Transcript Chapter 16

Chapter 16
ADDITIONAL SAMPLING
PROCEDURES
Acceptance Sampling by Variables
ADVANTAGES
•Same operating-characteristic curve can be obtained with a
smaller sample size than would be required by an attributes
sampling plan
•Measurement data usually provide more information than
attributes data
•Finally, when acceptable quality level as are very small, sample
sizes required by attributes sampling plans are very large
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
2
DISADVANTAGES
• Distribution of OC curve must be known. Most standard
plans assume distribution of quality characteristic is
normal. If not then it is assumed that it is, which leads to
serious problems regarding accepting or rejecting of lots.
• A separate sampling plan must be employed for each
quality characteristic that is being inspected i.e f there
are 4 quality characteristics, then 4 sampling plans.
• Possible to reject a lot even though the actual sample
inspected does not contain any defective items
Types of Sampling Plans available
• Two types of variable sampling plans
– Plans that control lot or process fraction
defective, and
– Plans that control the process parameter
(usually mean)
• Consider the first type of plan ,either the LSL
or USL will be defined or both.
• In Fig 16.1 LSL is mentioned, x is normally
distributed, mean is u and SD is 
• SD is known
• We may want to know that the sample
from the lot to determine whether or not
the value of the mean is such that the
fraction defective p is acceptable.
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
7
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
8
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
9
Cautions in the use of variables
sampling:
• Usual assumption is that the parameter of
interest follows the normal distribution
• If parameter of interest is not normally
distributed, estimates of the fraction
defective will not be the same as if
normally distributed
• Difference between estimated fraction
defectives may be large when dealing with
very small fractions defective
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
10
16.3 MIL STD 414 (ANSI/ASQ Z1.9)
• MIL STD 414 is a lot-by-lot acceptance-sampling plan for
variables
• Focal point is the AQL which ranges from 0.04% to 15%
• Five general inspection levels,where level IV is
designated as normal.
– Level V gives a steeper OC curve than level IV.
– When reduced costs are required, or greater risks can be
tolerated than lower levels can be used.
•
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
11
• Sample sizes are a function of the lot size and the
inspection level
• Provision is made for normal, tightened, and reduced
inspection
• Quality characteristic of interest is assumed to be
normally distributed
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
13
Refer to the textbook,
page 678 for Table 16.2
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
14
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
15
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
16
Discussion
• It is not possible to move directly from an attributes
sampling plan in the current MIL STD 105E to a
corresponding variables plan in MIL STD 414 if the
assurance of continued protection is desired for certain
lot sizes and AQLs
• Civilian counterpart of MIL STD 414 restores the match
to attributes plans—that is, ANSI/ASQC Z1.9 is directly
compatible with MIL STD 105E
–
Chapter 16
Makes it possible to start inspection by using an attributes
scheme from MIL STD 105E, collect sufficient information to use
variables inspection, then switch to variables scheme while
maintaining the same AQL-code letter combination
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
17
Continuous Sampling
• All the sampling plans are based on lot by
lot sampling.
• Explicit assumption is that the lots are
formed and then the sample from them is
tested to decide the acceptance or
rejection .
• But there are many manufacturing
processes when that is not the case.
• Two procedures can be used.
– Accumulation of production at a given point in
assembly line. But this may lead to in-process
inventory
– Second procedure marks off the given
segment of the production as lot. But if the lot
is rejected, and 100% inspection is required,
then it will lead to disassembly of semi fnished
products.
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
20
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
21
Chapter 16
Introduction to Statistical Quality Control, 6th Edition by Douglas C. Montgomery.
Copyright (c) 2009 John Wiley & Sons, Inc.
22