker, J.K., and Mason, P.B., Steam Turbines for Large
Power Applications, GER-3646D, GE Power Systems, Schenectady, NY.
Major Inspection – Steam Path
Stage efficiency improvement
Major Inspection – Steam Path
Boiler carryover
Major Inspection – Steam Path
Boiler carryover
Major Inspection – Steam Packing
Excessive clearances
Major Inspections – Generator
Stator and core
Major Inspection – Generator
Rotor winding
Major Inspection – Implementation
Outage duration for a major inspection can be optimized by:
• Effective planning – contingency plan development, safety plan, quality plan
• Team implementation – daily reporting and proactive management
• Pre-Qualified personnel – professional, resumes, down to working level
• Defined and organized tools
Conclusions
Steam turbine generators are rugged and with a comprehensive
maintenance program can operate reliably.
Using proper assessment techniques and performing strategic minor
inspections, Major Inspection intervals can be optimized and performed
predictably and cost efficiently.
Proper operation is imperative to maintain the equipment performance
but when anomalies occur, the potential impact must be assessed.
A tailored maintenance program can greatly reduce operating costs by
maintaining efficiency, availability, and reliability.
A planned and well organized outage plan/team can assure on-time
outage duration.