Wisconsin Dept. Of Transportation WEMA OCIP Presentation
Download
Report
Transcript Wisconsin Dept. Of Transportation WEMA OCIP Presentation
Wisconsin Dept. Of Transportation
2010 Contractor-Engineer Conference
Damien Barr, ARM-P, CRIS, CSE- Manager
of Risk Management, Wisconsin Department
of Transportation (608) 267-7722
Areas of Discussion
History of WisDOT OCIP’s
Claim Statistics
State of OCIP’s for WisDOT
What WisDOT has learned from using OCIP’s
Unique aspects of WisDOT OCIP’s
History of WisDOT OCIP’s
Marquette Interchange:
$850M in design/construction
Four prime contracts (north leg, south leg, west
leg, core)
Four year construction period
Commitment to completing in 4 years
Complex, multi-level bridge construction
Very high traffic volumes in the work zone
High pedestrian traffic
Rivers
Marquette Safety Record
525 total WC claims
83 claims temporary disability
229 claims medical only
213 GL claims
0 Fatalities
212 GL Claims
104 Compensable
1 Major (MPS Property Damage)
No Catastrophic
No Multi-vehicle collisions
No Deaths
History of WisDOT OCIP’s
I-94 North-South Freeway:
Total Est. project cost 1.9 billion
Construction started in 2009 through projected
2016
Corridor spans about 35 miles
Seventeen service interchanges
Mitchell Interchange Est. project cost 330
million
Mitchell Interchange- Junction with I-43 and I894
History of WisDOT OCIP’s
US-41 Corridor:
Est. total project cost 1.6 Billion
Construction started in 2009 estimated through
2015
Reconstruction of highway
Reconstruction of interchanges
Corridor spans over 31 miles
Construction over water
Railroad exposures
OCIP Claim Summary from
2/1/2009 to12/31/2009
I-94Workers Compensation:
General Liability:
Builders Risk:
41 claims
23 claims
0 claims
US-41
Workers Compensation:
General Liability:
Builders Risk:
8 claims
2 claims
0 claims
Next projected OCIP’s
ZOO Interchange:
At this point of time: Est. total project cost 650
Million
Corridor spans about seven miles
Est. start date of construction ……..?
Unique risks involved- Railroad crossings and
electrical sub-stations
State of OCIP’s for WisDOT
The Project size (Min: 100 Million)
Location
Technical complexity
Risk/Exposures
What have we learned?
OCIP’s are applicable to Highway Construction
OCIPs are still somewhat new/unique to highway
construction contractors
Administration process can be burdensome
Safety and Claims Management is greatly enhanced
Communication and Partnership with contractors is
critical
Unique elements to WisDOT OCIP
WisDOT/WTBA/Contractors partnership:
Established Safety/Risk/Risk management sub-
committees
Established a 4-hours OCIP training program, required
for all supervisory personnel other that the OSHA 10
hour
Safety incident trending meeting with contractors
Quarterly claims meeting open to all contractors
Open ad-hoc meeting between myself/WTBA and
contractors
Unique elements to WisDOT OCIP’s
Drug & alcohol testing (pre-work, random, suspicion, post
accident)
Best practices vs. OSHA
Penalties for non-compliance (Safety and Return to Work)
Return to Work requirements
NCCO certification required for cranes 75 tons or
larger
100% fall prevention/protection at 6 feet
Unique truck driver requirements
Staffing requirements
▪ 1 non-working safety person 30 or more workers combined
▪ 2 non-working safety personnel for 100+ workers combined
Questions?