Crossrail Central - Logistics - Triangle Management Services

Download Report

Transcript Crossrail Central - Logistics - Triangle Management Services

Crossrail Central - Logistics
Gordon Sutherland
Adrian Boughtflower
Crossrail Central
Traffic co-ordination & Logistics
•
Background
•
Sustainable transport
•
Lorry routes
•
Traffic Co-ordination Centre
•
Lorry Holding Areas
•
Lorry driver training
•
Freight Operators Recognition Scheme
•
Construction
Crossrail Commitments
Environmental Minimum Requirements
(EMR) Annex 1
‘The Construction Code’
4.6 Lorry Controls
•
4.6.1 Approval of local routes to be used by
construction lorries will be sought in accordance
with the requirements of any Act and associated
procedures resulting from the Act ( refer to
Schedule 7 of the Act).
•
4.6.2 As far as reasonably practicable, there will
be no parking of lorries on the highway in the
vicinity of any worksite except in specified
holding areas for lorries waiting to deliver or
remove materials from the site.
•
4.6.3 An appropriate control system will be
implemented for the dispatch of all vehicles
containing excavated material, demolition
materials or other waste material. Waste will be
controlled and deposited in accordance with
relevant legislation.
•
4.6.4 Signs will be displayed in a prominent
position on vehicles on public roads which are
dedicated to the Crossrail project. The signs will
uniquely identify the vehicle to
Transport Planning and Management
Deliveries to worksites restricted to ‘shoulder hours’ each side of core
working hours. This restricts vehicle movements therefore to 07:00hrs to
19:00hrs weekdays and 07:00hrs to 14:00hrs on Saturdays;
Transportation, storage and removal of excavated material by conveyor,
barge and rail wherever practical;
Regular traffic liaison with highway authorities, Police, bus operators and
emergency services;
Application of the materials management hierarchy:
Road Transport Specific
No engines running whilst awaiting loading or off loading;
Specified and approved lorry routes, holding areas and route signage;
A means of monitoring lorry use and those routes prohibited from use;
Wheel washing;
Correct loading and sheeting of vehicles;
A control system for the despatch of vehicles carrying excavated
materials, demolition materials and other waste materials;
Crossrail insignia on vehicles;
Exhaust silencers;
Noise control features on reversing alarms;
Low emission vehicles;
Ultra low sulphur fuels.;
Vehicles free from oil/ fuel leaks.
Undertakings & Assurances
Example General
Commitment 577 – Construction Traffic & Cycles
•
The Nominated Undertaker will provide site
induction for lorry drivers, including a module on
cycle awareness.
Commitment 0187– Schools - lorry routeing Tower
Hamlets
•
The Promoter undertakes that, where a proposed
Crossrail lorry route passes a school that is not
currently subject to heavy goods traffic, he will
restrict the hours during which Crossrail
construction traffic will operate and/or introduce
appropriate traffic management measures to be
agreed with the Council. These measures to
include a 30 minute prohibition of Crossrail
construction traffic when school pupils are arriving
at school and a 30 minute prohibition when pupils
are leaving. The exact hours will be agreed on a
case by case basis with each school. The
Promoter will work with the Council to develop a
strategy for lorry routes that takes into account the
nearby sensitive uses. The Promoter will consult
on the day to day management of lorry holding
sites.
Example Site Specific
Commitment 0739_65 – Liverpool Street Station
Use all reasonable endeavours to give UBS advance notice of
deliveries of plant/materials that would divert or obstruct
vehicular or pedestrian access to the Premises and where
reasonably practicable arrange for such deliveries to take place
outside working hours.
Commitment 0306 – Whitechapel Station
The promoter undertakes that construction traffic will be
prohibited from using Durward Street between the hours of 0815
and 0845 in the morning and 1530-1600 in the afternoon.
Commitment 0453_23 – Farringdon Station
Marshall the parking of Crossrail's vehicles in the vicinity of the
Properties to ensure that access by persons carrying out works
to or business at the Properties on the Developer's behalf and by
tenants/other occupiers of the Properties is not adversely
affected.
Logistics Function
C802 Traffic Co-ordination Centre
-Traffic information
- Contractor vehicle plans
- Lorry Holding Area coordination
LHA
PAD
C803 Signage
-Directional signage
LHA
BO
S
LHA
TCR
LHA
FAR
C806 Wallasea Island
-Construction of jetty
LHA
LI
S
LHA
WHI
C807 Excavated Material
- Movement of spoil from works
LHA
Victoria
Dock
Portal
LHA
Mile
End
Shaft
LHA
Eleanor
St
Shaft
LHA
LHA
Custom
House
Connaught
Tunnel
LHA
N.
Woolwich
Portal
LHA
Plumstead
Shaft
LHA
LHA
ROP
LHA
Fisher st
LHA
C305 Drive G Limmo
C305 Drive Z
to Victoria Dock Portal
Stepney Green to Pudding Mill
Lane
LIMMO
LHA Stepney
C300 Drive x Royal Oak to
Farringdon
Thames Tunnel
LHA
Plumstead
Portal
Green
C305 Limmo to Farringdon
Inston
e
Wharf
Dockland
s Transfer
Site
(C807)
/
Wallasea Island
C806
Excavated Material
RAIL
TRANSPORT
C807 Excavated Material
WATER
TRANSPORT
Fabrication of
Pontoons
and Conveyors
Northfleet
Transfer
Wharf
(C300 &
C310)
Sustainable Transport
• Contractors must produce a Sustainable Transport
Plan, prioritising the use of rail & water (where
practicable)
• Contractors must comply with Crossrail’s sustainability
measures
• Minimise part loads, maximise consolidation
• Support the principles of the London Freight Plan
Sustainable Transport
Sustainable Transport Hierarchy
Lorry Routes
Lorry Routes
Lorry Route Signage
Vehicle Identification
Contractor must ensure that all
hauliers are given and display the
agreed Crossrail identifying sign in
the cabs of all their vehicles.
Traffic Co-ordination Centre (TCC)
• To co-ordinate Crossrail traffic across central London
contracts
• To manage deliveries via the Vehicle Movement
Booking System (VMBS)
• Communication with external parties such as Police,
TfL, local authorities etc, to obtain information on
factors which could affect vehicle movements
Traffic Co-ordination
Vehicle Movement Booking System
• Centralised system used by Contractors and
the TCC
• Used to book future vehicle movements for
each worksite
• Identify individual vehicles and track
compliance with required vehicle standards;
• Monitor and report actual vehicle movements
Process flow – Plan submission
Long Range plan
Weekly plan
Daily plan
Contractor
Enters LR Plan
Contractor
Updates Plan
Contractor
Updates Plan
Plan Submitted
Plan Submitted
Plan Submitted
TCC checks plan
TCC checks plan
TCC checks plan
Objection
raised
Non objection
Objection
raised
Non objection
Objection
raised
Non objection
Final Plan
Resolve w
Contractor
Resolve w
Contractor
Resolve w
Contractor
Escalate if
necessary
Escalate if
necessary
Escalate if
necessary
Sample plan submission dates
November 2010
October 2010
Mon
Tues
Wed
Thu
Fri
Sat
Sun
1
2
3
Week
39
Mon
Tues
Wed
Thu
Fri
Sat
Sun
Week
44
1
2
3
4
5
6
7
Week
40
4
5
6
7
8
9
10
Week
45
8
9
10
11
12
13
14
Week
41
11
12
13
14
15
16
17
Week
46
15
16
17
18
19
20
21
Week
42
18
19
20
21
22
23
24
Week
47
22
23
24
25
26
27
28
Week
43
25
26
27
28
29
30
31
Week
48
29
30
“Today’s” date
Daily plan due - 0900
Weekly plan due
Long Range plan due
Lorry Holding Areas
• Regulates flow of traffic to site
• Vehicle safety checking point
• Reduces the risk of congestion
• Prevents vehicles circulating locally
Lorry Driver Training (LDT)
• A programme designed to train frequent drivers engaged on the
project
• 1 day course, focussing on sharing the road with vulnerable users
(e.g. cyclists); and fuel efficiency (reducing emissions)
• To date approximately 700 drivers have been trained
• Help lorry drivers understand how they can contribute to reducing
the threat of terrorism in London
• Enable Crossrail to demonstrate best practice in construction
road safety
LDT - Scope – Entire Supply Chain
Frequent Drivers
> 5 round trips to a Crossrail
Worksite In a 12 month period
Infrequent Drivers
< 5 round trips to a Crossrail
Worksite In a 12 month period
Driver Induction Training
Driver Induction Pack
Contractor Forecast
• 12 month
• 6 month
• 1 period
• 2 week
Contractor Forecast
• 2 periods in advance
LDT - Course Benefits
• Drivers complete a unique ‘Crossrail Centric’ driver training
course to become a safer driver.
• The course accumulates ‘Driver CPC’ periodic training of 7 hours.
• Employers save on costs associated with 7 hours D CPC
• Drivers gain a greater understanding of the safety issues related
to sharing London’s roads with vulnerable road users.
• Drivers gain an understanding of how they can ‘Contribute to
reducing the Threat of Terrorism’.
• Drivers gain a ‘Crossrail Induction Trained Driver’ certificate and
ID Tag.
• Provides CRL with a clear audit trail and the ability to
demonstrate
• that the requirements behind Undertaking 577 are being met.
Freight Operators Recognition Scheme
(FORS)
• Recognises & rewards excellence
• Raises standards
• Promotes sustainability
FORS
• Contractors must ensure that they and any suppliers
of any tier are registered with TfL’s FORS
• Attain bronze standard as a minimum within 3 months
of contract award
• If not FORS registered, a suitable equivalent standard
of achievement must be demonstrated
Vehicle safety equipment
• Minimum set of safety equipment to be fitted to all
vehicles
• Vehicles > 3.5 tonnes have additional safety
requirements
• Vehicle and Driver Safety Management Plan
• Refer to Works Information Volume 2B Part 26 Section
26.14
Contractor Responsibilities
• Appoint a Logistics Manager with relevant
competencies
• All Logistics activities within the site
• All Logistics activities to deliver the works
• All movement of plant, equipment, materials & people
to and from site
• The removal and treatment of all waste & excavated
material
• Coordination of all logistics activities with others
• Develop, plan and implement logistics solutions to
deliver the works
Contractor’s Logistics Plan
• The Contractor shall;
– ensure the plan is appropriate to all logistics activities included in the
works.
– train all employees, including subcontractors and suppliers of any
tier, with direct or indirect responsibilities under the plan, on the
contents of the plan that apply to its work.
• The Contractor shall review and update the plan to ensure it
remains suitable, adequate and effective as the works progress,
ensure that it reflects the current status of the works and:
– following any material change to the status of the works or Working
Areas that has an impact on logistics requirements;
– as instructed by the Project Manager; and
– at least every 6 months.
• The revised plan shall be submitted to the Project Manager for
acceptance.
Contractor Plans
• Excavated materials
–
–
–
–
Duty of care
Load tracking & compliance management
Waste & recycling
Forecast of daily volumes
• Sustainable transport
– Rail & water
– Hierarchy
• Modularisation & Off-Site Manufacture & Assembly
– Improve site working areas
Contractor Plans
• Consolidation
– Minimise vehicle movements
• Lorry Driver Induction Training
– Training plan
• Freight Operators
– Selection criteria
– Freight Operators Recognition Scheme
Contractor Plans
• Control & Coordination of Vehicle Movements
–
–
–
–
–
–
TCC / VMBS / LHA
Vehicle movement plan
Contingency plan
Training plan
London Lorry Ban permits
Site Traffic Control
• Vehicle Security
– All equipment, plant and materials
• Vehicle Safety Equipment Standards
– Vehicle & driver safety management plan
– Safety equipment
Delivering a world-class
affordable railway safely
through effective partnerships