Garnett Regional Detention Facility:
A Success Story In Managing NAI
With Competing Interests
Brandon Claborn, P.E., CFM
1437 SOUTH BOULDER AVE., SUITE 1080 TULSA, OKLAHOMA 74119 918.392.5620 (P) 918.392.5621 (F) WWW.MESHEKENGR.COM
Population
– 1990 – 11,151
– 2000 – 18,502
– 2008 – 37,328
Recent Development
– 2400 Residential Lots 2002-2009
– Annual Retail Sales:
– $200 Million in 2000
– $550 Million in 2007
CITY OF OWASSO, OK
Location – 11 Miles Northeast of Tulsa, OK
RANCH CREEK BASIN
344 Acres to Proposed Pond
DRAINAGE BASIN
Ranch Creek – Tributary A
1994
1994
2002
2002
2004
2004
2006
2006
2008
2008
EXISTING PROBLEMS
Flooding Downstream of Site
Full Development Upstream
Remove Some Existing Ponds
Sell City Owned Property
Protect Wildlife Habitat
Enhance Quality of Life
GOALS FOR DETENTION
Reduce Flooding Downstream
USACOE versus OKDEQ & EPA
Construction Costs: Developer/City
Park versus Flood Control
Maintenance versus Wetland/Habitat
COMPTETING INTERESTS
Development versus Mitigation
DEVELOPMENT PRESSURE
118 Acres of Undeveloped Property
More Frequent versus Less Frequent Floods
Frequency
1
2
5
10
25
50
100
500
40%PMF
Peak Flow Rate (cfs)
Existing Proposed Reduction
169
160
6%
270
210
22%
480
295
39%
590
330
44%
750
390
48%
845
815
4%
960
745
22%
1425
1390
2%
3800
3455
9%
FLOODPLAIN MITIGATION
Additional Competing Interests
404 Permit
– On Site Meeting Prior to Design
– Second On Site Meeting – Initial Design
Individual 404 Permit Application
– 100% On Site Mitigation
– 4:1 Ratio for Overall Wetland Habitat
401 Certification (OKDEQ)
– Required Additional Off Site Mitigation
Cultural Resources Investigation
Oklahoma Historical Society
PERMITTING ISSUES
CLOMR
Fee In Lieu of Detention
Additional City Planning Required
Negotiate Purchase of Property
CONSTRUCTION COSTS
Sell Existing Detention Facilities
Public Meeting During Design Phase
– Local Residents Expectations
Coordination With City Departments
– Upgrade Sanitary Sewer
– Maintenance Access
– Security (Police)
– Stormwater Quality
GENERAL SITE ISSUES
Neighborhood Meeting
No Adverse Impact
– One Piece of the Puzzle
– Reducing Flooding Is the Easy Part
– Several Competing Interests
– Coordinate City Departments
– Comprehensive Planning Is Crucial
– Leverage Resources
– Work With Developers
– Identify Permitting Needs Early
SUMMARY/RECOMMENDATIONS
Floodplain Management – Developing With
Questions?
Brandon Claborn, P.E. CFM
Project Manager/Associate Principal
[email protected]
1437 SOUTH BOULDER AVE., SUITE 1080 TULSA, OKLAHOMA 74119 918.392.5620 (P) 918.392.5621 (F) WWW.MESHEKENGR.COM