Public Meeting No. 2
McDougall & Cliff Project Area
•
•
•
•
•
•
•
Introduction to Project
Cost and Funding
Project Specific Scope – McDougall and Cliff
Status
Construction
Schedule
Public Involvement
McDougall & Cliff
Presentation Outline
McDougall & Cliff
Lander Streets and Utilities 2015
Costs & Funding
•
•
•
•
1% Optional Sales Tax
Countywide Consensus
Water Fund
Sewer Fund
McDougall & Cliff
• Total Estimated Project Costs $5.49M
• Funding
McDougall & Cliff
McDougall & Cliff Project
McDougall & Cliff Scope
• Full Street Reconstruction
• Pavement
• Curb, Gutter, and Sidewalks
• Driveway Approaches
• ADA Ramps
McDougall & Cliff
• Type A Curb
• 4-ft Wide Sidewalks
McDougall & Cliff Scope
• Utility Replacement
McDougall & Cliff
• Water Mains and Services w/ Curb Stop
• Sanitary Sewer Mains and Services w/ Cleanout
• Gas Utilities – McDougall – Relocate by Source Gas
Project Status
McDougall & Cliff
• 90% Design Presented to City & 1% Committee – March 23rd
• Permitting – Wyoming Department of Environmental Quality and
Wyoming Department of Transportation – Pending
• Final Design Ready for Bidding – April 13, 2015
Construction
• Full Time Inspection & Oversight
• Construction Activities
• Road Closures
• Utility Work - Water and Sewer Crews
• 800 feet at one time
• Trenches will be backfilled or barricaded
• Roadway Work – Milling, Final Grading, Paving
• Entire length
McDougall & Cliff
• One street at a time per project area
• 7am – 6pm, M-F
• No work on holidays or weekends
Construction
• Access During Construction
• Vehicular Access
• Access prohibited for a maximum of 10 hours at a time
• Limited to pedestrian access during these times
• Pedestrian Access Maintained
• Parking
• On street nearby
• FCSD1 parking area off 9th and Sweetwater
McDougall & Cliff
• Open to local traffic – evenings, weekends, and holidays
• Contacted by contractor a minimum of 48 hours prior to blocking access
Construction
• Disruption to Water & Sanitary Sewer Service
• Shutdown Times – Approved by City
• Maximum Allowable Interruption of Service – 10 hours
• Contacted by Contractor a Minimum of 48 Hours Prior to Interruption
of Service
McDougall & Cliff
• Service must be returned at end of work day
• Temporary water service may be required
Construction
• Deliveries
Mail Delivery – Walking Route – No Change
Regular Parcel Delivery – Park and Walk – No Change
Freight Delivery – Coordinate for Access with Contractor
Medical or Other Deliveries - Coordinate with Contractor
• Emergency Access
• LPD, EMS, and Fire – Routine Updates from DOWL & Contactor
• Contractor is Required to Provide Immedidate Access
McDougall & Cliff
•
•
•
•
Construction
• Solid Waste Collection
• Contractor to Collect
• Some impact to activity buses - DOWL to Coordinate
• Those with special needs & others who use a transportation service
will need to coordinate with the Contractor
• Parked Vehicles
• Contractor to provide a 72 hour notice to requesting vehicle be moved
• May request assistance of LPD after 72 hours
McDougall & Cliff
• Bus Routes
Construction
• Mailboxes, Signs, Fences, & Landscaping
• To be removed within construction area and reinstalled
• Small shrubs and bushes in ROW will be removed
• Trees >2” diameter will remain
• Contractor to maintain drainage in and around construction area
• Housekeeping
• Contractor is responsible for cleaning up rubbish, dust control,
cleaning up tracked soil or mud onto existing roads, maintaining roads
during shutdowns
McDougall & Cliff
• Drainage
Schedule
Advertise for Bid - April 19th & April 26th
Mandatory Pre-Bid Conference – April 30th
Bid Opening – May 7th
Award Bid – May 12th
Construction – June – October 2015
McDougall & Cliff
•
•
•
•
•
Continued Public Involvement
Diane L. Oress, PE
Project Manager
[email protected]
307.332.3285
McDougall & Cliff
• Next Meeting – Meet the Contractor
• Weekly Progress Meetings – On Site – Visit with DOWL
• Routine Updates Provided on City Website
www.landerwyoming.org
• Contact Engineer
McDougall & Cliff