AIM Management Organization

Download Report

Transcript AIM Management Organization

Review of AIM I/II Change
Requests (ACRs)
Ron Zinnato, NAWCTSD, AIM Lead S/W Eng
6 November 2009
Overview
• Summary of approved ACRs in AIM
I/II Rel 5.0
• Other change requests for AIM I/II
received since May 09 meeting
ACRs in Rel 5.0
ACR AIM-II-1998260
ACR AIM-II-1998380
ACR AIM-I-2000014
ACR AIM-I-2000004
Modify AIM I/II to standardize the discussion points for introduction: (Establish
contact, introduce yourself and give any background that might be of interest,
establish readiness, motivating statements, tell the trainer why he or she needs to
know the lesson material, tell the trainee How he will Use the course material, and
Safety) in the front matter of the LP.
Modify both AIM I/II to automatically enter “Unknown” when a unit cost field is blank.
This capability applies to both AIM I/II and to all RRL types that have a Unit Cost
field.
Modify AIM I to have the error message generated when IMPORTING a Training
Path System (TPS) or Course and the system finds a difference when comparing
the contents of 'included PPP tables' with tables currently in the database to include
the location (e.g., the Personnel Performance Profile (PPP) line item number) where
the difference was detected. The import process shall also continue comparing line
items until either the end of the PPP table or differences in 10 line items have been
detected. AIM I shall then terminate the import process and display the expanded
error message.
Development and maintenance of the Exercise Controller Guide (ECG) is currently
not supported in AIM. The Contractor shall implement an ECG Module in AIM I/II as
an option for development following the development of the Training Course Control
Document (TCCD). The ECG shall support the Lesson Plan (LP) or stand alone as
guidance for the instructor and ensure consistency of the learning objectives
throughout curriculum.
ACRs in Rel 5.0
(contd)
ACR AIM-I-2004-002
Linking to folders within the IMI category of the Site RRL in traditional AIM I.
ACR AIM II-2000-485
Change the import function in both AIM I/II to determine if the importing
course exists in importing database earlier in the process than such check
currently occurs. If the course already exists in the importing database, AIM
shall ask the user if he/she wants to replace the existing course.
ACR AIM-II-2008-656
The Contractor shall use the Split Unit/Topic functionality from the COI
screen in AIM II to enable the following functionality:
Use the Split Unit/Topic functionality from the COI screen in AIM II to enable
the following functionality: 1) User clicks on first EO to be joined; 2) clicks on
“Join EO”; 3) a new window comes up that allows the user to select the
applicable EO from the list of ALL EOs (even those from other TOs); 4) user
performs the Join function as usual (possibly more than one at a time)
ACR AIM-II-1999-420
ACR AIM-II-2000-475
Modify AIM I/II to permit the user to associate RIA with Notes or Cautions.
The user shall be able to move lower level DPs created after
Notes/Cautions.
The Contractor shall modify the message in the AIM II CTTL to advise the
user as to which LOs will be affected by selecting Rebuild LOs.
ACRs in Rel 5.0
(contd)
ACR AIM-II-2000-511
Modify AIM I/II to add the capability to update the TCCD with newer info
when the Training Project Plan (TPP) is locked after the first time.
ACR AIM-II-2000-518
Modify AIM I/II to allow the user to remove an RLL from CTTL as easily as it
was added.
ACR AIM-II-2000-525
Modify AIM I/II so that when the user is adding the document name for Job
Sheet input (References), he/she need only double click on the document
block and have the program automatically call up the course RRL.
ACR AIM-II-2001-577
Modify AIM I/II to save graphics in their native file format vs. converting
before saving in the graphics library.
ACR AIM-II-2001-578
The Contractor shall add a notes field to the Manpower section in the TPP
for AIM I/II.
ACR AIM-II-2003-628
Modify AIM I/II to provide users the option to turn Lesson Plan IMI preview
on or off.
ACRs in Rel 5.0
(contd)
ACR AIM-II-2004-642
Modify AIM I/II to create and maintain performance tests.
ACR AIM-II-2006-651
Modify AIM I/II so that the Testing Module Testing Plan allows enough text in
the fields to copy and paste the Testing Plan outline, and Written Progress
Test information from pages 2 - 4 of the 1540C sample package.
ACR AIM-II-2002-614
Develop a document that defines software tools and implementation options
that support TG printing to PDF and support NAWCTSD staff in evaluating
those options with various members
NAVSPECWARCENfunded Requirement
Implement an Associated Curriculum Documents (ACD) Module in AIM I/II
as an option for development following the development of the Training
Course Control Document (TCCD). The ACD shall support the Lesson Plan
(LP) or stand alone as guidance for the instructor and ensure consistency of
the learning objectives throughout the curriculum. The ACD functionality
shall support authoring and administration of high risk training documents to
address NSW unique curriculum documents per paragraph 2.1.3 of this
SOW. The Contractor shall also provide analytical reports on
NAVSPECWARCEN-generated AIM Trouble Reports (TRs) or AIM Change
Requests (ACRs).
ACRs Not Included in Rel 5.0
AIM-II-1998-380
AIM-II-2008-655
When developing a Training Project Plan (TPP) there is a requirement to
enter materials required, including cost per item, for the new or revised
course of instruction. There are instances when it is impossible to
determine the unit cost for a specific item. In these instances the unit Cost
field is left blank. The appropriate AIM system automatically enters $0.00
when the Unit Cost field is blank.
When working with an existing list of CTTL items, it sometimes becomes
necessary to move tasks from one duty to another duty. Currently, that is not
possible without changing duties to tasks, reorganizing the tasks, then
changing certain duties back to a task.
Recommendations: Please allow for the reordering of tasks between duties,
a warning message to alert the user that they are moving a task to another
duty would be appropriate to ensure that the user intends to make that
change.
New ACRs Since May Mtg
• Items reported to Ron Zinnato
• CNATT ACR on AIM II privilege levels
for Central Site – funded by CNATT –
ACR defined in coordination among
Denise Green of CNATT and Steve
Wicinski/Paul Graf of AIM team