SuperConference Pre-Arbitration Disputes
Download
Report
Transcript SuperConference Pre-Arbitration Disputes
th
6
INTERNATIONAL
CONFERENCE
6/7th May 2006
Budapest
Dispute Boards – A new force to
be reckoned with in international
construction. A brief overview
Peter Chapman
[email protected]
© PHJ Chapman 2006
Recognised methods of dispute
resolution in construction
Party negotiation (with or w/o facilitation)
Mediation/Conciliation
Adjudication
Dispute Boards
(early and ‘real-time’ dispute
avoidance/resolution)
Arbitration
Litigation
© PHJ Chapman 2006
Dispute Boards – a new force
Job site ‘adjudication plus’ process
Members independent and impartial
Appointed from the start
Part of the construction process
Not an ‘add-on’ or ex post facto device
Real-time influence on the project
© PHJ Chapman 2006
Dispute Boards – a new force
Publishes decisions – coercive
Jurisdiction by contract and maybe under
statute
Construction industry but others also
Long shadow, omnipresence – influences
behaviour
Dispute AVOIDANCE
© PHJ Chapman 2006
Dispute Boards
International Adjudication
3 principal areas of activity: Contracts developed for International
Projects financed by World Bank (WB) or
other Multilateral Development Banks
Contracts developed by the International
Federation of Consulting Engineers (FIDIC)
International Chamber of Commerce (ICC)
© PHJ Chapman 2006
Some history of the DB process
WB promoted a Dispute Board on El Cajon
hydro project in Honduras in 1980
DB resulted in successful settlement of
disputes – WB grew to favour this approach
1995 – WB Standard Bidding Document
published that used modified FIDIC
conditions – deleted the usual provision of
the “Engineer” deciding disputes, giving this
task to a Dispute Review Board (DRB), similar
to those being used at the time in USA
© PHJ Chapman 2006
History (cont’d)
Disputes (that could not be settled
by the parties themselves) to be
submitted to DRB for a written
“recommendation” which, if no
objections within 14 days, became
final and binding
In case of objections, parties free to
negotiate or, ultimately, “appeal”
© PHJ Chapman 2006
History (cont’d)
WB required all borrowers of >US$50m to
establish a three-man DRB by contract
Borrowers of between US$10m - $50m could
use a one-man board or Dispute Review
Expert (DRE)
Other development fund banks, followed this
example
WB retained these provisions until 2000
© PHJ Chapman 2006
FIDIC –International Federation of
Consulting Engineers
Known as publishers of model forms used
for construction internationally
1995 – Design-Build Turnkey form
published with a Dispute Adjudication
Board (DAB) – (3 man or 1 man board)
empowered to decide disputes referred
by either party
NB “Decisions” were made interim
binding i.e., coercive, not merely
persuasive
© PHJ Chapman 2006
FIDIC (cont’d)
1999 – Three major FIDIC model forms published,
all involving DABs/DREs:
– Red Book: Conditions for Construction –
standing DAB (3 man or 1 man)
– Yellow Book: Plant & Design Build – ad hoc
DAB
– Silver Book: Engineer Procure & Construct
(Turnkey) – ad hoc DAB
© PHJ Chapman 2006
FIDIC (cont’d)
Standing Dispute Boards, from the
outset, brings the benefit of dispute
avoidance by their routine operations
Ad-hoc boards formed only when
disputes arise – (apparently) justified by
the “design & manufacture” element
not giving rise to so many disputes
© PHJ Chapman 2006
World Bank makes changes
2000 – New edition of Procurement of Works
which makes the “recommendations” of the
DRB or DRE coercive unless modified by the
award of an arbitrator
2005 – WB (on behalf of all development
banks) engaged FIDIC to draft and publish a
harmonised set of conditions for use in
connection with all projects funded by the
World Bank and other lending institutions.
Determinations by the DB are coercive.
© PHJ Chapman 2006
ICC –
International Chamber of
Commerce
2002 – Task Force prepared draft rules for
Dispute Boards.
Choice of 3 types available for users of ICC
documents:– World Bank “old” style DRB –
recommendations being persuasive only
– FIDIC / WB “new” style DAB – decisions
interim binding
© PHJ Chapman 2006
ICC (cont’d)
Combined Dispute Board (CDB)– issues
recommendations (persuasive, not
immediately binding) BUT if requested by
either party or if the CDB itself believes
that a coercive decision is essential for
the good performance of the project the
CDB can issue a decision that is
immediately binding.
© PHJ Chapman 2006
Europe
Significant procurement of EU/ EIB /
EBRD / WB funded works utilising the
1999 FIDIC forms of contract and thus
requiring the establishment of DABs
Traditional procurement
Build and Construct
Concession Contracts
© PHJ Chapman 2006
Dispute Boards – a new force
Average 50% of all legal costs in construction
industry are dispute related
In 10% projects 10% of total project costs
was legal cost.
Plus hidden costs such as commercial
injuries, reputation, executive time and lost
opportunities. A better way for the future?
© PHJ Chapman 2006
Dispute Boards – a new force
Early resolution makes good sense for all
parties as it creates CERTAINTY
Dispute board unique in providing a forum
for regular, real-time, senior-level
discussions of matters of concern to parties
or supervisors leading to the avoidance of
disputes.
Development of trust and confidence in the
members of the dispute board vital to
success.
© PHJ Chapman 2006
Dispute Boards – a new force
One, three or more members
All members acceptable to both parties
Default mechanisms – FIDIC, ICE lists
Balanced board, technical/legal
Multi-contract boards, wider panels,
specialist boards, standing ‘industry’ boards.
© PHJ Chapman 2006
Dispute Boards – a new force
Routine visits ensure a forum for discussion,
ensures board is conversant with the project
and can thereby act with alacrity,
confidence and full background knowledge
No need to recreate historical events – the
DB has ‘looked down the hole’ and has the
contemporaneous information it needs
The magic of the dispute board comes from
its early involvement and by its stimulation
of project communication
© PHJ Chapman 2006
Dispute Boards – a new force
Do they work?
98% of referred disputes end with the DB
Of the 2% remaining, half of the ‘appeals’
uphold the DB decision.
Of the 1% upset by the arbitrator/courts,
almost always due to procedural irregularity,
not on the substance of the decision
PLUS dispute avoidance value
© PHJ Chapman 2006
Dispute Boards – a new force
Reality prevails – self imposed reality checks
by parties
‘Duals of Egos’ reduced
Fewer spurious claims advanced
Less acrimonious correspondence exchanged
Attitudes remain more positive
Behaviour controlled
© PHJ Chapman 2006
Dispute Boards – a new force
Swings and roundabouts pragmatism
Fantasies do not turn into expectations
Cash-flow benefits and final cost certainty.
Programmes can be adjusted and agreed
Face saving dispute settlement that has spinoff value throughout contract/project
Prevents a blame culture developing
© PHJ Chapman 2006
Dispute Boards – a new force
Misconceptions:
Why pay? – may not be needed. Insurance
policy, dispute avoidance, less than 0.2% of
project cost on a medium size contract.
Why encourage claims – quite the reverse.
Issues settled, many DB contracts with no
formal disputes referred
© PHJ Chapman 2006
Dispute Boards – a new force
But it is not final – no, but usually it is.
Don’t pay retainers – just compare the costs
of bringing an arbitral tribunal up to speed
and that of retaining a dispute Board
Many owners after reluctantly using a DB on
a major project will thereafter encourage
future use (Boston Central Artery, Ertan
HEPP)
© PHJ Chapman 2006
Dispute Boards – a new force
You
know it makes sense!
© PHJ Chapman 2006