Transcript Ring Road Proposal
Ring Road Proposal
PWD
Pune Ring Road
• To avoid traffic a ring road congestion in the city it is necessary to have for Pune.
•Decision taken in the meeting conducted by Hon’ble Chief Minister on 12/06/2007.
•Pune and Pimpri – Chinchwad Municipal Corporation to make necessary provision in their Development Plan.
•PWD to implement the project on BOT basis.
• • • • •
Ring road alignment
Survey of following stretches of ring road undertaken.
Part I – Theurphata NH9, Kesnand, Wagholi, Bhavdi,Tulapur, Alandi, Kelgaon, Chimbli, NH50.
Part II – NH50, Chimbli Moi, Nighoje, Sangurde, Shelarwadi, Chandkhed, Pachne, Pimploli, Rihe, Ghotawde, Pirangutphat.
Part III – Pirangut, Bhugaon, Chandni Chowk, Ambegaon, Katraj.
Part IV – Ambegaon, Katraj, Mangdewadi, Wadachiwadi, Holkarwadi, Wadkinaka, Ramdara, Theurphata, NH9
Proposed Ring road - Map
•
Detail survey
of Part I , II and IV
completed.
• Presentation was made on 19.04.2008. As Part III and IV are very close to the city limits considering rapid growth of city •
Revised Alignment
google earth images for Part III & IV is considered.
based on toposheets and
Alignment Details
Part I Theurphata NH9, Kesnand, Wagholi, Bhavdi,Tulapur, Alandi, Kelgaon, Chimbli, NH50.
39.89 km Part II Part III Chimboli phata to Nighoje to Sangurde, Shelarwadi, Shirgaon, Chandkhed, Pimploli, rihe, Ghotawde, Pirangutphat.
Pirangut, Urwade, Mutha Bahuli, Sangrun, Nigde, Khamgaon, Ghera Sinhgad, Kalyan, Kondanpur, Shriramnagar 46.40 km 51.20 km Part IV NH4 , Gogalwadi, Patharwadi, Bhivri, Kanifnath, New Mula – Mutha canal, Theurphata, NH9 32.24 km After the alignment of Part III & IV is finalised work will be undertaken.
detail survey
Acquisition Proposed
• Ring road length • Land Acquisition cost 169.73km
Rs. 2374.00 crores • • Construction cost Total cost Rs. 6065.00 crores Rs. 8439.00 crores .
• Satelite townships in 38.38km stretch in balance width of 200m (expected area 8,25,93,760 sq.ft) – by giving FSI of 1.0 + additional 1.0
= 2.0 the expected revenue Rs. 9228.00 crores .
Approx. estimates
• Acquisition length – is proposed for 38.38km length – 100m width and 10.44km length – 300m width, 121.12km 45 to 60m.
• Acquisition cost Rs. 2374 crores.
• Construction cost – Rs. 6065 crores.
• For the stretch of 38.38km road length acquisition is proposed for 300m width and the width balance after that required for road i.e. 200m will be developed with additional FSI of 1.0
over and above existing 1.0 FSI to make the project financially viable.
• State Govt. to approve the project on concession of extra FSI.
a PPP model without toll alongwith
Details of Ring road
1 1 2 3 4 Name of the Road Length in m 2
¦Part I –
Theurphata, NH9, Kesnand, Wagholi, Bhavdi, Tulapur, Alandi, Kelgaon, Chimbli, NH50
¦Part II –
Chimboliphata to Nighoje to Sangurde, Shelarwadi, NH4, Shirgaon, Chandkhed, Rihe, Ghotawde, Pirangut.
Part III –
Pirangut, Urwade, Mutha Bahuli, Sangrun, Nigde, Khamgaon, Ghera Sinhgad, Kalyan, Kondanpur, Shriramnagar.
Part IV –
NH4, Gogalwadi, Patharwadi, Bhivri, Kanifnath, New Mula – Mutha canal, Theurphata, NH9 3 39.89
46.400
51.200
32.240
169.940
160 1850 500
3160
Flyovers Road Length in m 4 650 Railway length in m Majo r bridg es lengt h in m Mino r bridg es lengt h in m Viad ucts bridg es lengt h in m 5 300 6 490 7 450 8 200 150
650
850 1520
2860
300 300 150
1200
3070 2250
5320
Under pass length 9 1260 10 630 90 980 120
2960 120
Tunnel s length in m Elevat ed road 11 12 2750 Land Acquisition 100 m width area in hectare s 13 355 300m width road area in hectares 14 132 650 2928 8050 3490 1200
11628 7440
242.6
425 203.00
55.70
1281.4
695.8
255.00
45.00
1116.8