Transcript Document

GSRS 2.1 Training Module S.2.6
How to find an Order Line
GSRS Support team
Philips Supply Management
May 29, 2007
Global Supplier Rating System
How to find an Order Line?
• Use the Current month tab to find supplier data for the
current month
 Select “CURRENT MONTH” Tab from the top navigation toolbar
 Select the relevant “Operations” from the drop down box
 Select (A) "view current detail by PO”
or (B) “view current detail by Part”.
If you choose (A), you have to fill in PO and PO line;
If you choose (B), you have to choose a Part number.
 Click on the “View Current Detail” button
 If desired, change the criteria from CLIP to e.g. CVP by clicking in
the sub-category toolbar
Philips Supply Management, GSRS Support team, May 29, 2007
2
Global Supplier Rating System
How to find an Order Line?
Use the Supplier tab to find Order Line results for
previous months:
 Select “SUPPLIER” Tab from top navigation bar
 Drill down “Total Score” for the CTR Supplier
 Drill down “Total Score” for the Supplier you require
 Drill down “Delivery” for the supplier-operation
 Click on the Delivery criteria you require e.g. CLIP
 Select part (12NC) you require
or via 12NC search function
(On the page of KPI, there is a 12NC search box.)
 Select the Line Item i.e. PO Line you require
Philips Supply Management, GSRS Support team, May 29, 2007
3
Global Supplier Rating System
Definitions of Column headers - CLIP
The following definitions refer to the Column headers on the ORDER Detail Screen
for CLIP.
- Week#
indicates the Philips calendar week e.g. 610 refers to year 2006 and week 10
- Manual Update indicates whether a manual update of the data has been made in the GSRS
frontend. This is indicated by an asterix in the row where data has been changed.
This can be clicked on to show the changes
- Day
indicates the date (DD/MM/YYYY)
- Tol. Early
indicates the accepted time tolerance in days earlier than the scheduled date
- Tol. Late
indicates the accepted time tolerance in days later than the scheduled date
- Tol. Over
indicates the accepted quantity over the scheduled quantity
- Tol. Under
indicates the accepted quantity under the scheduled quantity
- Sch. Qty.
indicates the scheduled quantity
- Del. Qty.
indicates the delivered quantity
- Min
indicates the accepted calculated quantity under the scheduled quantity
- Max
indicates the accepted calculated quantity over the scheduled quantity
- Cum Min
indicates the cumulative minimum accepted combined with time and quantity
tolerance
- Cum Max
indicates the cumulative maximum accepted combined with time and quantity
tolerance
- Cum Delivery
indicates the actual cumulative delivery
- CLIP OK/NOK indicates whether the CLIP delivery scores an OK or NOK
- CLIP %
indicates the percentage awarded for the CLIP result
Philips Supply Management, GSRS Support team, May 29, 2007
4
Global Supplier Rating System
Definitions of Column headers - RLIP
The following definitions refer to the Column headers on the ORDER Detail Screen
for RLIP.
- Week#
indicates the Philips calendar week e.g. 610 refers to year 2006 and week 10
Manual Update
indicates whether a manual update of the data has been made in the
GSRS
frontend. This is indicated by an asterix in the row where data has been
changed.
This can be clicked on to show the changes
- Day
indicates the date (DD/MM/YYYY)
- Tol. Early
indicates the accepted time tolerance in days earlier than the requested scheduled
date
- Tol. Late
indicates the accepted time tolerance in days later than the requested scheduled
date
- Tol. Over
indicates the accepted quantity over the requested scheduled quantity
- Tol. Under
indicates the accepted quantity under the requested scheduled quantity
- Sch. Qty.
indicates the requested scheduled quantity
- Del. Qty.
indicates the delivered quantity
- Min
indicates the accepted calculated quantity under the requested scheduled quantity
- Max
indicates the accepted calculated quantity over the requested scheduled quantity
- Cum Min
indicates the cumulative minimum accepted combined with time and quantity
tolerance
- Cum Max
indicates the cumulative maximum accepted combined with time and quantity
tolerance
- Cum Delivery
indicates the actual cumulative delivery
- CLIP OK/NOK indicates whether the RLIP delivery scores an OK or NOK
- CLIP %
indicates the percentage awarded for the RLIP result
Philips Supply Management, GSRS Support team, May 29, 2007
5
Global Supplier Rating System
Definitions of Column headers - OLIP
The following definitions refer to the Column headers on the ORDER Detail Screen
for OLIP.
- Week#
indicates the Philips calendar week e.g. 610 refers to year 2006 and week 10
- Manual Update indicates whether a manual update of the data has been made in the GSRS
frontend. This is indicated by an asterix in the row where data has been changed.
This can be clicked on to show the changes
- Day
indicates the date (DD/MM/YYYY)
- Tol. Early
indicates the accepted time tolerance in days earlier than the order lead time date
- Tol. Late
indicates the accepted time tolerance in days later than the order lead time date
- Tol. Over
indicates the accepted quantity over the scheduled quantity
- Tol. Under
indicates the accepted quantity under the scheduled quantity
- Sch. Qty.
indicates the scheduled quantity
- Del. Qty.
indicates the delivered quantity
- Min
indicates the accepted calculated quantity under the scheduled quantity
- Max
indicates the accepted calculated quantity over the scheduled quantity
- Cum Min
indicates the cumulative minimum accepted combined with time and quantity
tolerance
- Cum Max
indicates the cumulative maximum accepted combined with time and quantity
tolerance
- Cum Delivery
indicates the actual cumulative delivery
- CLIP OK/NOK indicates whether the OLIP delivery scores an OK or NOK
- CLIP %
indicates the percentage awarded for the OLIP result
Philips Supply Management, GSRS Support team, May 29, 2007
6
Global Supplier Rating System
Definitions of Column headers - CVP
The following definitions refer to the Column headers on the ORDER
Detail Screen for CVP
- Week#
indicates the Philips calendar week e.g. 610 refers to year 2006 and week 10
- Manual Update indicates whether a manual update of the data has been made in the GSRS
frontend. This is indicated by an asterix in the row where data has been changed.
This can be clicked on to show the changes
- Day
indicates the date (DD/MM/YYYY)
- Part UM
indicates the unit of measurement for the 12NC part e.g KG = Kilos
- Ordered Qty.
indicates the ordered quantity
- Delivered Qty. indicates the delivered quantity
- Accumulated
indicates the accumulated ordered quantity for that specific day
Ordered Qty.
- Accumulated
Delivered Qty.
indicates the accumulated delivered quantity for that specific day
- CVP%
inicates the calculated CVP% result per day, and also weekly (highlighted in light
blue
Philips Supply Management, GSRS Support team, May 29, 2007
7